Page | 8
Potential Impacts from Changing Statutory Requirements for Transfers Between
Subbasins
When examining whether transfers of water between subbasins within the same major river basin
should continue to be required to comply with all of the same requirements under G.S. 143-
215.22L as transfers of water between major river basins, DEQ considered changing the
requirement for transfers between subbasins to follow the truncated process (Figure 3) outlined
in G.S. 143-215.22L (w). The advantages and disadvantages to both are discussed in more detail
below.
Advantages to Changing Statutory Requirements for Transfers Between Subbasins
If the current statutory requirements for surface water transfers were eliminated for subbasins, it
would save substantial time and money for those systems seeking to transfer water between
subbasins (see above) by not having to go through a lengthy IBT certificate process. Changing
the requirements to follow the truncated process outlined in subsection (w) would reduce the cost
and time to obtain an IBT certificate. The current statutory requirements identify three separate
points in the process through public notices to solicit review and comment as well as public
hearings. The initial public meetings following the NOI are often not well attended as the
proposed project is in the scoping stage with many aspects of the project still unknown.
Changes in the requirements, either through truncation or elimination, for subbasin transfers
could make it easier for neighboring systems to have interconnections. This could increase water
systems’ resiliency to water shortage conditions such as drought or emergency situations such as
line breaks.
Disadvantages to Changing Statutory Requirements for Transfers Between Subbasins
Changes to, or the elimination of, the current requirements for subbasin transfers could reduce
opportunities for public involvement and transparency, and adequate review to protect both the
source and receiving river subbasins’ water users and the environment.
Many of the current requirements for obtaining an IBT certificate are in place to protect the
state’s water resources and comply with the federal Clean Water Act. Without a thorough
environmental review of a proposed surface water transfer, there could be impacts not identified,
resolved or mitigated to both water users and the environment in both the source and receiving
river basins. This is a significant concern to ensure adequate protection of both water quality and
quantity for the affected river basins. There could be sensitive areas with protected species,
impaired waters, segments of a river disproportionately impacted, or different water systems
more at risk during water shortages. Without thorough environmental review and
documentation, water systems may be at increased risk for litigation.
Public involvement is a key element in the current statutory process required for water systems
seeking an IBT certificate. Public involvement provides a more complete picture to both DEQ
and the EMC, including additional facts and perspectives. Eliminating the opportunity for public
notice, review and comment throughout the process could result in critical issues being left
unaddressed or coming to light late in the review process. It can also make the decisions seem
less legitimate and ultimately more susceptible to litigation.