*This is an unreported opinion and therefore may not be cited either as precedent or as
persuasive authority in any paper, brief, motion, or other document filed in this Court or any
other Maryland court. Md. Rule 1-104.
Circuit Court for Worcester County
Case No. C-23-CV-20-000034
UNREPORTED
IN THE COURT OF SPECIAL APPEALS
OF MARYLAND
No. 921
September Term, 2021
______________________________________
WICKED PROFESSIONAL SERVICES INC.
v.
DANIEL HOLLAND, ET AL.
______________________________________
Kehoe,
Leahy,
Friedman,
JJ.
______________________________________
Opinion by Leahy, J.
______________________________________
Filed: November 3, 2022
Unreported Opinion
This appeal and cross-appeal arise from a custom home construction contract
dispute. Laura and Daniel Holland, appellees/cross-appellants, contracted with Wicked
Professional Services, Inc. (WPS), appellant/cross-appellee, a home building company
owned and operated by Donald Littleton, for the construction of a new home on land
titled in the name of their limited liability company, Chesapeake Bay Land Company,
LLC (Chesapeake). The Hollands filed suit against WPS for breach of contract and
related claims, and WPS filed a counterclaim and a third-party complaint against
Chesapeake, asserting claims for breach of contract, unjust enrichment, and related
claims. The claims, cross-claims, and third-party claims were tried to the court over one
day. The trial court ruled in favor of the Hollands on their breach of contract claim,
awarding them $57,853.46 in damages, but against them on their claim for breach of the
Maryland Custom Home Protection Act (MCHPA), Maryland Code, (1974, 2015 Repl.
Vol., 2017 Supp.), Real Property Article (RP), §§ 10-50110-509. The court entered
judgment against WPS on its counterclaims and third-party claims.
On appeal, WPS presents four questions,
1
which we have consolidated and
rephrased as two:
1
The questions as posed by WPS are:
1. Did the [c]ourt err by finding the written proposal to control when the
Hollands pled that the contract was not a written contract?
2. Assuming that the proposal was fully signed and delivered to WPS, did the
court err by simply voiding paragraph 28 of the proposal without trying to
reconcile the provisions of the document, or using extrinsic evidence and
course of conduct to interpret its terms?
(Continued)
Unreported Opinion
2
I. Did the circuit court err by determining that the parties had entered into
a written construction contract and that WPS breached that contract?
II. If the written contract is binding, did the circuit court err by not
enforcing paragraph 28 of the contract, which provided for WPS to
receive a construction management fee?
In their cross-appeal, the Hollands challenge the trial courts decision not to award
attorneys fees under the MCHPA, and ask: Does the [MCHPA] apply to the
construction of a single family dwelling for a married couple on land owned by the
couples limited liability company?
We hold that the circuit court did not err in determining that the parties entered
into a written contract that established a fixed total price for the construction of the
Hollands home, and that WPS breached the contract when it demanded money above
and beyond the total price as a condition to completing the work. We also hold that the
court did not err, based on the evidence in this case, in ruling that the Hollands were not
obligated to pay WPS a construction management fee.
3. Did the [c]ourt erred [sic] by finding the proposal controlling for the
construction of the plans dated January 18, 2018[?]
4. Did the [c]ourt err, given the course of conduct of the parties during the
term of the construction contract, in failing to have change orders, by
allowing changes by the Hollands (including expansion of the project by
more than 2000 square feet of construction), by rejecting charges for
additional work by WPS, and failing to consider the Unjust enrichment of
[Chesapeake] thereby?
Despite including an unjust enrichment theory in its fourth question, WPS does not
present any argument on this issue in its brief. Consequently, that issue is not before us.
See Beck v. Mangels, 100 Md. App. 144, 149 (1994) (declining to address issues raised
by the appellant, but on which no argument was presented); Md. Rule 8-504(a)(5)
(requiring a party to present “argument in support of the party’s position”).
Unreported Opinion
3
On the cross-appeal, however, we conclude that the circuit court erred in ruling
that the MCHPA did not apply in this case. Accordingly, we shall vacate the denial of
the Hollands request for attorneys fees under Count III of the amended complaint and
remand for the circuit court to hold additional proceedings to determine whether the
contract violated the MCHPA, and if so, whether an award of attorneys fees under the
MCHPA is justified.
BACKGROUND
Since 2011, the Hollands, through Chesapeake, have owned and managed
Chesapeake Bay Dairy, a dairy farm located at 3847 Whitesburg Road in Pocomoke City
(the Property), which previously was owned by Mr. Hollands parents family business.
For many years, the Hollands lived in an existing farmhouse on the Property. In 2017,
they contracted with David Quillen, an architect, to design a Proposed New Holland
Residence to be built on the Property. Mr. Quillen drew up plans, dated May 4, 2017,
for a 3,912 square foot custom home.
Contract Negotiations
In late May or early June 2017, the Hollands were introduced by their pastor to
Mr. Littleton, who owns and operates WPS. Initially, the Hollands asked WPS to
construct the shell of the house for them and make it watertight, with the expectation
that they would finish the inside over time. Mr. Littleton emailed Ms. Holland on June 7,
2017 with a costs and materials proposal, with a total cost of $249,500 to construct the
house, which was then planned to be built on a concrete slab except for a 400 square foot
Unreported Opinion
4
basement room. He stated that the pricing in the email included material & labor, but
that he would try and get things done cheaper
2
if he could. Any savings would be
passed on to the Hollands and WPS would charge a 10 percent management fee for
scheduling and getting this project done on [sic] a timely manner [within] the budget[.]
By June 20, 2017, the Hollands had advised WPS that they wanted him to
construct and finish the house, and Mr. Littleton sent them a new proposal by email. In
that email, Mr. Littleton estimated a total cost of $665,750 if the Hollands separately
contracted for the well, permits, site work, and digging for the mason. He estimated a
total cost of $700,250 for him to do the whole project but added that he would try to get
them better pricing as we go along.
The Hollands decided to hire WPS to construct their home, soup to nuts[.]
According to Mr. Quillens contemporaneous notes from a July 7, 2017 meeting between
him, the Hollands, and Mr. Littleton, WPS would be doing the project as a mix between
a [general contractor] and a [construction manager]. Mr. Littleton would giv[e] [the
Hollands] a not-to-exceed number in the contract, but will also show them bids for subs.
The Contract
On July 24, 2017, WPS emailed Ms. Holland a Construction Contract created
from a template available on the website rocketlawyer.com (the Contract). WPS
agreed to begin providing services to the Hollands on September 4, 2017. Specifically, it
2
The emails from WPS are written in all uppercase letters. For ease of reading, we
use sentence case capitalization.
Unreported Opinion
5
would CONSTRUCT A CUSTOM HOME IN ACCORDANCE WITH PLANS AND
SPEC SHEETS DESIGNED BY DAVID QUILLEN THE ARCHIETECT [sic] WITH
PLANS DATED MAY 4TH, 2017 JOB # 1608. Under section 2 of the Contract, WPS
would provide all services, materials and labor for the construction of the house, but
was not responsible for the driveway, the well, clearing the lot, or the geothermal system,
unless otherwise written on a change order to be approved by all parties involved. The
Hollands agreed, in section 3, to make the plans, specifications, and related construction
documents available to WPS. In section 5, the Hollands warrant[ed] that they owned
the Property and were authorized to enter into the contract.
WPS agreed, in section 6 of the Contract, to provide to the Hollands a List of
each and every party furnishing materials and/or labor to [WPS] as part of the Services,
and the dollar amounts due or expected to be due with regards to provision of the
Services herein described. That list was to be attached to the Contract as Exhibit A.
Section 7 governed the terms of payment. The Hollands agreed to pay [to WPS]
the total sum of $700,250.00 under a specified draw schedule. That schedule provided
for six payments tied to specific events, with the first payment due upon signing the
Contract and breaking ground and the final payment due when a certificate of occupancy
was issued by the building department.
Unreported Opinion
6
WPS agreed to begin construction within 30 days of September 4, 2017, and to
complete the work by May 16, 2018, with time being of the essence.
3
Section 9 provided that modifications to the scope of the Contract only could be
made by written Change Order, which is signed and dated by both parties. If a
change order was executed, it would be become part of the Contract and the Hollands
agreed to pay any increase in the cost of the Construction work resulting from a change
order. Likewise, any other modifications to the Contract were required to be made in
writing, signed by both parties. ¶ 24.
The indemnification clause contained in section 13 provided, in relevant part:
With the exception that this Section shall not to be [sic] construed to
require indemnification by [WPS] to a greater extent than permitted under
the public policy of the State of Maryland, [WPS] may agree to indemnify
[the Hollands] against, hold it [sic] harmless from, and defend [the
Hollands] from all claims, loss liability, and expense, including actual
attorneys fees, arising out of or in connection with [WPS]s Services
performed under this Contract.
So, it appears that the Contract permitted, but did not require, WPS to indemnify
and defend the Hollands against claims, losses, liability, and expense arising from its
provision of services under the Contract.
3
Time is of the essenceis a term of art in contract law. 15 Richard A. Lord,
Williston on Contracts § 46:2 (4th ed. 1998) (Meaning of "time is of the essence"). It
requires strict adherence to the time designated for performance. When time is of
the essence” is included in a contract, time is such a material matter that strict compliance
by performance within the specified periods of time is a prerequisite to the right to
require performance by the other party. Granados v. Nadel, 220 Md. App. 482, 489, 104
A.3d 921, 925 (2014) (citations omitted).
Unreported Opinion
7
Events of material default were defined in section 18 to include a failure to make
a required payment when due by the Hollands and a failure to perform the construction
services by WPS.
An integration clause in section 22 provided:
This Contract contains the entire Contract of the parties, and there are no
other promises or conditions in any other contract whether oral or written
concerning the subject matter of this Contract. Any amendments must be
in writing and signed by each party. This Contract supersedes any prior
written or oral agreements between the parties.
Section 28, entitled Additional Provisions, specified that WPS would
RECEIVE A MINIMUM OF TWELVE PERCENT CONSTRUCTION
MANAGEMENT FEE FOR ALL ASPECTS OF CONSTRUCTION ON THE
HOLLAND PROJECT.
Mr. Littleton signed the Contract electronically, on behalf of WPS, on July 24,
2017. According to Ms. Holland, she and her husband later met with Mr. Littleton and
went over a hard copy of the Contract very specifically. The Hollands then signed the
Contract.
The Construction Loan
Meanwhile, the Hollands, on behalf of Chesapeake, applied for a $600,000
construction loan through First Shore Federal bank (FSFB). The loan was approved on
January 11, 2018 and was secured by a deed of trust on the Property. Chesapeake Bay
Land Company, LLC was named in the Construction Agreement securing the loan as
Owners [sic] and that document stated that it was the borrower on the loan. Faith
Unreported Opinion
8
Bissonette, supervisor of the servicing division at FSFB, created a draw schedule
reflecting six payments split between Chesapeake and FSFB triggered by completion of
various phases of construction. It reflected that the total cost of improvements was
$700,250. Of that amount, Chesapeake already had paid $19,000 directly to Shore
Lumber and for a building permit and would owe $81,250 in installment payments.
FSFB would pay the remaining $600,000. The draw schedule later was revised in April
2018 to reflect the following six payments: 1) $100,250 when the foundation was
installed ($4,330 by Chesapeake and $95,920 by FSFB); 2) $115,000 when the subfloor
and framing was complete and the survey was received ($10,188.80 by Chesapeake and
$104,811.20 by FSFB); 3) $115,000 when the house was sheathed and wrapped,
windows were installed, and rough-ins were in progress ($16,468 by Chesapeake and
$98,532 by FSFB); 4) $131,000 when insulation and drywall was complete, siding
installed, and appliances ordered ($18,759.20 by Chesapeake and $112,240.80 by FSFB);
5) $120,000 when drywall, paint, and trim were complete, and cabinets and countertops
were ordered ($17,184 by Chesapeake and $102,816 by FSFB); and 6) $100,000 when a
certificate of occupancy was issued and inspections completed ($14,320 by Chesapeake
and $85,680 by FSFB).
The Hollands signed the revised draw schedule on April 18, 2018, and Mr.
Littleton signed it, on behalf of WPS, on May 4, 2018.
Unreported Opinion
9
Revision of the Plans
The Worcester County Department of Development Review and Permitting (the
County) a building permit on November 18, 2017. The applicant on the permit was Mr.
Littleton and the owners were listed as Chesapeake Bay Land Company, LLC [and]
Laura Holland[.] By the end of that month, however, the Hollands, at the suggestion of
Mr. Littleton, had decided to forgo their original plan to construct their home on a
concrete slab with one small basement room and, instead, elected for WPS to construct a
full basement. On December 6, 2017, they met with Mr. Littleton and Mr. Quillen to
discuss this change. According to Mr. Quillens contemporaneous notes, Mr. Littleton
advised that this change would only add[] $10,000 to the cost.
Mr. Quillen drafted revised plans, dated January 22, 2018, to reflect the addition
of the basement and other changes to the house. On that date, WPS filed a revised permit
application with the County and a new permit on February 2, 2018. The permit revision
application states that the proposed revision will Enlarge basement area for additional
living space and that the estimated construction cost was $10,000. Mr. Littleton signed
the application and affirmed that he was duly authorized to make [the] permit
modification application on behalf of Chesapeake Bay Land Company, LLC and that
the work proposed was authorized by the property owner.
Construction of the House
WPS began work on the project in January 2018, after the loan was funded. The
progress initially was slow because of rainy conditions that delayed the digging of the
Unreported Opinion
10
basement. By May 4, 2018, the foundation was completed, and FSFB released the first
draw.
By July 2018, the house was pretty much under roof, and Ms. Holland asked
Mr. Littleton for a list of allowances for fixtures and finishes so that she could pick out
items. On July 23, 2018, Mr. Littleton sent her a list of allowances totaling $192,000,
specifying the maximum amount she could spend within budget on items including
windows and doors, kitchen cabinets, appliances, countertops, shower tiles, and other
items. Ms. Holland met with Mr. Littleton at various distributor show rooms to pick out
items, such as tile and appliances. She was not always advised of the pricing, but
throughout the process, she confirmed with him that they were on budget.
FSFB and the Hollands released the second and third draws on August 22, 2018
and September 15, 2018, respectively.
Ms. Holland met with Mr. Littleton at Shore Appliances in October 2018 to select
appliances, agreeing to pay extra for a high-end range. Mr. Littleton stated that he would
return the next day to give the appliance store a certified check for the appliances. In
fact, he did not do so at any time during the project.
The fourth draw was due after insulation and drywall were complete, siding
installed, and all appliances ordered. FSFB sent an inspector to the Property at the end of
November 2018 to determine if the fourth draw could be released. He reported to Ms.
Bissonnette that, although insulation was complete, and drywall had been started, siding
was not installed, and no siding materials were on site. Ms. Bissonnette relayed this
Unreported Opinion
11
information to Mr. Littleton and asked him to provide her with a copy of the appliance
orders he told her had been made so that she could reimburse him for that amount until
the remainder of the draw was released. Mr. Littleton did not provide proof that he had
ordered appliances. He responded that the stucco siding would not be completed until the
end of construction and that he had done considerable work that was not accounted for in
the draw schedule. Ms. Bissonnette asked the Hollands if they would approve release of
the fourth draw based upon Mr. Littletons representations, and they agreed. The draw
was paid on December 3, 2018.
The fifth draw, payable when drywall, paint, and trim were complete and the
cabinets and countertops were ordered, was paid in two installments, the last of which
was paid on July 8, 2019.
Payment Dispute
On the night of July 17, 2019, Mr. Littleton sent an email to Ms. Holland with the
subject line, Payments Needed to Help Project Along. He stated:
Do [sic] to the weather this job has been held up alot [sic] of months. At
which we keep accumalating [sic] bills for the construction of this custom
home with equipment and other delays to the contractors.
At this time funds are really tight on the house. I have all the bills and paper
work at my accountants [sic] office being put on a spread sheet so you can
see where we stand. I really need to collect from you is [sic] your portion
on draw # 6 please which is $ 14,320.00.
Also, we have been paid by you and the bank the sum of $581,250.00.
Wicked Professional management fee on the monies above is $58,125.00.
I really need to collect $29,062.00 of this please.
I will be bringing all trades back now that flooring is almost complete.
From Monday on Ill be there running everybody to get this house turned
over for inspection.
Please call with any questions anytime tomorrow.
Unreported Opinion
12
Ms. Holland responded by requesting a copy of the spreadsheet in advance of the
meeting so that she and her husband could go over it with him and there would be no
surprises.
On July 25, 2019, WPSs accountant forwarded Ms. Holland a spreadsheet. It
reflected that the project would cost $1,075,102.30, nearly $400,000 over the budget. It
showed that WPS had paid nearly $800,000 out of pocket already.
Three days later, Mr. Littleton emailed Ms. Holland, advising that he had been
trying to contact her about finishing the house. He understood that the spreadsheet was
more than a bomb went off[.] Ms. Holland responded that the information he had sent
her was shocking given that she had stressed from the beginning that [she] had to stay
on budget and asked him to keep her informed. She emphasized that this was the first
time she was learning that the budget was not on target. Ms. Holland stated that she
did not want Mr. Littleton to do any more work until they sat down to discuss matters
because she could not afford the overages.
Mr. Littleton responded that he had to keep working because he needed the final
draw payment given that he had put in more money than he had been paid. He
apologized that it got away from [him,] explaining that [i]t was to[o] much going on at
one time.
The Hollands met with Mr. Littleton at the Property on August 7, 2019. He
brought with him copies of the supporting documentation for the data in the spreadsheet.
Unreported Opinion
13
He asked the Hollands for more money to finish the job, but they told him they needed to
review everything first.
After the meeting, Mr. Littleton sent several emails to the Hollands requesting
payment of the 12 percent management fee on the amounts already paid by the Hollands
and FSFB. By August 30, 2019, he gave them an ultimatum, stating that if he did not
receive a check of some sort by Tuesday, September 3
rd
[,] 2019, he would have to cease
all work on the project.
On September 3, 2019, the Hollands contacted WPS through counsel, advising
that they disputed that any further funds were due to him until such time as a certificate
of occupancy was issued. A month later, WPS responded through counsel that work
continued on the project and that the contract amount had been modified by agreement
when the Hollands selected numerous upgrades. Counsel maintained that aside from the
upgrades, the contract explicitly provided for a 12 percent management fee and suggested
that if the Hollands would pay that fee on the amounts already paid, which it calculated to
be $72,000, that should be sufficient to get this moved along quickly.
The Hollands, through counsel, disputed that the management fee was a valid
charge and, in the alternative, maintained that it would not be due until the project was
complete and passed inspection.
In October and December 2019, two WPS subcontractors filed mechanics lien
actions against Chesapeake. On January 21, 2020 and March 17, 2020, respectively,
Unreported Opinion
14
interlocutory mechanics liens in the amount of $17,015 and $16,330 were entered
against the Property.
The Legal Action
On January 24, 2020, the Hollands filed suit against WPS for breach of the
Contract. The amended complaint asserted four counts. Counts I and II asserted claims
for breach of the Contract and breach of the indemnification clause in the Contract.
Count III asserted that the Contract did not comply with the MCHPA, which amounted to
an unfair or deceptive trade practice under the Maryland Consumer Protection Act,
Maryland Code (1975, 2013 Repl. Vol., 2019 Supp.), Commercial Law Article, §§ 13-
10113-501. Count IV asserted that, if the Contract was not the agreement between the
parties as WPS claimed, then WPS violated the MCHPA by not having a written contract
with the Hollands.
WPS filed a counterclaim and a third-party complaint, naming Chesapeake as a
third-party defendant. In Count I of its counterclaim, WPS asserted that the Hollands
breached the Contract by not paying for services rendered plus the profit thereon[.]
Count II asserted that the Hollands misrepresented their ownership of the Property.
Counts III and IV asserted claims for unjust enrichment and breach of contract against
Chesapeake. Count V asserted a claim for fraud against the Hollands, also based upon an
alleged misrepresentation of their ownership interest in the Property.
Unreported Opinion
15
The Bench Trial
The bench trial commenced on June 28, 2021. In the Hollands case, they called
five witnesses: Ms. Bissonnette; Mr. Quillen; Daniel Ruark, an excavating subcontractor;
Chris Puckett, a contractor who provided an estimate to the Hollands to complete the
house; and Ms. Holland. In WPSs case, Mr. Littleton testified and called one witness,
E.P. Cronshaw, Jr., the owner of Shore Lumber. Ms. Holland was recalled in rebuttal.
The Hollands introduced 32 exhibits, and WPS introduced 23 exhibits. Both parties filed
trial memoranda in advance of trial and written closing arguments at the conclusion of
trial.
In addition to the above stated facts, the following evidence was adduced. Ms.
Bissonnette testified that after WPS ceased work on the home, FSFB had the Property
inspected and disbursed funds to subcontractors for completion of aspects of the home.
The total remaining undisbursed loan funds totaled $14,370.13, which were held subject
to the mechanics liens.
Mr. Quillen explained the difference between a general contractor and a
construction manager arrangement. In the former arrangement, the general contractor
gives the client a fixed price to deliver the project as its shown in the construction
documents. The general contractor builds his or her profit into that figure. In a
construction management arrangement, the contractor just shows all of his expenses for
time, labor, and material plus a management fee. Mr. Quillens understanding of WPSs
arrangement with the Hollands was that it would be somewhere in the middle[,] with a
Unreported Opinion
16
not to exceed number typical of a general contractor, but open book as the project
progressed, plus a management fee. Mr. Quillen understood the contract price of
$700,250 to be a hard cap on the total expenses.
Ordinarily, Mr. Quillen performed construction administration over projects he
designed, meaning that he would conduct site visits and ensure that the project was being
built to specifications. In this case, he explained that because of difficulties with site
access and communication issues with Mr. Littleton, he notified the Hollands that he
could not perform that function and would not charge them his fee for that service. In his
view, the lack of construction administration was where things went off the rails[.]
Mr. Ruark testified that he was present when Mr. Littleton suggested the alternate
basement plan to the Hollands. Mr. Littleton suggested other changes to the plans that
could offset any price increase.
Ms. Holland testified that throughout the project her focus was on staying within
the budget and she routinely questioned whether proposed changes to the design would
increase her costs. She identified two extra expenses that she agreed to pay the cost for
arched doorways ($2,000) and the cost for a kitchen vent ($10,000). Aside from those
costs, Ms. Holland testified that Mr. Littleton never emailed her, texted her, or verbally
advised her of any change in the cost until his email in July 2019.
She explained that she requested the list of allowances to ensure that she would
not go over budget. At one point, Ms. Holland chose appliances at Lowes that cost less
than the allowance of $8,000. Upon informing Mr. Littleton, he told her that she should
Unreported Opinion
17
not purchase appliances for her fine house from Lowes and directed her to meet him at
Shore Appliances instead. He likewise insisted that she purchase cabinets from a
distributor in Centreville even though the same cabinets were available at Lowes for less
money.
Ms. Holland testified that, as of trial, the house was not complete, and a certificate
of occupancy still had not issued. She and her husband had since paid for the appliances
that Mr. Littleton never ordered, paid out of pocket for countertops because those also
were not ordered, purchased some vanities, purchased a new door to replace one that was
the wrong size, and had arranged for certain of WPSs subcontractors to return and finish
some work for them.
Given the budget overages and the time the Hollands had been forced to spend
arranging for the remaining work to be completed, Ms. Holland did not believe that WPS
earned its management fee. She explained that [p]art of managing is managing the
budget and managing to finish the work on time and [WPS] did neither. As an example,
Ms. Holland explained that when she discussed a movie room in her house with Mr.
Littleton, she asked for a darkened room where her children could watch television.
Without consulting her, Mr. Littleton subcontracted with Impact Theaters for a $20,000
theater room and that cost was reflected on the spreadsheet. She was never given the
option to choose or decline that option.
On cross-examination, Ms. Holland testified that Mr. Littleton told her that the 12
percent management fee was built into the contract price of $700,250. Counsel for WPS
Unreported Opinion
18
questioned how Ms. Holland could believe that the cost for the job would remain
unchanged after the plans were revised to add a full finished basement. Ms. Holland
responded that her expectation was that any change in the price would be reflected in a
change order, as required under the terms of the Contract. She emphasized that aside
from the two changes for which she explicitly agreed to pay more, Mr. Littleton
represented to her that every other change they made was within budget because she also
agreed to forgo certain items in exchange.
In response to questions posed by the circuit court, Ms. Holland explained that she
agreed to swap out other items in the house to ensure that the basement did not impact the
budget. Specifically, she agreed to eliminate a spiral staircase, to swap a gas insert in
place of a masonry fireplace, to change rooflines, and to remove a covered walkway from
the plans.
In WPSs case, Mr. Cronshaw testified that he suggested the full, finished
basement to Ms. Holland and showed her his basement in his home. He recalled
speaking with her about staying in budget when she picked out floor coverings and
cabinets. She decided against custom cherry cabinetry because it was too expensive,
choosing a less expensive semi-custom product.
Mr. Littleton testified that he had worked as general contractor for 35 years.
During that time, he had built fifteen custom homes. When he began working with the
Hollands, he agreed to provide them with [his] cost, and then add something . . . so that
Unreported Opinion
19
[he] got paid for doing what [he was] doing[.] He explained that because the Hollands
had not picked the finishes out for their home, he could not give [them] a solid number.
He testified that he did not ordinarily use an online template to prepare a contract,
but that the Hollands needed something for the bank. He included Paragraph 28, which
pertained to his 12 percent management fee, because he did not build any profit into the
contract price. Mr. Holland testified, from what [he] could gather, that the Hollands
never signed the Contract.
With respect to the revision of the plans, Mr. Littleton explained that because the
full basement added 1,700 square feet to the house, they were required to go to the
County to get it repermitted. The swaps that Ms. Holland testified had offset the cost
of adding the basement only covered the cost of the basement walls, according to Mr.
Littleton. The cost to finish the basement was much greater, and they never agreed on a
price for that. Mr. Littleton explained that he did not prepare any change orders on the
job [b]ecause [he] was working for a percentage at the end just like a construction
manager does.
The spreadsheet came about after WPSs accountant reached out to tell Mr.
Littleton he needed an influx of cash. At that time, Mr. Littleton was working on two
jobs. He provided the accountant with all the invoices he had received on the Hollands
job. Every price in the spreadsheet was straight up pricing from the people. When
the numbers came out to be as high as they were Mr. Littleton was surprised. That was
Unreported Opinion
20
the first time he told Ms. Holland that the project was over budget. Up until that point,
he unaware because he was working 90 hours a week.
On cross-examination, Mr. Littleton clarified that the other project he was
managing simultaneously was much larger, with a total price of $5 million for a 276-unit
complex. He acknowledged that he was very busy and lost track of everything.
Mr. Littleton did not dispute that he told the owner of Shore Appliances that he
would return the next day with a certified check to order the appliances Ms. Holland
selected. He also did not dispute that he never did so. He denied that he ever told Ms.
Bissonnette that he had already ordered them, however.
Mr. Littleton agreed that the Contract was the only contract [he] had with Mr. and
Mrs. Holland and that it never got changed by any written change order[.]
In response to questioning by the court, Mr. Littleton testified that he ordinarily
draws up his own contracts after sitting down with his clients and talking through
everything that they want.
After receiving all the evidence, the court directed the parties to submit written
closing arguments. In their memorandum, the Hollands argued that the Contract was the
sole agreement between the parties and had not been modified by any change orders or
other writings, which was the only way it could modified. The Contract entitled WPS to
receive $700,250 in six payments tied to the progress of construction. It received the first
five payments but did not receive the final payment because it did not complete
construction and no certificate of occupancy was issued. In contrast, the Hollands fully
Unreported Opinion
21
performed their obligations under the Contract. They maintained that they were entitled
to judgment for breach of contract and breach of the indemnification provision and
submitted a summary of damages totaling $189,557, comprising unused allowances for
three items ($15,500); payments made and amounts due directly to subcontractors after
WPS ceased work ($9,205 and $25,649); estimates received for work necessary to
complete the house ($89,516); the two mechanics liens ($33,345); and attorneys fees
and costs incurred defending the lien actions and prosecuting and defending this action
($45,032).
The Hollands further argued that WPSs counterclaims should be denied because
there was no evidence supporting its position that they failed to pay amounts due given
that they complied with the draw schedule. With respect to the misrepresentation and
fraud counts, WPS presented no evidence to support his claim that the Hollands
concealed that their land was owned by Chesapeake or to show reliance on the alleged
misrepresentation.
4
The Hollands did not dispute that the Contract bound them and
Chesapeake but denied that they breached its terms. Finally, they argued that to the
extent that the management fee in section 28 of the Contract was enforceable, that the
court should find that WPS did not earn the fee due to its mismanagement of the project
and material breaches of the Contract.
4
We note that the FSFB loan and the draw schedule were in the name of
Chesapeake, not the Hollands. Mr. Littleton signed the draw schedule when he received
his first check from FSFB. He also signed the application to revise the building permit
on behalf of Chesapeake.
Unreported Opinion
22
WPS argued that Ms. Hollands trial testimony was disingenuous and that she
was trying to paint herself as an unsophisticated farmer when she owned and managed a
concierge business in Washington, D.C.
5
It asked the court to reject Ms. Hollands
testimony that she believed that the revision of the plans to include a full basement would
not affect the price of the house. According to WPS, the negotiations between the parties
coupled with the language of the Contract support their position that this was a
construction manager arrangement, not a general contractor arrangement. WPS pointed
to Ms. Hollands testimony that she was concerned about what they were spending as
evidence that she was aware that the price for her home was not fixed and that the
finishes she chose would impact the final cost.
WPS also disputed Ms. Hollands testimony that she and her husband signed the
Contract shortly after Mr. Littleton emailed it to them. It pointed to evidence that the
Hollands printed the Contract from the Rocket Lawyer website on multiple occasions,
including on the day the bank funded their loan.
WPS acknowledged that the Hollands did not willfully misrepresent their
ownership of the Property but maintained that it made it more difficult for WPS to
pursue a Mechanics Lien. It asked the court to enter judgment in its favor and award
damages consistent with an attached damages statement. That statement calculated total
5
Ms. Holland testified that in addition to running the dairy farm with Mr. Holland,
they also managed a business in Washington, D.C. that provided front desk personnel for
apartment buildings. She was able to manage that business largely from Pocomoke City
and spent about five percent of her time on it.
Unreported Opinion
23
damages of $352,647.25, comprising the total unreimbursed amount WPS paid out of
pocket ($218,347); the 12 percent management fee on the total cost of the $845,372
project ($101,444)
6
; and prejudgment interest ($32,856.25).
The Courts Ruling
The court reconvened to rule from the bench on July 27, 2021. The judge
prefaced his ruling by noting that this was an unusual construction contract dispute
because there were no complaints about the quality of the workmanship. It found no
evidence of bad faith or dishonesty on the part of any of the parties, but rather a
complete and utter failure to effectively communicate. The court credited Mr.
Quillens testimony that the arrangement between the parties was anticipated to be a mix
between a construction manager and a general contractor arrangement, with a not to
exceed number.
Turning to the Contract, the court found that it was legally deficient and woefully
in[adequate] and that that was the underlying cause of the dispute. In any event, it was
drafted by WPS and tilted in [its] favor given the indemnification clause and the
management fee that was tacked onto the end[.] The court emphasized that though
there was considerable extrinsic evidence presented about the contract negotiations and
the understanding of the parties, it would limit its interpretation to the four corners of the
contract. The Contract present[ed] as a standard general contractor contract as
6
The 12 percent fee was applied against all amounts paid during the time WPS
worked on the project, including amounts paid by the Hollands.
Unreported Opinion
24
accepted in the industry with a management fee tacked onto the end. Section 7 set
forth the total sum that the Hollands agreed to pay. The court acknowledged that section
6 obligated WPS to provide documentation of the costs as an attachment to the Contract.
However, there was no evidence that WPS ever provided that documentation and,
consequently, it was not incorporated into the Contract. The court concluded that section
6, read in conjunction with section 28, was not sufficient to establish the contract in the
nature of a construction management or a cost-plus contract as is generally recognized.
The court reasoned that the management fee was inconsistent with a general contractor
arrangement generally and with the subject contract specifically and was poorly defined.
It did not specify when the fee was earned and how it would be paid. Given that WPS
drafted the Contract, it could have made the terms of the management fee clear but did
not. On those bases, the court ruled that section 28 was unenforceable for vagueness.
Alternatively, the court ruled that the fee was not earned because [t]he job was not
completed and was not effectively managed.
The court determined that the allowances were incorporated into the Contract
when they were requested by Ms. Holland and provided by WPS. Those amounts were
used to determine the Contract price. The court agreed with the Hollands that to the
extent items listed in the allowances never were provided by WPS, they were entitled to a
credit for those unused allowances. On the other hand, the court ruled that WPS was
entitled to credits for costs incurred in excess of any allowance, consistent with the
industry practice.
Unreported Opinion
25
The court reviewed all the invoices introduced into evidence by WPS and the
allowances sheet and determined that four allowances required additional findings. In
sum, the court found that WPS was entitled to a credit of $47,088.75 for expenditures by
the Hollands in excess of the allowances for flooring and tile, kitchen cabinets, and
specialty doors.
In the courts view, the evidence showed that the Contract was satisfactorily
adjusted by the parties as it relates to the basement. Specifically, the Hollands agreed to
revise the plans to cover the cost of expanding the basement and to pay an additional
$10,000. To the extent that there was an additional cost increase associated with the
revision of the plans to include a full basement, the Contract required the parties to
execute a change order and that did not occur.
The court found that WPS was entitled to a $10,764.71 credit for the cost of the
driveway, which was an item specifically excluded from the Contract.
On the other hand, the court ruled that WPS breached the Contract by stopping
work and purporting to terminate [it]. WPS erroneously viewed the [C]ontract as a
construction management or cost plus cont[r]act and it was indisputable that it
overspent on the project due to inattentiveness, which [Mr. Littleton] acknowledge[d].
Because the court concluded that the Contract was a general contractor contract with a
fixed price, with a purported management fee tacked on, however, it ruled that the
Hollands were not in breach of its terms when WPS ceased worked and attempted to
terminate the Contract. They had made all payments to which WPS was entitled under
Unreported Opinion
26
the draw schedule and then some and WPSs demands for additional money was itself
a breach of the Contract.
As a direct consequence of WPSs breaches, the Hollands suffered damages in the
form of costs to complete the work on their home, one of the two mechanics liens,
7
and
the costs to defend against that mechanics lien, plus the unused allowances under the
Contract, totaling $115,920. The court denied the Hollands request for attorneys fees
incurred in prosecuting this action, however, because the indemnification clause in the
Contract was phrased in discretionary language and did not obligate WPS to indemnify
the Hollands. It likewise denied their fee request under the MCHPA, ruling that because
the Hollands executed the Contract with WPS, but the land upon which their home was to
be constructed was owned by Chesapeake, they did not qualify for protection under the
Act.
On July 27, 2021, the court entered judgment for the Hollands on Count I of the
amended complaint, awarding damages of $58,066.54. It denied the relief sought by
WPS in its counterclaim. This timely appeal and cross-appeal followed.
STANDARD OF REVIEW
“When an action has been tried without a jury, the appellate court will review the
case on both the law and the evidence.” Md. Rule 8-131(c). We review the circuit courts
factual findings for clear error, “giv[ing] due regard to the opportunity of the trial court to
7
The court found that the second mechanics lien, which arose from monies due to
a subcontractor for refinishing the floors, was a cost that already exceeded the allowance
for flooring and, consequently, the Hollands were responsible for that cost.
Unreported Opinion
27
judge the credibility of the witnesses.” Id. We will only overturn the trial court’s findings
of fact that are “clearly erroneous[.]Torboli v. Torboli, 127 Md. App. 666, 672 (1999)
(internal citations omitted). If there is any competent and material evidence to support
the factual findings of the trial court, those findings cannot be held to be clearly
erroneous.” L.W. Wolfe Enterprises., Inc. v. Md. Nat’l Golf, L.P., 165 Md. App. 339, 343
(2005) (quotations and citation omitted). But we review a trial courts legal rulings
without deference to determine whether the trial court was legally correct. Credible
Behavioral Health, Inc. v. Johnson, 466 Md. 380, 388 (2019)
DISCUSSION
APPEAL
I.
Enforcement of the Contract
A. Parties Contentions
WPSs primary position is that the Contract is not binding. First, it contends that
the Hollands are judicially estopped from relying upon the Contract because they pled in
the alternative in their amended complaint that the parties agreement was not in writing.
Second, it argues that the Contract was not executed by the Hollands and, consequently,
that though the writing is evidence of the structure of the parties agreement, it does not
bind them. WPS contends that the court should have treated the Contract as a proposal
and looked to other extrinsic evidence to determine that the parties agreed to a
construction management arrangement. It also argues that the court should have
Unreported Opinion
28
considered that the parties course of conduct showed that they never intended the
Contract to govern the construction project, particularly after the January 18, 2022
revision of the plans to expand the basement.
The Hollands respond that the court correctly found that the Contract was the
entire written agreement between the parties and that they were bound by its terms.
Because the Contract is clear and unambiguous, the Hollands maintain that the circuit
court was not permitted to look beyond its language. With respect to the revision of the
plans for the home, the Hollands assert that the Contract specified that the only way the
scope of the work could be revised was by a written change order signed by both parties
and that to the extent that the revisions increased the cost to build the home, WPS was
obligated to follow that procedure to alter the parties agreement.
B. Estoppel
As a threshold matter, we hold that the Hollands are not estopped from relying
upon the Contract for their claims. Under Maryland Rule 2-303(c), [a] party may set
forth two or more statements of a claim . . . alternatively or hypothetically and may
also state as many separate claims . . . as the party has, regardless of consistency[.] In
Counts I, II, and III of their amended complaint, the Hollands pled that the July 24, 2017
Contract was the governing agreement between the parties and alleged that WPS
breached its terms and violated the MCHPA by not including certain terms in the
Contract. In Count IV, they pled in the alternative that, if the circuit court agreed with
WPS that there was no executed, written contract between the parties, the lack of a
Unreported Opinion
29
written contract also would violate the MCHPA. The Hollands were not precluded from
pleading and obtaining relief on the theory that WPS breached the Contract merely
because it alleged an alternative theory of WPSs liability under the MCHPA.
We likewise perceive no merit in WPSs argument that the amended complaint did
not allege that there was an executed written contract between the parties. To the
contrary, the first paragraph in the amended complaint alleges that the Hollands and WPS
entered into a Construction Contract dated July 24, 2017, (Contract) for [WPS] to
build a custom home in Pocomoke, Maryland for [the Hollands] for $700,250. This
allegation cannot reasonably be understood to refer to any document other than the
written Contract bearing that date.
C. Contract Interpretation
Turning to the Contract,
8
we are guided by the well-established principles of
contract interpretation. “The cardinal rule of contract interpretation is to effectuate the
intentions of the parties.” Owens-Illinois, Inc. v. Cook, 386 Md. 468, 497 (2005). Our
task is to “give effect to the plain meaning of the contract, read objectively, regardless of
the parties’ subjective intent at the time of contract formation.” Impac Mortg. Holdings,
8
WPS contends throughout its brief that the Contract never was executed by the
Hollands. To be sure, it advanced this position during the bench trial, questioning why
the Hollands printed copies of the Contract from Rocket Lawyer after the date they
claimed to have executed it. Nevertheless, the Hollands introduced a fully executed copy
of the Contract into evidence, and Ms. Holland testified that she and her husband
executed it in Mr. Littletons presence in July 2017, shortly after they received it. The
circuit court plainly credited Ms. Holland’s testimony. As the finder of fact, the court
was free to accept her testimony and to reject Mr. Littleton’s testimony to the contrary.
Unreported Opinion
30
Inc. v. Timm, 474 Md. 495, 507 (2021). “In other words, when the contract language is
plain and unambiguous, ‘the true test of what is meant is not what the parties to the
contract intended it to mean, but what a reasonable person in the position of the parties
would have thought it meant.’” Id. (quoting Dennis v. Fire & Police Emps.’ Ret. Sys.,
390 Md. 639, 656-57 (2006)).
Ambiguity arises when a term of a contract, as viewed in the context of the entire
contract and from the perspective of a reasonable person in the position of the parties, is
susceptible of more than one meaning. Impac Mortg., 474 Md. at 507. If a contract
provision is ambiguous, the narrow bounds of the objective approach give way, and the
court may consider extrinsic evidence to ascertain the mutual intent of the parties. Id.
(citing Credible Behavioral Health, Inc. v. Johnson, 466 Md. 380, 394 (2019)).
The Contract, read as a whole, obligated WPS to construct a custom home for the
Hollands based upon plans and specifications designed by Mr. Quillen, then dated May 4,
2017, and to provide all materials and services with certain specified exceptions. The
Hollands were obligated to make the plans, specifications, and construction documents
available to WPS, to make the work site accessible, and to pay a fix price to WPS
according to a draw schedule.
Section 7 of the Contract, entitled Payment is the only clause of the Contract
that obligates the Hollands to pay any money to WPS. It specifies that the total sum
the Hollands would be obligated to pay for the construction of their home was $700,250.
This clause also established a timeline upon which the payments were to be made. Each
Unreported Opinion
31
payment was tied to a progress point in the construction, with final payment not due until
a certificate of occupancy issued. Nothing in the Contract evidences an intent for the
price to fluctuate based upon costs incurred. WPS agreed to complete the work by May
16, 2018, specifying that time was of the essence.
Sections 9 and 24 make clear that the Hollands only were obligated to pay for
costs above $700,250 if a price increase was reflected in a written change order, executed
by all parties, and that other modifications also were required to be in writing and signed.
The circuit court found that the parties modified the Contract in three ways during the
project. First, the allowances provided to Ms. Holland by WPS were a signed writing
incorporated into the Contract. Neither party disputes that ruling on appeal, and the
Hollands do not challenge any of the credits awarded to WPS for costs that exceeded the
allowances. Second, the court implicitly ruled that the revised draw schedule prepared by
FSFB and executed by both parties modified the draw schedule set out in the Contract.
Neither party disputes this. Third, the circuit court implicitly ruled that the January 22,
2018 revised plans were incorporated into the Contract. WPS disputes this, arguing that
the Contract only governed construction of the custom home according to the original
plans.
9
9
Even if we did not conclude that the parties modified the Contract to incorporate
the revised plans, we would decline to address WPSs argument that the Contract was
specifically only applicable to the plans dated May 4, 2017. WPS did not advance this
argument in its trial memoranda or its written closing arguments. To the contrary, it
argued that the significant expansion of the custom home after the Contract was executed,
(Continued)
Unreported Opinion
32
We hold that the revised plans were incorporated into the Contract when, as
discussed, Mr. Littleton, filed an application to revise the building permit with the
County, which he signed as an agent of Chesapeake. The application was a writing
signed by and on behalf of all the parties and it specified that price increase for this
revision was $10,000. The Hollands do not dispute that the Contract price was increased
to accommodate this adjustment. WPS did not at any time propose an increase in the
price outside of this $10,000 figure, which Ms. Holland and Mr. Quillen testified was the
amount quoted during a discussion of the revision. There is no change order or other
writing documenting any other price increase agreed to by the parties, presumably
because the parties testified that they agreed to offset the additional cost for the basement
by removing other construction costs.
For all these reasons, we conclude that the circuit court did not err: 1) in
determining that the Contract established a fixed total price for the construction of the
Hollands home; 2) in ruling that WPS breached the Contract when it demanded money
above and beyond the total price as a condition to completing the work and then
terminated the Contract; or, 3) in awarding damages to the Hollands, offset by credits due
to WPS.
as reflected in the revised plans, was evidence that the parties were operating under a
construction management arrangement.
Unreported Opinion
33
II.
Section 28 of the Contract
WPS contends that if the Contract is deemed binding, the circuit court failed to
enforce its unambiguous language requiring the Hollands to pay WPS a 12 percent
management fee on top of the Contract price. The Hollands respond that the circuit court
correctly found that WPS did not earn the management fee.
10
Section 28 of the Contract states that WPS will receive a minimum of twelve
percent construction management fee for all aspects of construction on the Holland
project. The circuit court determined that this clause was unenforceable because it does
not specify how and when the fee becomes payable or whether it is incorporated into the
Contract price of $700,250, as would be standard in a general contractor arrangement.
Consequently, the circuit court severed this provision from the Contract under the section
22 (If any provision of this Contract will be held to be invalid or unenforceable for any
reason, the remaining provisions will continue to be valid and enforceable.).
Alternatively, the court ruled that WPS was not entitled to collect its management fee
because [t]he job was not completed and was not effectively managed. Because we
agree that WPS could not collect the fee considering its material breaches, we need not
reach the issue of enforceability.
10
The Hollands do not argue on appeal that the management fee clause was
unenforceable.
Unreported Opinion
34
Generally, where one party has materially breached a contract, the other party is
no longer obligated to perform. See Barufaldi v. Ocean City Chamber of Com., 196 Md.
App. 1, 26 (2010). Here, the circuit court found that WPS materially breached its
performance obligations by stopping work and demanding money it was not entitled to
receive and failed to deliver to the Hollands a completed home for which a certificate of
occupancy could be issued. It also found that WPS mismanaged the budget. The
evidence unquestionably supported these findings. Mr. Littleton testified at trial and at
his deposition that he was unaware that the project was significantly over budget until
July 2019well over a year after construction commenced and after the home was to be
delivered completed under a time is of the essence provision. See Granados v. Nadel,
220 Md. App. 482, 488 n.5 (2014) (When time is of the essence is included in a
contract, time is such a material matter that strict compliance by performance within the
specified periods of time is a prerequisite to the right to require performance by the other
party. (citing Elderkin v. Carroll, 403 Md. 343, 358 (2008)). Mr. Littleton admitted that
it got away from [him] because he was working on two projects at once. He did not
dispute that he did not notify the Hollands that they were over budget until he made his
demand for additional payments. As a direct consequence of the breaches, the Hollands
were forced to manage the completion of the project, which remained unfinished. On this
evidence, the circuit court did not err by ruling that the Hollands were not obligated to
pay WPS a construction management fee.
Unreported Opinion
35
III.
Custom Home Protection Act
A. Parties Contentions
In their cross-appeal, the Hollands contend that the circuit court erred as a matter
of law by ruling that the MCHPA did not apply to them because the land on which their
custom home was built was titled in Chesapeakes name and never was owned by them
individually. Because that was an alternative basis upon which they sought an award of
attorneys fees, the Hollands maintain that remand is necessary for the circuit court to
consider their fee request.
11
WPS responds that the Hollands do not describe any basis for ignoring the
corporate entity in this matter and that [t]here is no[] basis for ignoring how the land
was owned and thereby increasing the requirements on WPS. WPS further avers that
even if the statute applied to this matter and the contract was found wanting, the remedy
for not having a compliant contract should not be the unjust enrichment of the Hollands.
B. Analysis
The General Assembly enacted the MCHPA in 1986. The stated purposes of the
legislation included:
requiring certain payments to custom home builders to be held in trust;
providing for certain funds to be kept in escrow; providing for a surety
11
The Hollands do not challenge in their cross-appeal the circuit courts
construction of the indemnification clause in the Contract to permit, but not require, WPS
to pay their attorneys fees. They also do not suggest that they are entitled to additional
damages for violations of the MCHPA.
Unreported Opinion
36
bond in lieu of an escrow fund; defining certain terms; providing that
certain contracts be in writing; providing that the contract shall provide
certain information and disclosures under certain conditions; providing that
certain provisions of law apply to a sale by a vendor or builder that has
outstanding a certain number of certain contracts; providing for penalties
for certain violations of this Act; and generally relating to custom home
contracts.
Schwartz v. State, 103 Md. App. 378, 388 (1995) (quoting 1986 Md. Laws, ch. 853). The
Acts overall purpose is “to provide a specific remedy for custom homeowners dealing
with impecunious contractors.” Id. at 389.
The MCHPA requires that [e]very custom home contract between a custom home
builder and the buyer . . . be in writing and that the contract comply with these
provisions:
(1) Include a draw schedule that shall be set forth on a separate sheet . . .
that shall be separately signed by the buyer and the [builder];
(2) Identify to the extent known the names of the primary subcontractors
who will be working on the custom home;
(3) Expressly state that any and all changes that are to be made to the
contract shall be recorded as change orders that specify the change in the
work ordered and the effect of the change on the price of the house;
(4) Set forth in bold type whether or not the vendor or builder is covered by
a warranty program . . . ;
(5) Require the vendor or builder to deliver to the purchaser within 30 days
after each progress payment a list of the subcontractors, suppliers, or
materialmen who have provided more than $500 of goods or services to
date and indicate which of them have been paid by the [builder]; and
(6) Require that the [builder] provide waivers of liens from all applicable
subcontractors, suppliers, or materialmen within a reasonable time after the
final payment for the goods or services they provide.
Unreported Opinion
37
RP § 10-505. Additionally, section 10-506 requires a custom home builder to include in
each custom home contract a disclosure concerning a buyers risk under mechanics lien
laws.” RP § 10-506(a). A builder who violates these sections is subject to several
penalties, and a violation constitutes “[a]n unfair or deceptive trade practice” under the
Maryland Consumer Protection Act. RP § 10507. In order to be entitled to damages or
an award of reasonable attorneys fees in an action under the Consumer Protection Act
premised upon a violation of the MCHPA, a homeowner must show that they were
actually injured by [the] violation of the Act[.] DeReggi Constr. Co. v. Mate, 130 Md.
App. 648, 665 (2000).
Of significance here, section 10-501(b) of the MCHPA defines a Buyer as any
person who seeks or enters into a contract for the construction of a custom home.
Person is elsewhere defined to include individuals, corporations, and any other legal
or commercial entity. RP § 10-501(h). A Custom home is a single-family dwelling
constructed for the buyers residence on land currently or previously owned by the
buyer. RP § 10-501(c) (emphasis added).
The circuit court reasoned that the Hollands did not fall within the ambit of the
statute because they signed the Contract in their own names and did not currently or
previously own the land upon which the custom home was to be constructed.
Consequently, they were not a Buyer as that term was defined under the Act. We
disagree.
Unreported Opinion
38
The cardinal rule of statutory interpretation is to ascertain and effectuate the real
and actual intent of the legislature. State v. Bey, 452 Md. 255, 265 (2017) (quoting State
v. Johnson, 415 Md. 413, 421 (2010)). We begin “with the plain language of the statute,
and ordinary, popular understanding of the English language dictates interpretation of its
terminology.” Blackstone v. Sharma, 461 Md. 87, 113 (2018). “The statutory language
should be read so that no word or phrase renders any part of it ‘meaningless, surplusage,
superfluous, or nugatory.’” Bd. of Educ. of Howard Cnty. v. Howard Cnty. Educ. Assn-
ESP, Inc., 445 Md. 515, 533 (2015) (quoting Blitz v. Beth Isaac Adas Israel
Congregation, 352 Md. 31, 40 (1998)). We, however, do not read statutory language in
a vacuum, nor do we confine strictly our interpretation of a statute’s plain language to the
isolated section alone. Johnson v. State, 467 Md. 362, 372 (2020) (quoting Wash. Gas
Light Co. v. Md. Pub. Serv. Comm’n, 460 Md. 667, 685 (2018)). Instead, “‘[w]e presume
that the Legislature intends its enactments to operate together as a consistent and
harmonious body of law, and, thus, we seek to reconcile and harmonize the parts of a
statute, to the extent possible consistent with the statute’s object and scope.’” Gerety v.
State, 249 Md. App. 484, 498 (2021) (quoting Bey, 452 Md. at 266). We will also
consider the consequences resulting from one meaning rather than another and adopt
that construction which avoids an illogical or unreasonable result, or one which is
inconsistent with common sense. Bolling v. Bay Country Consumer Fin., Inc., 251 Md.
App. 575, 589 (2021), reargument denied (Sept. 2, 2021) In addition to these well-
Unreported Opinion
39
established canons, we liberally construe a remedial statute to effectuate its broad
remedial purpose. Id.
Here, the Contract contemplated the construction of single-family dwelling that
the Hollands would use as their residence on land owned by them indirectly, as the sole
members of their limited liability company. The Hollands took out a construction loan in
Chesapeakes name, and the draw schedule, which was incorporated into the Contract,
reflected Chesapeakes ownership of the Property. WPS executed the draw schedule and
the revised building permit, both of which named Chesapeake as the owner. It would
defeat the remedial purpose of the MCHPA to construe it narrowly to permit the
misidentification of the Buyer in a contract to eliminate protections under the Act.
This is especially so because a limited liability company may be a Buyer under the
MCHPA. See RP § 10-501(b) & (h) (permitting any legal entity to be a person who . .
. enters into a contract for the construction of a custom home).
Here, the Contract was for a Custom home to be constructed for the buyers
residence on land currently or previously owned by the buyer. RP § 10-501(c). The
Hollands are the sole members of Chesapeake, and the construction loan from which
WPS took its draws was secured by a deed of trust on the Property naming Chesapeake
on the title. For all of the foregoing reasons, we conclude that the Contract was required
to comply with the MCHPA. Because the circuit court ruled that the Hollands could not
seek relief under the MCHPA, it did not consider their request for attorneys fees under
the Act. Thus, we shall vacate the denial of the Hollands request for attorneys fees
Unreported Opinion
40
under Count III of the amended complaint and remand for the circuit court to hold
additional proceedings not inconsistent with this opinion to determine whether the
Contract violated the MCHPA, and if so, whether attorneys fees are justified.
12
JUDGMENT OF THE CIRCUIT COURT
FOR WORCESTER COUNTY AFFIRMED,
IN PART, AND VACATED, IN PART;
CASE REMANDED FOR FURTHER
PROCEEDINGS CONSISTENT WITH
THIS OPINION; COSTS TO BE PAID BY
APPELLANT/CROSS-APPELLEE.
12
We note that the Hollands, in their cross-appeal, have limited their request for
remand to consider an award of attorneys fees and not any other potential damages that
may be available under the MCHPA. An issue not raised by an appellant or cross-
appellant in its opening brief in this Court is deemed waived or abandoned. Md. Auto Ins.
Fund v. Baxter, 186 Md. App. 147, 154 (2009); Remsburg v. Montgomery, 376 Md. 568,
585 n.8 (2003) (collecting cases)). Consequently, only the Hollands claim for attorneys
fees under the MCHPA is before the circuit court on remand.