CECW-PR
Regulation No.
1165-2-130
Department of the Army
U.S. Army Corps of Engineers
Washington, DC 20314-1000
ER 1165-2-130
15 Jun 89
Water Resources Policies and Authorities
FEDERAL PARTICIPATION IN
SHORE PROTECTION
Distribution Restriction Statement
Approved for public release; distribution is unlimited.
ER 1165-2-130
DEPARTMENT OF THE ARMY
Office of the Chief of Engineers
Washington, DC 20314-1000
CECW-RR
15 June 1989
Regulation
No. 1165-2-130
Water Resources Policies and Authorities
FEDERAL PARTICIPATION IN SHORE PROTECTION
Table of Contents
Subject Para. Page
Purpose......................................... 1 3
Applicability................................... 2 3
References...................................... 3 3
Definitions..................................... 4 4
Program Legislation............................. 5 4
Program Policies................................ 6 4
Shore Protection.............................. 6a 4
Related Recreation.......................... 6a(1) 5
Related Dredged Material Disposal........... 6a(2) 8
Geographic Applicability...................... 6b 9
Coastal Zone Management Plans................. 6c 9
Coastal Barrier Resources System.............. 6d 9
Beach Creation................................ 6e 9
Project Purposes.............................. 6f 9
Shore Categories.............................. 6g 10
Public Use.................................... 6h 12
Improvements for Recreation................... 6i 13
Federal Role in Project Development............. 7 13
Preauthorization Studies...................... 7a 13
Postauthorization Studies..................... 7b 14
Construction.................................. 7c 14
Maintenance................................... 7d 15
Periodic Nourishment.......................... 7e 15
Plan Formulation and Evaluation................. 8 16
Formulation................................... 8a 16
Evaluation.................................... 8b 16
This regulation supersedes ER 1165-2-130, 15 January 1979.
2
ER 1165-2-130
15 Jun 89
Cost Sharing................................... 9 17
General Policy............................... 9a 17
Applicability................................ 9b 17
Policies Regarding Formulation,
Evaluation and Cost Allocation............. 9c 17
Cost Apportionment........................... 9d 18
Policies Limiting Corps of Engineers
Participation.............................. 9e 20
Emergency Authorities........................ 9f 22
Multiple-Purpose Projects.................... 9g 22
Related Dredged Material Disposal............ 9h 22
Local Cooperation Requirements................. 10 22
Local Cooperation Standard Wording............. 11 23
Local Cooperation Agreements................... 12 23
Tables
1 - Federal Participation in Shore Protection
Projects that Include Recreation Facilities
or Generate Recreation Benefits..................... 6
2 - Percent Federal Participation in Costs for
Shore Protection by Shoreline Ownership
Category and Project Benefits....................... 11
Appendices
Appendix A - Definitions of Terms Used in ER
Appendix B - Synopsis of Program Legislation
Appendix C - Example Computations for Cost Sharing
3
ER 1165-2-130
15 Jun 89
1. Purpose
. This Engineer Regulation (ER) provides policies and
guidelines for determining the extent of Federal participation in
potential Federal projects for protection from shore erosion,
hurricanes, and abnormal tidal and lake flooding that result in damages
or losses to coastal resources and/or development.
2. Applicability
. This ER is applicable to all HQUSACE/OCE elements
and all field operating activities (FOAs) having Civil Works
responsibilities. The policies and guidelines set forth in this
regulation are applicable to all Congressionally-authorized
preconstruction studies and preconstruction studies conducted under the
authority of Section 103, Public Law (P.L.) 87-874, and under the
authority of Section 111, P.L. 90-483 for projects not specifically
authorized by the Congress.
3. References
.
a. P.L. 71-520, 3 July 1930, River and Harbor Act (R&HA).
b. P.L. 79-526, 24 July 1946, Flood Control Act (FCA) of 1946.
c. P.L. 79-727, 13 August 1946.
d. P.L. 84-71, 15 June 1955.
e. P.L. 84-99, 28 June 1955.
f. P.L. 84-826, 28 July 1956.
g. P.L. 85-500, 3 July 1958, R&H and FCA of 1958.
h. P.L. 86-645, 14 July 1960, R&H and FCA of 1960.
i. P.L. 87-874, 23 October 1962, R&H and FCA of 1962.
j. P.L. 88-172, 7 November 1963.
k. P.L. 89-72, 9 July 1965, Federal Water Project Recreation Act.
l. P.L. 90-483, 13 August 1968, R∧H and FCA of 1968.
m. P.L. 91-611, 31 December 1970, R∧H and FCA of 1970.
n. P.L. 91-646, 2 January 1971, Uniform Relocations Assistance and
Real Property Acquisition Policy Act of 1970.
o. P.L. 92-583, 27 October 1972, Coastal Zone Management Act of
1972.
p. P.L. 93-251, 7 March 1974, Water Resources Development Act
(WRDA) of 1974.
4
ER 1165-2-130
15 Jun 89
q. P.L. 94-587, 22 October 1976, WRDA of 1976.
r. P.L. 97-348, 18 October 1982, Coastal Resources Barrier Act.
s. P.L. 99-662, 17 November 1986, WRDA of 1986.
t. P.L. 100-676, 17 November 1988, WRDA of 1988.
u. Executive Order 11988, Floodplain Management, 24 May 1977.
v. Executive Order 11990, Protection of Wetlands, 24 May 1977.
w. ER 200-2-2, Policy and Procedures for Implementating NEPA.
x. ER 1105-2-100, Planning Guidance Notebook.
y. ER 1110-2-1407, Hydraulic Design for Coastal Shore Protection
Projects.
z. ER 1130-2-307, Dredging Policies and Practices.
aa. ER 1130-2-400, Management of Natural Resources and Outdoor
Recreation at Civil Works Water Resource Projects
bb. ER 1130-2-435, Preparation of Project Master Plans.
cc. ER 1165-2-18, Reimbursement for Advance Non-Federal
Participation in Civil Works Projects.
dd. ER 1165-2-131, Policy Guidance for New Start Construction
Projects.
ee. ER 1165-2-400, Recreation Planning, Development, and Management
Policies
4. Definitions
. To facilitate use of this ER and promote understanding
the policies and procedures set forth herein, definitions of terms as
used in this ER are provided in Appendix A.
5. Program Legislation
. Legislation that provides the bases for and
changes in the policies and procedures set forth in this ER is
synopsized in Appendix B.
6. Program Policies
.
a. Shore Protection
. It is Corps policy to provide Federal
assistance in reducing damages to shorefront development and coastal
resources from shore erosion, hurricane, and abnormal tidal and lake
flooding by undertaking shore protection projects where such projects
5
ER 1165-2-130
15 Jun 89
best serve the public interest. Plans will be developed, evaluated, and
selected in accordance with the Water Resources Council's (WRC) Economic
and Environmental Principles and Guidelines (P∧G) for Water and
Related Land Resources Implementation Studies (dated 10 March 1983) as
required by ER 1105-2-100. WRC P∧G directs water and related land
resources planning toward the Federal objective of contributing to
national economic development consistent with protecting the Nation's
environment, pursuant to national environmental statutes, applicable
Executive Orders, and other Federal planning requirements. In
connection with existing shore protection, hurricane protection, and/or
beach erosion control projects, it is Corps policy to consider extension
of Federal participation in any periodic nourishment for the project as
a new investment decision subject to current evaluation criteria, and
cost apportionment and cost sharing will be in accordance with P.L.
99-662. In any case in which the use of fill material for beach erosion
control or beach nourishment is authorized as a purpose of an authorized
water resources project, it is Corps policy to consider acquiring such
material by purchase, exchange, or otherwise from nondomestic sources
and use such materials for such purposes only if such materials are not
available from domestic sources for environmental or economic reasons.
The extent of Federal participation in any shore protection plan will be
based on the policies and requirements given in the following
paragraphs. Section 934 of P.L. 99-662 will not be used to extend the
period of authorized periodic nourishment of projects that use
sand-bypassing/backpassing plants.
(1) Related Recreation
. It is the policy of the United States to
assist in the construction, but not the maintenance, of works to protect
against erosion by waves and currents along the shores of the United
States for the purposes of preventing damages to property and promoting
and encouraging healthful recreation (P.L. 79-727, as amended).
However, recreation is not considered to be a high priority or primary
project output under current Department of the Army policy.
Accordingly, the Corps participates in shore protection plans that
include recreation facilities or generate recreation benefits if the
recreation outputs are incidental (i.e., no separable construction costs
are required to realize recreation outputs) and are not the primary
outputs (Table 1, Case 1). Corps participation in separable recreation
features at shore and hurricane protection projects, even though such
features may be economically justified, is precluded under current
Department of the Army policy (Table 1, Case 2). Federal funds are also
not used to support construction of shore or hurricane protection
projects which depend on separable recreation benefits for economic
justification (Table 1, Case 3), or for which incidental recreation
benefits are greater than 50 percent of the total benefits unless the
project is economically justified based on primary project outputs alone
(Table 1, Case 4), or based on the combination of primary benefits and
an equivalent amount of incidental recreation benefits (Table 1, Case
5). Land loss prevention benefits attributable to undeveloped private
lands are to be categorized as private benefits, even though the shore
may be public. Implementing policies and procedures on Corps
participation in recreation development are provided in ER 1105-2-100,
ER 1130-2-400, ER 1130-2-435, and ER 1165-2-400.
6
ER 1165-2-130
15 Jun 89
TABLE 1 - FEDERAL PARTICIPATION IN SHORE PROTECTION PROJECTS THAT
INCLUDE RECREATION FACILITIES OR GENERATE RECREATION BENEFITS
CASE 1 - Federal participation in this recreation benefit generating
shore protection (SP) project is warranted since the recreation benefits
are incidental, comprise less than 50 percent of total benefits, and,
when combined with the primary H∧SDR benefits, produce an
economically justified project (i.e., project is not justified on H&SDR
benefit alone).
CASE 2 - Federal participation in this recreation benefit generating SP
project is limited to the portion that generates primary H&SDR benefits
(i.e., H&SDR portion of overall project is separably economically
justified). Federal participation in the separable recreation of the
overall project is restricted by Army budgetary policy even though it is
separably justified.
7
ER 1165-2-130
15 Jun 89
CASE 3 - Federal participation in this recreation benefit generating SP
project is not warranted since separable recreational benefits are
necessary to justify the overall project (i.e., project is not justified
based on primary H∧SDR benefits alone, or on the combination of
H&SDR and incidental recreation benefits, with incidental recreation
benefits limited to an equivalent amount of H∧SDR benefits).
CASE 4 - Federal participation in this recreation benefit generating SP
project is warranted since the recreation benefits are incidental and,
even though they comprise over 50 percent of total benefits, they are
not necessary for project justification (i.e., project is justified
based on primary H∧SDR benefits alone).
CASE 5 - Federal participation in this recreation benefit generating SP
project is warranted since recreation benefits are incidental, and, when
combined with and limited to an equivalent amount of primary H∧SDR
benefits, they produce an economically justified project.
8
ER 1165-2-130
15 Jun 89
(2) Related Dredged Material Disposal
. It is Corps policy to
accomplish construction and maintenance dredging in the least costly and
most environmentally sound manner possible (ER 1130-2-307). If
placement of dredged material on a beach or beaches is determined by the
Corps to be the least costly acceptable means for disposal of the
material, then such placement should be considered integral to
accomplishment of the project work and not subject to any special
non-Federal cost-sharing requirements (unless benefits from the on-beach
placement are required for project justification and those benefits are
of a kind with which special cost sharing is associated).
(3) It is Corps policy to participate in the additional costs for
placing beach-quality sand or other suitable material, dredged by the
Corps during construction or maintenance of Federal navigation projects,
onto adjacent beaches or near shore waters subject to the following:
(a) Placement of the material on a beach or beaches and
Federal (Corps) participation in the costs must be requested by the
State in which the beach or beaches are located;
(b) The added cost of disposal must be justified by the
benefits associated with the protection of such beach or beaches;
(c) The storm damage reduction benefits resulting from the
beach protection must exceed 50 percent of the total benefits, unless
the placing of dredged material is economically justified based on storm
damage reduction benefits alone, or on the combination of storm damage
reduction benefits and an equivalent amount of incidental recreation
benefits if incidental recreation benefits exceed 50 percent of total
benefits.
(d) The beaches involved must be open to the public;
(e) The placement must be environmentally acceptable, pursuant
to all applicable statutes and regulations;
(f) Local interests must pay 50 percent of the added cost of
disposal above the alternative least costly method of disposal; and
(g) Local interests must provide (without cost sharing) any
necessary additional lands, easements, rights-of-way, and relocations.
(4) Should all of the foregoing conditions not pertain, it is Corps
policy to place beach-quality sand or other suitable material, dredged
by the Corps during construction and maintenance of Federal navigation
projects, onto beaches or nearshore waters, even though more costly than
alternative means of disposal, subject to the following:
(a) Placement on a beach or beaches must be requested by the
State in which the beach or beaches is located;
9
ER 1165-2-130
15 Jun 89
(b) A finding can be made that, regardless of evaluated
benefits, protection of the beaches involved is in the public interest;
(c) The placement must be environmentally acceptable, pursuant
to all applicable statutes and regulations;
(d) Local interests must pay 100 percent of the added cost of
disposal above the alternative least costly method of disposal; and
(e) Local interests must provide any necessary additional
lands, easements, rights-of-way, and relocations.
b. Geographic Applicability
. Shore erosion control, hurricane, and
abnormal tidal flooding authorities are applicable to the shores of the
Atlantic and Pacific Oceans, the Gulf of Mexico, the Great Lakes, the
estuaries and bays directly connected therewith of each of the States
(including the Federated States of Micronesia and the Marshall Islands),
the Commonwealths of Puerto Rico and Northern Marianas Islands, and the
Territories (U.S. Virgin Islands, Guam, American Samoa) of the United
States. Authority for shore erosion control activities extend only the
distance up tributary streams where it can be demonstrated that the
dominant causes of erosion and damage are ocean tidal action (or Gulf of
Mexico and Great Lakes water motion) and wind-generated waves. They
will not address erosion at upstream locations caused by streamflows or
vessels. Lake flood protection activities are generally limited to the
Great Lakes, or as otherwise specifically authorized under public law.
c. Coastal Zone Management Plans
. Project proposals shall be
consistent to the maximum practicable extent with approved State Coastal
Zone Management Programs developed under the authority of the Coastal
Zone Management Act of 1972, as amended.
d. Coastal Barrier Resources System
. Project proposals shall be
subject to compliance with the Coastal Barrier Resources Act of 1982.
e. Beach Creation
. Existing shore erosion control authority
provides for "restoration" and "protection." It does not provide for
Federal cost sharing in extending a beach beyond its historic shoreline
unless the extension is needed for engineering reasons to provide
protection from erosion or as otherwise specifically authorized under
public law.
f. Project Purposes
. Shore protection projects have been
authorized for a variety of purposes: beach erosion control,
shore/shoreline protection, hurricane/hurricane wave protection, and
storm protection. For cost sharing purposes, the benefits/outputs
associated with the foregoing project purposes will be reassigned to
conform to the appropriate purposes specified in Section 103(c) of P.L.
99-662 (normally, hurricane and storm damage reduction, and/or
recreation), and costs shared in the same percentage as the purposes to
which costs are assigned.
10
ER 1165-2-130
15 Jun 89
g. Shore Categories
. Three general categories of shore, based on
ownership and use, and incidence and type of benefits, must be
considered in determining the extent of Federal participation in shore
protection. These categories, and the levels of Federal participation
applicable thereto, are listed in Table 2, with the following
clarifications:
(1) Private Shores.
All costs assignable to benefits to
privately-owned shores, within or downdrift of physical project limits,
(where use of such shore is limited to private interests) are
non-Federal, except that benefits to private shores beyond project
limits, if trivial in amount, are considered incidental for cost sharing
purposes. Federal participation may be recommended for the protection
of developed private shores if the use of such shores is not limited to
private interests. Benefits from prevention of losses of developed
private lands are treated as storm damage reduction benefits.
(2) Losses of Private Lands
. All costs assigned to the
prevention of losses of undeveloped private lands (including privately-
owned marshes and wetlands) are non-Federal, even though the beach may
be public. Normally determinations of the market value for the land
losses will be based on the value of nearshore upland. Nearshore upland
is sufficiently removed from the shore to lose its significant increment
of value because of its proximity to the shore, when compared to
adjacent parcels that are more distant (inland) from the shore. Other
valuation methods are potentially acceptable, if it can be shown that
the use of nearshore values does not provide a realistic estimate of the
value of lost land.
(3) Federal Shores.
All costs assigned to the protection of
Federally-owned shores are Federal, and the Federal agency benefiting
from the project is responsible for these costs.
(4) Non-Federal Public Shores (Park and Conservation Areas)
.
Section 103 of the 1962 River and Harbor Act provided that under special
conditions, beach erosion protection of a state, county, or other
publically-owned shore park and conservation area is eligible for
Federal cost sharing up to 70 percent of the total project costs,
exclusive of land costs. The WRDA of 1986 discontinues this special
cost sharing. Evaluation of land loss benefits at non-Federal public
shores will reflect the special use to which the land is dedicated, and
the value of the output produced by that use. Consequently lands
dedicated to non-Federal park and conservation areas (including historic
parks and landmarks) will normally be valued on the basis of loss of
recreation outputs, with cost sharing 50/50, and Federal participation
limited by current Department of the Army policy. In cases where the
use of the land cannot be accurately calculated in economic terms, the
value of nearshore upland may be used (see paragraph 6.g(2) above). No
land loss benefit will be claimed for beach areas, or for shorefront
lands subject to temporary shoreline recessions.
11
ER 1165-2-130
15 Jun 89
TABLE 2 - PERCENT FEDERAL PARTICIPATION IN COSTS FOR SHORE PROTECTION BY
SHORELINE OWNERSHIP CATEGORY AND PROJECT BENEFITS
Shoreline Ownership Category (2) Federal Participation (%)
Project Benefits Construction(3) OM&R
I. Federally owned (4)
Hurricane ∧ Storm Damage Reduction 100 100
Land loss (12) 100 100
Recreation (Separable) (5) 100 100
II. Publicly owned and/or privately
owned with public benefits (6)(7)
Hurricane & Storm Damage Reduction (8) 65 (11) 0
Land loss (9)(10)(12) 50 (11) 0
Recreation (Separable) (5) 50 (11) 0
III.Privately owned
Hurricane & Storm Damage Reduction 0 0
Land loss (12) 0 0
Recreation (Separable) (5) 0 0
(1) The Corps does not recommend construction authorization
for shore protection projects that protect only one private property
owner, (profit or non-profit) (see paragraph 9.e(1)). The Corps may
recommend construction authorization for shore protection projects that
protect only one public owner, if the project is formulated and
justified in accordance with policies applicable to hurricane and storm
damage reduction. Federal funds will not be used to implement a project
with recreation benefits greater than 50 percent of total benefits
unless the project is economically justified based on (a) primary
project outputs alone (see paragraph 6.a(1) above), or (b) the
combination of reduced storm damages and an equivalent amount of
incidental recreation benefits.
(2) Shores which lie within recognized Indian Tribal
Reservations do not usually fall within categories. The status of such
lands will depend upon the particular treaty provisions pertaining to
the lands under consideration and will need to be examined in each
instance. Specific cases should be referred to CDR, USACE (CECW-P),
WASH DC, 20314-1000 for guidance.
(3) Where appropriate, periodic beach nourishment is
considered construction (see paragraph 7.e below).
12
ER 1165-2-130
15 Jun 89
(4) See paragraph 9.e(5) on protecting other Federal agency
shores and work for another Federal agency.
(5) Department of the Army policy precludes Civil Works
funding of separable recreation features at shore protection projects.
(6) Privately-owned shores under public control, as through a
sufficiently long-term lease assuring realization of public benefits
throughout the economic life of the project.
(7) See paragraph 9 below, concerning incidental protection of
privately-owned shores.
(8) Basic project may also include incidental recreation
benefits (i.e., inseparable from basic project purpose). Benefits from
prevention of loss of developed private lands are treated as storm
damage reduction benefits. Benefits from prevention of damages to
transportation facilities are considered as storm damage reduction
benefits.
(9) Non-Federal public shores dedicated to park (recreation;
historic/landmark) and/or conservation (fish and wildlife) uses.
(10) Adjusted by the ratio of public benefits along each
category of shore to total benefits along each category of protected
shore. Prevention of losses of undeveloped private lands is a private
benefit.
(11) These cost sharing percentages are applied to project
costs including the fair market value of LERRD.
(12) The Corps does not recommend construction of shore
protection projects where the benefits consist solely of land loss
prevention regardless of the number of owners.
h. Public Use
. Public use is a condition for Federal participation
in hurricane, abnormal tidal or lake flood protection projects. Current
shore erosion control law provides that "Shores other than public (i.e.,
privately owned) will be eligible for Federal assistance if there is a
benefit such as that arising from public use..." In the case of beaches
used for recreation, public use means use by all on equal terms. This
means that project beaches will not be limited to a segment of the
public. Unless the protection of privately-owned beaches is incidental
to protection of public beaches (paragraph 9), they must be open to all
visitors regardless of origin or home area, or provide protection to
nearby public property to be eligible for Federal assistance. Items
affecting public use are discussed below.
(1) User Fees
. A reasonable beach fee, uniformly applied to
all, for use in recovery of the local share of project costs is
allowable. Normal charges made by concessionaires and municipalities
for use of facilities such as bridges, parking areas, bathhouses, and
umbrellas are not construed as a charge for the use of the Federal beach
project, if they are commensurate with the value of the service they
provide and return only a reasonable profit. Fees for such services
must be applied uniformly to all concerned and not as a prerequisite to
beach use.
13
ER 1165-2-130
15 Jun 89
(2) Parking
. Lack of sufficient parking facilities for the
general public (including non-resident users) located reasonably nearby,
and with reasonable public access to the project, will constitute de
facto restriction on public use, thereby precluding eligibility for
Federal participation. Generally, parking on free or reasonable terms
should be available within a reasonable walking distance of the beach.
Street parking is not considered acceptable in lieu of parking lots
unless curbside capacity will accommodate the projected use demands.
Parking should be sufficient to accommodate the lesser of the peak hour
demand or the beach capacity. In some instances State and local plans
may call for a reduction in automobile pollutants by encouraging public
transportation. Thus, public transportation facilities may substitute
for or complement parking facilities. However, reports which consider
public transportation in this manner must indicate how the public
transportation system would be adequate for the needs of projected beach
users. In computing the public parking accommodations required, the
beach users not requiring parking should be deducted from the design
figure.
(3) Access
. Reasonable public access must be provided in
accordance with the recreational use objectives of the particular area.
However, public use is construed to be effectively limited to within
one-quarter mile from available points of public access to any
particular shore. In the event public access points are not within one-
half mile of each other, either an item of local cooperation specifying
such a requirement and public use throughout the project life must be
included in project recommendations or the cost sharing must be based on
private use.
(4) Beach Use by Private Organizations
. Federal participation
in private shores owned by beach clubs and hotels is incompatible with
the intent of the P.L. 84-826 if the beaches are limited to use by
members or paying guests.
(5) Public Shores With Limitations
. Publicly-owned beaches
which are limited to use by residents of the community or a group of
communities are not considered to be open to the general public and will
be treated as private beaches.
I. Improvements for Recreation
. Improvements to enhance the
recreational value of shore protection projects such as bathhouses,
access roads, toilet facilities, and parking areas are a local
responsibility. Provision of those facilities is not eligible for
Federal assistance through the Corps programs, and costs for those
facilities are not ordinarily included as project costs.
7. Federal Role in Project Development
.
a. Preauthorization Studies
. The Corps of Engineers may undertake
specific studies relating to shore erosion, hurricane, abnormal tidal
and lake flood problems with the authorization of Congress, either in
response to resolutions adopted by the Committee on Environment and
Public Works of the United States Senate or the Committee on Public
Works and Transportation of the House of Representatives, or by an Act
of Congress. Without specific Congressional authorization, the Corps
may initiate studies for projects, under the authorities of Section 103
of P.L. 87-874,
14
ER 1165-2-130
15 Jun 89
Section 111 of P.L. 90-483, and Section 14 of P.L. 79-526, as amended,
which comprise part of the Corps Continuing Authorities Program.
Reconnaissance studies are 100 percent Federally funded; feasibility
studies are conducted under a contract (Feasibility Study Cost Sharing
Agreement) providing 50-50 Federal/non-Federal cost sharing.
b. Postauthorization Studies
. Planning and engineering studies for
shore protection projects authorized under Section 105 (a) and 105 (b)
of P.L. 99-662 are conducted under a contract providing 50-50
Federal/non-Federal cost sharing. Evaluation studies for disposal of
materials dredged from navigation inlets and channels, during original
Federal improvement or maintenance, onto adjacent beaches under Section
145 of P.L. 94-587, as amended, will be initially financed by the Corps;
the cost of the evaluation report will be added to the separable
construction costs for placement of dredged material on beaches and cost
shared accordingly. (In the event the Corps financed evaluation study
does not result in placement of materials on beaches as requested by the
State, costs will be absorbed by the Federal Government.) Studies for
extension of beach nourishment periods under Section 934 of P.L. 99-662
will be initially financed by the Federal Government. If extension of
periodic nourishment is approved, the cost of preparing the reevaluation
reports will be shared in the same proportion as the allocation of
construction costs to the type of benefits accruing from the project.
The non-Federal sponsor will reimburse its share to the Federal
Government at the time of initial construction. Costs of
preconstruction engineering and design (PED) of a water resources
project are considered part of, and included in the total project cost,
and are cost shared in the same percentage as the basic purpose(s) of
the project. PED is initially financed by the Corps and reimbursed to
the Federal Government during the first year of construction (refer to
ER 1165-2-131). PED may include project performance monitoring for up
to five years after completion of initial construction. Guidance on
cost sharing of projects authorized in P.L. 99-662 for planning,
engineering, and design pursuant to Sections 105b and 105c is provided
in ER 1105-2-100.
c. Construction
. Construction of authorized projects is a
responsibility of the Corps of Engineers. However, local interests may
construct portions of projects, after they are authorized by Congress,
and be reimbursed by the Federal Government within the limitations of
Section 215 of the 1968 Flood Control Act, as amended, if prior approval
is obtained from the Chief of Engineers (refer to ER 1165-2-18 for
approval procedures and policies). If local interests desire to proceed
with construction of the projects, they may do so with the understanding
that:
(1) Federal participation would be limited to the Federal
shares of the costs of the elements constructed which are in accordance
with the authorized plan;
15
ER 1165-2-130
15 Jun 89
(2) Reimbursement will be subject to future appropriation of
funds applicable to the project and shall not take precedence over other
pending projects of higher priority; and,
(3) Local interests provide assurances that they bear any
increased costs of measures which may result from advance work, unless
there are extenuating circumstances which warrant omission of this
condition.
d. Maintenance
. Maintenance is generally a non-Federal
responsibility. However, if a portion of the benefited area is in
Federal ownership the Federal maintenance responsibility shall be
established as the same portion as the length of Federal shoreline is to
the length of total shoreline, provided costs are relatively uniform per
length of shore. In the case of multipurpose projects providing for
navigation, particularly those which involve complex operating
procedures, operation and maintenance responsibility for the entire
project might best be vested in the Federal Government. In such cases,
non-Federal interests should be obligated to contribute their share of
costs to the Federal Government on a scheduled basis throughout the
project life or to make a cash contribution of the capitalized value of
the non-Federal share of the maintenance cost. Future maintenance costs
are to be capitalized using the authorized discount rate.
e. Periodic Nourishment
. Periodic nourishment by placement of
suitable material on a beach at appropriate intervals of time, is
considered "construction" for cost-sharing purposes when, in the opinion
of the Chief of Engineers, such periodic nourishment would be a more
economical erosion protection measure than retaining structures such as
groins. Thus, projects recommending periodic nourishment should not
include structures which materially reduce littoral drift from reaching
downdrift shores. When sand replacement is proposed as a maintenance
measure, as for example when it would serve to maintain protection
accompanied by structures intended to confine the benefits of the sand
within a beach compartment rather than serving as a full or partial
alternative to such structures, Federal assistance toward its cost
should not be recommended, except to the extent warranted in paragraph
7d, above. Projects with short low-profile groins included to maintain
a shore alignment, but not to materially prevent littoral drift from
nourishing downdrift beaches are eligible for periodic nourishment.
Federal assistance for periodic nourishment may continue throughout the
economic life of the project, but a specified period of time up to 50
years after initiation of construction must be recommended in planning
reports. If there is reason to doubt the technical viability of
periodic nourishment for such a period of time, a shorter period may be
recommended. After that period, the project should be reexamined to
determine if Federal participation in periodic nourishment is the most
efficient and economic solution. Continuation of such Federal
participation beyond 50 years or other modification of the project
requires additional authorization. Prior to the expiration of the
16
ER 1165-2-130
15 Jun 89
nourishment period, the local sponsor will be notified that extension to
50 years is not automatic and that the sponsor must request the
extension and express willingness to cost share in accordance with P.L.
99-662.
8. Plan Formulation and Evaluation
.
a. Formulation
. Projects shall be formulated in accordance with
policies, principles, and procedures contained in ER 1105-2-100 and
related regulations (e.g., ER 200-2-2) describing the planning process
developed to implement the Water Resources Council's Principles and
Guidelines, the National Environmental Policy Act, EO 11988, EO 11990
and other requirements. Consideration shall be given to both structural
and nonstructural solutions. Plan formulation should be accomplished
systematically to arrive at the best solution, considering all factors,
including engineering, economic, environmental, and social.
b. Evaluation
. As required by ER 1105-2-100, effects of
alternatives will be determined and evaluated in terms of four accounts:
national economic development (NED); environmental quality (EQ);
regional economic development (RED); and other social effects (OSE).
Effects normally associated with hurricane and storm damage reduction
projects include but are not limited to the following. The impacts of
sea level rise on shore protection projects will be determined and
evaluated in accordance with guidance in ER 1105-2-100.
(1) Prevention of land loss and other physical damages;
(2) Reduction in maintenance costs of existing protection
works;
(3) Reduction of emergency costs to residences, businesses,
and governmental entities;
(4) Increased recreational usage, and where appropriate,
relief of overcrowding for existing recreational usage;
(5) Changes in maintenance costs associated with navigation
projects;
(6) Employment of unemployed or underemployed labor resources
for project construction;
(7) Prevention of loss of historic and scenic aspects of the
environment;
(8) Changes in shore processes and equilibrium conditions;
(9) Accretion or erosion along downdrift shores;
(10) Changes in tidal floodplain development;
(11) Changes in the extent and quantity of wetlands; and
17
ER 1165-2-130
15 Jun 89
(12) Changes in water quality and ecology in vicinity of
construction activities.
9. Cost Sharing
.
a. General Policy
. Prior to enactment of P.L. 99-662 (WRDA of
1986), shore protection legislation was directed to the prevention and
control of beach erosion with no explicit legislative definition of a
Federal responsibility in protecting against hurricane and storm damages
to the nation's coasts and shores of the Great Lakes. With enactment of
the WRDA of 1986, Congress established hurricane and storm damage
reduction as a project purpose to which costs should be assigned. Beach
erosion control is not recognized as a project purpose, but subsection
103(d) specifies that the costs of constructing beach erosion control
measures will be assigned to "appropriate" project purposes listed in
subsections 103(a), 103(b), and 103(c), with cost sharing in the same
percentage as the purposes to which the costs are assigned. The
appropriate project purposes are hurricane and storm damage reduction,
and recreation. Subsection 103(d) provides for two exceptions to this
sharing of assigned costs. First, costs assigned to benefits to
privately-owned shores (where use of such shore is limited to private
interests) are non-Federal costs. Second, costs assigned to benefits
from the prevention of losses of private (undeveloped) lands are to be
non-Federal, and all costs assigned to the protection of Federally-owned
shores are Federal.
b. Applicability
. The cost sharing requirements of the WRDA of
1986, as described below, are applicable to any project (including any
Continuing Authorities Program project which is not specifically
authorized by Congress and for which the Secretary had not approved
funding before 17 November 1986), or separable element thereof, on which
physical construction was initiated after 30 April 1986. Physical
construction means an action that physically alters the environment,
such as dredging beach fill, removing existing structures, or placing
beach fill. Physical construction is distinguished from the acquisition
of land, award of a construction contract, and subsequent mobilization
of contractor's equipment, all of which are accomplished before physical
construction can begin.
c. Policies Regarding Formulation, Evaluation and Cost Allocation
.
(1) Shore protection projects are to be formulated first to
provide for hurricane and storm damage reduction. Recreation associated
with this type of project is considered incidental for cost sharing
purposes, although recreation benefits are NED benefits to be included
in the economic analysis. Additional beach fill, over that required for
the hurricane and storm damage reduction project, to satisfy recreation
demand is a separable recreation feature.
(2) Costs for measures for the prevention of land losses are
assigned to either Federal or non-Federal interests depending upon shore
ownership. At non-Federal public shores dedicated to recreation,
18
ER 1165-2-130
15 Jun 89
historic, or fish and wildlife purposes, the cost of measures for the
prevention of loss of land are eligible for 50 percent Federal
participation.
(3) When the cost of construction per unit of benefited shore
length is not reasonably uniform for the entire project area, the
project should be subdivided into elements (reaches) within which this
condition is met. The first cost for H∧SDR measures for the
project, or each of the subdivided reaches, will then be allocated to
the various categories of directly benefited shore properties.
(4) Benefits to private shores beyond project limits, if
trivial in amount, may be omitted from cost sharing considerations. If
these benefits are significant (e.g., required for project
justification), they should be included in cost sharing considerations.
Where significant benefits accrue outside the project limits and the
non-Federal sponsor desires the recipients of these benefits to
contribute to the non-Federal share of the project costs, the
responsibility for negotiating with the recipients of the benefits rests
entirely with the non-Federal sponsor.
(5) Projects will be designed and implemented in the most cost
efficient manner (considering both Federal and non-Federal costs), using
appropriate engineering, economic, and environmental criteria. This
practice defines the alignment, size and location of project features
and LERRD requirements needed to make the project function in a safe and
reliable manner, independent of cost sharing determinations. From this
basic project design, the appropriate Federal and non-Federal
participation can then be calculated. The project area is normally
limited to the protected shore front area and does not usually include
the borrow area within its boundaries.
d. Cost Apportionment
. Federal participation in a project
formulated for hurricane and storm damage reduction is 65 percent of the
estimated total project first costs (including LERRD) assigned to this
purpose. Cost apportionment percentages for Federal participation in
shore protection by shore ownership and project benefit are given in
Table 2 (pg. 11). Non-Federal costs for a hurricane and storm damage
reduction project, or separable element, must be provided during the
period of construction.
(1) Lands, Easements, Rights-of-Way, Relocations, and Dredged
Material Disposal Areas (LERRD). Non-Federal interests must provide all
of the LERRD for shore protection projects, including borrow areas, at
non-Federally-owned shores. Generally, the fair market value of these
items (excluding the value of any publicly-owned beaches) is included in
the total project cost, and non-Federal interests receive a credit for
the value of these contributions against the non-Federal cost share.
However, the value of LER eligible for credit toward the non-Federal
share of shore protection project costs is that which is not subject to
loss through erosion in the without project condition. LER needed for
placement of shore protection project features that prevent the loss of
the land itself has no value for crediting purposes. The real estate
19
ER 1165-2-130
15 Jun 89
market may not however, reflect this and a project sponsor may in fact
incur costs in acquiring requisite interests. Accordingly, a sponsor
will be credited for his actual costs or for the net reduction in total
market valuation of the parcels (from which interests for the project
must be drawn) assuming no Federal project compared to assuming the
project in place (i.e., including consideration of special benefits to
the property owners), whichever is least.
(2) Additional Cash Contribution
. When the fair market value
of the LERRD items assigned to a project purpose is less than the
appropriate non-Federal percentage of the total first cost assigned to
that purpose (i.e., hurricane and storm damage reduction - 35%;
recreation (separable) - 50%; prevention of loss of land: Federal
shores - 0%; non-Federal public shores - 50%; private shores - 100%).,
the difference must be provided by non-Federal interests as a cash
contribution during construction.
(3) Limitation
. When the fair market value of the LERRD items
assigned to a project purpose exceeds the appropriate percentage of the
total first cost assigned to that purpose, as specified in paragraph
9.d(2) above, the non-Federal share is limited to that percentage, and
the excess will be reimbursed by the Federal government after completion
of project construction. Guidance on the mechanism for funding the
value of LERRD that exceeds the appropriate percentage is contained in
ER 1165-2-131.
(4) Credit for Borrow Areas
. Contractors will normally obtain
material for the project from available sources, subject to Corps
specifications and approval. In some cases (e.g., limited competition)
a borrow area source may be specified by the Corps.
(a) When a borrow area is provided by the sponsor as part
of its LERRD requirements, the resource invested by the sponsor and
available for credit against its non-Federal cost-sharing
responsibilities is the net cost of the borrow area, after deducting the
residual land value from the original acquisition cost. Only the net
cost should be included in project evaluations and credited against the
non-Federal cost-sharingresponsibilities. If a sponsor makes available
borrow already in its ownership, the net value for crediting purposes
will be established on the basis of borrow area appraisals before and
after use for project borrow.
(b) Where borrow materials can be more economically
obtained from nearby commercial sources, local provision of a borrow
area is not required. The Corps designates for the contractor what
sources will be acceptable and the contractor makes appropriate
arrangements. In such case, there are no related LERRD costs and the
material costs include the contractor's payment to the supplier for the
material and a delivery charge, if the supplier delivers, or the
contractors cost for hauling to the project site if the contractor loads
the material onto his equipment at the supply site.
20
ER 1165-2-130
15 Jun 89
(C) Where borrow materials can be more economically
obtained from offshore sources, no credit will normally be given since
the before and after market values are considered identical.
(5) Operation, Maintenance, Replacement and Rehabilitation
(OMRR). Non-Federal interests are responsible for 100 percent of the
OMRR costs for shore protection projects and separable elements.
(6) Periodic Nourishment. Placement of sand on a beach at
suitable intervals of time is considered "construction" for funding and
cost-sharing purposes when it is more efficient and economical than
other methods of controlling erosion. Periodic nourishment should be
thought of as an alternative to construction of expensive seawalls and
groinfields and as staged construction of a beach. Sand-
bypassing/backpassing plants, which operate essentially on a continual
basis requiring annual funding, are normally considered operation and
maintenance (a non-Federal responsibility for beach erosion control
projects) and not staged construction. However, periodic nourishment
may include a sand-bypassing/backpassing plant, if the
bypassed/backpassed sand would substitute for sand which would be placed
on the beach as part of an existing Federal periodic nourishment
project, and if the cost of constructing and operating the
bypassing/backpassing plant would be more economical than other methods
of nourishing the beach. Recommendations for Federal involvement in
periodic nourishment using a sand-bypassing/backpassing plant will be
limited to the remaining life of an existing periodic nourishment
project. Section 934 of P.L. 99-662 will not, in such cases, be used to
extend the period of authorized periodic nourishment of such projects.
e. Policies Limiting Corps of Engineers Participation
.
(1) Single Property Owner Situations
. Federal participation
in the construction and/or costs of any shore protection project
presumes that the proposed shore protection project would protect more
than one property owner (public and/or private). In the event the
proposed shore protection project would protect only one private
property owner (profit or non-profit), the Corps would not recommend
construction authorization. If the proposed shore protection project
would protect only one public owner, the Corps may recommend
construction authorization if the project is formulated and justified in
accordance with policies applicable to hurricane and storm damage
reduction.
(2) Land Loss Prevention Benefits
. If the benefits for the
shore protection project consist solely of land loss prevention (i.e.,
no buildings or facilities subject to damage), recommendations for
Federal participation will not be made regardless of the number of
owners.
(3) Public Ownership and Use
. Section 103(d) of the WRDA of
1986 prohibits Federal participation in costs assigned to benefits to
privately-owned shores where the use of such shores is limited to
private interests. Non-Federal interests must, therefore, assure
continued conditions of public ownership and use of the shore upon which
the amount
21
ER 1165-2-130
15 Jun 89
of Federal participation is based during the economic life of the
project. Non-Federal interests must also provide and maintain necessary
access roads, parking areas and other public use facilities open and
available to all on equal terms. Specific cases may also warrant
assigning other additional local responsibilities, such as providing
appurtenant facilities required for realization of recreational
benefits.
(4) Federal Budgetary Resources
. Department of Army policy
precludes the use of Army Civil Works resources for implementing
recreation-oriented projects as part of the Civil Works program. Civil
Works funds normally may be used to support development of recreation
when recreation benefits are less than 50 percent of total project
benefits. In addition, recreation benefits must result from development
of recreation potential created by projects formulated for and justified
by other primary purposes. Exceptions to this 50 percent limit on
recreation benefits will be granted if a project is economically
justified by: (a) benefits from reduced storm damages alone, or (b) a
combination of reduced storm damages and incidental recreation benefits
limited to an equivalent amount of storm damage reduction benefits (see
Cases 2 and 3, Table 1, page 8; para. 6.a(1), pages 6 and 7). The
allocation or assignment of costs for projects granted exception to this
policy, will be on the basis of the benefits formulated for the project,
and not influenced by this arbitrary test to determine qualification for
an exception.
(5) Other Federal Agency Lands
. Costs for shore protection
for lands controlled by another Federal agency (for example, military
installations and National Park Service lands) will be borne by that
agency. The Corps will accomplish such work on a reimbursable basis
upon request. One exception would be a case wherein the lands in
question involve only a minor, but integral, part of the overall
protection frontage. In such case, protection would be included at
Federal cost using Civil Works funds to assure a complete overall
project.
(6) Exception for the Territories
. Local cost sharing
requirements for all studies and projects in American Samoa, Guam, the
Northern Mariana Islands, the Virgin Islands, and the Trust Territory of
the Pacific Islands, will be reduced by an amount not to exceed
$200,000, for each study and each project, in accordance with Section
1156 of the WRDA of 1986. Cost sharing for each study and/or project
will be established using the general cost sharing criteria, and the
non-Federal share will then be reduced by $200,000, or to zero if the
non-Federal share is less than $200,000. These reductions will not
raise the individual project ceilings for Federal participation
specified in Section 915 of the WRDA of 1986.
(7) Trust Territory of the Pacific Islands
. Although Section
915(h) of P.L. 99-662 authorizes use of the Section 103 (P.L. 87-874)
and Section 111 (P.L. 90-483) authorities, under current budget
instructions funds are not to be expended in this region due to changing
governmental status.
22
ER 1165-2-130
15 Jun 89
f. Emergency Authorities
.
(1) The cost sharing in Section 103 of P.L. 99-662 does not
apply to emergency operations and disaster assistance under P.L. 84-99,
as amended. However, cost sharing under Section 103 of P.L. 99-662
would apply to measures that may be required to restore the protective
function/level of a shore protection project prior to the onset of the
storm season or following a storm which exceeded design storm conditions
but did not necessitate action under P.L. 84-99.
(2) The flood control cost sharing in Section 103(a) of P.L.
99-662 is applicable to recommendations under Section 14 of the 1946
Flood Control Act, as amended.
g. Multiple-Purpose Projects
. For multiple-purpose hurricane and
storm damage reduction and recreation projects having separable
recreation facilities, Federal cost sharing in the recreation purpose is
limited to 50 percent of the construction costs of the separable
recreation facilities, while OM∧R thereof is a non-Federal
responsibility in accordance with Sections 103(c) and 103(j) of P.L. 99-
662. However, Federal funds will not be used to implement the separable
recreation elements of a multiple-purpose project in accordance with
current Department of the Army budget priorities.
h. Related Dredged Material Disposal
. Federal participation in the
disposal of dredged material from construction and maintenance of
Federal navigation projects onto adjacent beaches or in nearshore water
is limited to a maximum of 50 percent of the incremental costs above the
least costly and environmentally sound method for the disposal of the
dredged materials (see paragraph 6.a(3)). FOA's must complete a report
providing a cost analysis supporting the least costly alternative method
of disposal of dredged material and other documentation and analyses to
meet the criteria set forth in paragraph 6.a(3).
10. Local Cooperation Requirements
. Reporting officers must obtain a
letter of intent from a public agency, authorized under State law, to
fulfill the non-Federal obligations of water resources projects
recommended for Federal participation. The letter will indicate that
prior to construction, the sponsor will enter into a written Local
Cooperation Agreement (LCA), as required by Section 221 of P.L. 91-611,
as amended, to provide local cooperation satisfactory to the Secretary
of the Army. Such local cooperation will include the following
non-Federal responsibilities in addition to the responsibility for
fulfilling the requirements of law for the recommended project:
a. Provide to the United States all necessary lands, easements,
rights-of-way, relocations, and suitable borrow and/or disposal areas
required for construction and subsequent maintenance of the project,
including that required for periodic nourishment.
23
ER 1165-2-130
15 Jun 89
b. Hold and save the United States free from claims for damages
which may result from construction and subsequent maintenance,
operation, and public use of the project, except damages due to the
fault or negligence of the United States or its contractors.
c. Maintain continued public ownership and public use of the shore
upon which the amount of Federal participation is based during the
economic life of the project (normally 50 years).
d. Maintain and repair the protective measures and/or structures
during the economic life of the project as required to serve the
intended purposes at their design levels of hurricane and storm damage
protection and in accordance with regulations prescribed by the
Secretary of the Army (see ER 1110-2-1407 for specification of O&M
requirements and provision of an O&M manual).
e. Provide and maintain necessary access roads, parking areas and
other public use facilities open and available to all on equal terms.
f. Participate in and comply with applicable Federal flood plain
management and flood insurance programs prior to initiation of
construction and during the economic life of the project.
g. Contribute in cash the appropriate percentage of project
construction cost (computed from the policies given in paragraph 9), the
percentage to be in accordance with existing law and based on shore
ownership and use at the time of implementation, provided that credit
will be given for the value of lands, easements, rights-of-way and
relocations.
h. Contribute the local share of periodic beach nourishment, where
and to the extent applicable (up to 50 years) as required to serve the
intended purposes.
i. Specific cases may also warrant assigning other additional local
responsibilities, such as: providing appurtenant facilities required
for realization of recreational benefits.
11. Local Cooperation Standard Wording
. The wording given in
paragraphs 10.a through 10.h should be considered standard for all
recommended plans which include hurricane and storm damage reduction as
a plan purpose. In the case of dredged material disposal, the wording
in paragraphs 10.c and 10.e, in addition to the contributions required
by paragraphs 6.a(3) and 9.d, should be considered standard for all
recommended plans. Deviations from such wording should not be made
unless the reporting officer has justifiable circumstances warranting
such action.
12. Local Cooperation Agreements
. Any project or separable element
subject to the cost sharing provisions of P.L. 99-662 shall be initiated
only after non-Federal interests have entered into binding agreements
24
ER 1165-2-130
15 Jun 89
(LCA's) with the Secretary of the Army covering the appropriate items of
local cooperation described above. All agreements must comply with the
policies governing Federal and non-Federal financing and payments
included in ER 1165-2-131.
FOR THE CHIEF OF ENGINEERS:
ALBERT J. GENETTI, JR.
Colonel, Corps of Engineers
Chief of Staff
3 Appendices
APP A - Definitions of Terms Used in ER
APP B - Synopsis of Program Legislation
APP C - Example of Computations for Cost Sharing
A-1
ER 1165-2-130
15 Jun 89
APPENDIX A - Definitions of Terms Used in ER
1. "Beach" - the zone of unconsolidated material that extends landward
from the low water line to the place where there is marked change in
material or physiographic form, or to the line of permanent vegetation.
2. "Coastal area" - the land and water area bordering the shore.
3. "Construction costs" - the project first costs associated with
initial construction or periodic nourishment (paragraph 7e) including
the costs of lands, easements, rights-of-way, relocations, and
disposal/borrow areas (LERRD), and engineering and design and
supervision and administration (E∧D and S∧A).
4. "Historical shoreline" - the most seaward position of the mean high
water or mean higher high water position recorded by previous surveys or
interpreted from previous photographs, other historical records, or
other sufficiently reliable sources to permit comparison with the
present position.
5. "Hurricane and abnormal tidal flooding" - inundation from abnormal
rises and water levels due to hurricanes, storms, and tsunami.
6. "Incidental recreation benefits" - recreation benefits generated by
a basic project designed for some other primary purpose (e.g., hurricane
and storm damage reduction) which do not require construction of any
additional, incremental or separable recreational features (i.e.,
jointly produced).
7. "Investment costs" - the total costs of initially constructing a
project including E∧D and S∧A, LERRD and interest during
construction (IDC). Guidance on computation of IDC is provided in ER
1105-2-100.
8. "Lake flooding" - storm-induced inundation superimposed on the
ordinary fluctuations of the lake level, or inundation from abnormal
rises in static water level due to climatological changes (e.g.,
extended periods of abnormal precipitation, temperatures and/or
humidity) or tectonic changes.
9. "Land loss prevention benefits" - benefits from prevention of public
and/or private land loss due to shore erosion. Prevention of losses of
developed private land should be categorized as storm damage reduction
benefits. Prevention of losses of undeveloped private land (including
privately-owned marshes or wetlands) is a benefit category in which
there is no Federal interest (i.e., non-Federal interests are assigned
all costs of preventing losses of undeveloped private land), even though
the shore may be public. Prevention of loss of Federal and/or
non-Federal public land will reflect the special use to which the land
is dedicated and the value of the output produced by that use (e.g.,
lands dedicated to non-Federal park and conservation areas will normally
be valued on the basis of loss of recreation output).
A-2
ER 1165-2-130
15 June 89
10. "Maintenance" - periodic replacement or repair of the
measures/structures comprising a shore protection project, including
sand relocation and profile reshaping (i.e., moving sand laterally along
and perpendicular to shore, respectively), but excluding periodic beach
nourishment that is incorporated in the project as deferred
construction. Includes sand relocation and reshaping, and sand
replacement to the extent that it serves to maintain protection
accompanied by structures intended to confine benefits of the sand
within a beach compartment (rather than serving as an alternative to
such structures).
11. "Periodic nourishment" - fill placed at intervals of time to
replenish material eroded from the design beach section of a beach
erosion control project which is eligible for Federal participation as
deferred construction (paragraph 7e).
12. "Public benefits" - benefits resulting from public recreational use
and the prevention of damage to publicly-owned facilities such as
highways, buildings, parks, boardwalks, etc.
13. "Publicly owned" - ownership by a State, municipality, or other
political subdivision. Federal ownership is not included within) this
definition since Federal participation (cost sharing percentages) in
beach erosion control measures along Federal shores and publicly-owned
shores differ (see Table 2, page 16).
14. "Public use" - available for use by any and all of the general
public on equal terms.
15. "Separable recreation benefits" - recreation benefits generated by
construction of any additional, incremental or separable recreational
features associated with a basic project designed for some other primary
purpose (i.e., not jointly produced).
16. "Shore" - land adjacent to and in immediate contact with a body of
water, including the zone between high and low water lines. A shore of
unconsolidated material is usually called a beach.
17. "Shore restoration or protection" - measures or projects designed
to stabilize and/or restore shores, and/or to prevent or reduce damages
caused by erosion, flood, and wave impact due principally to storm tide
levels and wave action, including wave setup and runup in coastal areas.
The terms "shore restoration and protection" and "beach erosion
control" are used interchangeably.
18. "Storm damage reduction benefits" - benefits from prevention of
damages to Federal and public property and facilities (i.e., lands
and/or structures, except non-Federal public lands dedicated to park and
conservation uses) and developed private property and facilities due to
shore erosion and/or tidal inundation. Prevention of losses to private
undeveloped land should be categorized separately since there is no
Federal interest in this benefit category.
B-1
ER 1165-2-130
15 Jun 89
APPENDIX B - Synopsis of Program Legislation
SHORE PROTECTION
1. P.L. 71-520 (1930)
. Section 2 authorizes the Chief of Engineers to
conduct shore erosion control studies in cooperation with appropriate
agencies of various cities, counties, or States. Amended by Section
103, P.L. 86-645. Section 2 also established the Beach Erosion Board.
Amended by P.L. 88-172.
2. P.L. 79-526 (1946)
. Section 14 authorizes emergency bank-protection
works to prevent flood damage to highways, bridge approaches and public
works. Amended by P.L. 93-251 and P.L. 99-662.
3. P.L. 79-727 (1946)
. Establishes Federal policy to assist in the
construction, but not maintenance, of works to protect publicly-owned
shores of the United States against erosion from waves and currents.
Amended by P.L. 84-826, P.L. 87-874, and P.L. 91-611.
4. P.L. 84-99 (1955)
. Authorizes the Chief of Engineers to provide
emergency protection to threatened Federally authorized and constructed
hurricane and shore protection works, and to repair or restore such
works damaged or destroyed by wind, wave, or water action of other than
an ordinary nature.
5. P.L. 84-826 (1956)
. Expands the Federal role by authorizing Federal
participation in the cost of works for protection and restoration of the
shores of the United States, including private property if such
protection is incidental to the protection of publicly-owned shores, or
if such protection would result in public benefits. It also provides
for Federal assistance for periodic nourishment on the same basis as new
construction, for a period to be specified by the Chief of Engineers,
when it would be the most suitable and economical remedial measure.
Amended by Section 156, P.L. 94-587, and Section 934 of P.L. 99-662.
6. P.L. 86-645 (1960)
. Section 103 amends Section 2, P.L. 71-520, and
authorizes the Chief of Engineers under the direction of the Secretary
of the Army to conduct shore erosion prevention studies in cooperation
with the appropriate agencies of various coastal States, the
Commonwealth of Puerto Rico and possessions of the United States.
7. P.L. 87-874 (1962)
. Section 103 increases the proportion of
construction costs borne by the Federal Government for beach erosion
control and shore protection projects. Section 103 authorizes the
Secretary of the Army, acting through the Chief of Engineers, to plan
and construct small beach erosion control projects within certain limits
without specific Congressional authorization. Amended by Section 112,
P.L. 91-611 and Section 915(e), P.L. 99-662. Implementing policies and
procedures for this authority can be found in ER 1105-2-100.
B-2
ER 1165-2-130
15 Jun 89
8. P.L. 88-172 (1963)
. Abolished the Beach Erosion Board, transferred
its review functions to the Board of Engineers for Rivers and Harbors
(BERH), and established the Coastal Engineering Research Center.
9. P.L. 89-72 (1965)
. Requires that planning of water resources
projects consider opportunities for outdoor recreation and fish and
wildlife enhancement. The Act specifies that outdoor recreation
benefits that can be attributed to a project shall be taken into account
in determining the overall benefits of a project (e.g., recreational use
of beach fill, groins or other shore protection structures).
10. P.L. 90-483 (1968)
.
a. Section 111 authorizes the Secretary of the Army, acting through
the Chief of Engineers, to study, plan, and implement structural and
nonstructural measures for the mitigation of shore damages attributable
to Federal navigation works. This authority applies to both public and
privately-owned shores along the coastal and Great Lake shorelines.
Amended by Sections 915 (f) and 940, P.L. 99-662. Implementing policies
and procedures for this authority may be found in ER 1105-2-100.
b. Section 215 authorizes the Secretary of the Army, acting through
the Chief of Engineers, to enter into agreements providing for
reimbursement to States or political subdivisions for work to be
performed by them at authorized Federal projects. Unless specifically
authorized by Congress, reimbursement for work commenced by local
interests subsequent to 13 August 1969 is to be made in accordance with
these authorities. Amended by Section 913, P.L. 99-662. Implementing
policies and procedures can be found in ER 1165-2-18.
11. P.L. 92-583 (1972)
. Section 307 of the Coastal Zone Management Act
requires all Federal agencies with activities directly affecting the
coastal zone, or with development projects within that zone, to assure
that those activities or projects are consistent with the approved State
program.
12. P.L. 93-251 (1974)
.
a. Section 27 raised the cost limits for emergency bank protection
projects to $250,000 and program fiscal funding limit to $10 million per
year. Project purpose was extended to cover construction, repair,
restoration and modification of emergency streambank and shoreline
protection works. Eligibility definition was extended to include
churches, hospitals, schools and similar non-profit public services.
Amended by Section 915(c) of P.L. 99-662.
b. Section 55 authorizes the provision of technical and engineering
assistance to non-Federal public interests in developing structural and
nonstructural methods of preventing damages attributable to beach
erosion.
B-3
ER 1165-2-130
15 Jun 89
13. P.L. 94-587 (1976)
.
a. Section 145 authorizes the Secretary of the Army, acting through
the Chief of Engineers, to place beach-quality sand obtained from
construction and maintenance dredging of navigation inlets onto adjacent
beaches, providing such placement is requested by the interested State
Government, is in the public interest, and local interests pay 100
percent of any increased costs above the cost required for alternative
methods of disposing of such sand that would be used in the absence of
beach disposal. Amended by Section 933, P.L. 99-662.
b. Section 156 authorizes the Secretary of the Army, acting through
the Chief of Engineers, to extend Federal participation in periodic
beach nourishment, where such nourishment has been authorized for a
limited period, up to 15 years from the date of initiation of
construction. Amended by Section 934, P.L. 99-662.
14. P.L. 97-348 (1982)
. Establishes policy that coastal barrier
islands and their associated aquatic habitats are to be protected by
restricting Federal expenditures which have the effect of encouraging
development of coastal barriers. The Act provides for a Coastal Barrier
Resources System (the extent of which is defined by a set of maps
approved by Congress on 30 September 1982) which identifies undeveloped
coastal barriers within which Federal expenditures (including
expenditures for flood insurance, roads, bridges, shoreline structures)
may not be made. Specific exceptions to the expenditure prohibition
include navigation, beach nourishment, and research works.
15. P.L. 99-662, Water Resources Development Act (WRDA) of 1986.
a. Section 101(c) provides that costs of constructing projects or
measures for the prevention or mitigation of erosion or shoaling damages
attributable to Federal navigation works shall be shared in the same
proportion as the cost sharing provisions applicable to the project
causing such erosion or shoaling. The non-Federal interests for the
project causing the erosion or shoaling shall agree to operate and
maintain such measures. Also see Section 940 of P.L. 99-662 (page
B-5).
b. Section 103(d) specifies that the costs of constructing projects
for beach erosion control must be assigned to selected project purposes
such as hurricane and storm damage reduction, and/or recreation. Cost
sharing for these project purposes is specified in Section 103(c).
However, all costs assigned to benefits to privately-owned shores (where
use of such shores is limited to private interests), or to prevention of
losses of private lands are a non-Federal responsibility. All costs
assigned to protection of Federally-owned shores are a Federal
responsibility.
B-4
ER 1165-2-130
15 Jun 89
c. Section 103(i) specifies that non-Federal interests shall provide
all lands, easements and rights-of-way, and disposal areas required and
perform all necessary relocations (LERRD). The value of LERRD is
credited to the non-Federal share of the project cost.
d. Section 501 authorizes construction and preconstruction planning,
engineering, and design (PED) of various projects for shoreline
protection, beach erosion control, shore and hurricane wave protection,
and beach erosion control and hurricane protection, subject to various
conditions such as determination that construction will be in compliance
with the Coastal Barrier Resources Act (P.L. 97-348).
e. Section 502 directs the Secretary of the Army to apply the cost
sharing provisions of Section 31(1), P.L. 93-251, to periodic
nourishment of the continuing construction project at Westhampton Beach,
New York, for a period of 20 years after 17 November 1986.
f. Section 706 (Great Lakes Levels Study) authorizes the Secretary
of the Army, to conduct a cooperative study of shoreline protection and
beach erosion control policy and related projects of the Secretary in
view of existing high lake levels and long-term expected increases in
the levels of the Great Lakes.
g. Section 713 (Louisiana Shoreline Erosion Study) authorizes the
Secretary of the Army to conduct a nearshore sediment inventory to
determine availability of suitable sediment in the offshore waters of
Louisiana between Southwest Pass and Sabin Pass, and in Lake
Pontchartrain and in Lake Borgne, and to determine the feasibility of
specific measures to diminish shoreline erosion, marsh deterioration,
salt water intrusion, hurricane vulnerability, and barrier island
destruction and to carry out reasonable planning efforts that require
suitable sediment for nourishment.
h. Section 731 (Study of Rising Oceans) authorizes the Secretary of
the Army to conduct a cooperative study of shoreline protection and
beach erosion control policy and related projects of the Secretary in
view of the prospect for long-term increases in the levels of the ocean.
i. Section 732 (Shoreline Erosion Damage on Lake Superior) directs
the Secretary of the Army to determine the extent of shoreline erosion
damage in the United States causally related to the regulation of the
waters of Lake Superior by the International Joint Commission United
States and Canada subsequent to an emergency application by the United
States made on 26 January 1973.
j. Section 913 increases Federal reimbursement up to $3 million for
work accomplished under Section 215(a) of P.L. 90-483.
B-5
ER 1165-2-130
15 Jun 89
k. Section 915(c) increases the Federal limits up to $500,000 for
participating in emergency shoreline protection of public works (Section
14) projects. Section 915(e) increases the Federal limits up to $2
million for participating in small beach erosion control (Section 103)
projects. Section 915 (f) increases the Federal limits up to $2 million
for participating in mitigation of shore damage attributable to Federal
navigation works (Section 111) projects. Section 915 (h) of P.L. 99-662
authorizes use of the Section 103 (P.L. 87-874) and Section 111 (P.L.
90-483) authorities in the Trust Territory of the Pacific Islands.
l. Section 925 (Compilation of Laws) directs the Secretary of the
Army to compile and publish the laws of the United States relating to
beach erosion and other water resources development enacted after 8
November 1966 and before 1 January 1987.
m. Section 933 increases to 50 percent the proportion that may be
borne by the Federal Government of the additional costs, above that
required for alternative methods for disposal, for placement of material
dredged during the construction and maintenance of navigation inlets
onto adjacent beaches.
n. Section 934 increases to 50 years the authorized period of time
Federal participation can be extended in periodic beach nourishment
after the date of initiation of construction.
o. Section 935 authorizes the Secretary of the Army to acquire fill
material for beach erosion and beach nourishment by purchase, exchange,
or otherwise from nondomestic sources for authorized water resources
projects needing such materials, if they are not available from domestic
sources for environmental or economic reasons.
p. Section 940 increases the Federal cost limits for participating
in mitigation of shore damage caused by Federal navigation works to $2
million, and requires a non-Federal public body to operate and maintain
such measures. Structural and non-structural measures can be
implemented under the Section 111 authority of P.L. 90-483,
andimplementation costs will be shared in the same proportion as the
cost-sharing provisions applicable to the original project,
includingprojects constructed at full Federal expense.
16. P.L. 100-676, Water Resources Development Act (WRDA) of 1988.
Section 14 amends Section 402 of the 1986 WRDA to require non-Federal
interests to agree to participate in and comply with applicable Federal
flood plain management and flood insurance programs before construction
of any hurricane and storm damage reduction project.
B-6
ER 1165-2-130
15 Jun 89
HURRICANE AND ABNORMAL TIDAL FLOOD PROTECTION
1. P.L. 84-71 (1955)
. Authorizes the Secretary of the Army, in
cooperation with the Secretary of Commerce and other Federal agencies
concerned with hurricanes, to make studies of the Atlantic and Gulf
coasts of the United States to secure data on the behavior and frequency
of hurricanes and to determine means of preventing loss of life and
damages to property. This Act does not specify any cost sharing for
construction of protective works.
2. P.L. 84-99 (1955)
. Authorizes the Chief of Engineers to provide
emergency protection to threatened Federally authorized and constructed
hurricane and shore protection works, and to repair or restore such
works damaged or destroyed by wind, wave, or water action of other than
an ordinary nature.
3. P.L. 85-500 (1958)
. Section 203 added provisions of local
cooperation to three hurricane flood protection projects authorized
under this Act: non-Federal interests were required to assume 30
percent of total first costs, including the value of lands, easements
and rights-of-way, and to operate and maintain the projects.
4. P.L. 91-611 (1970)
. Section 208 authorized Federal participation in
hurricane protection projects up to 70 percent of the total cost
exclusive of land costs.
5. P.L. 99-662 (1986)
. Section 103(c)(5) requires non-Federal
interests to assume 35 percent of the cost assigned to the hurricane and
storm damage reduction purpose of a project.
6. P.L. 100-676, Water Resources Development Act (WRDA) of 1988.
Section 14 amends Section 402 of the 1986 WRDA to require non-Federal
interests to agree to participate in and comply with applicable Federal
flood plain management and flood insurance programs before construction
of any hurricane and storm damage reduction project.
LAKE FLOOD PROTECTION. The Federal interest in projects for lake flood
protection is not clearly defined by legislation.
1. Section 401(e)(4), P.L. 99-662, authorizes the Secretary of the Army
to construct dikes along the west side of the Great Salt Lake, Utah,
which rose above record levels in June 1986. These dikes are part of a
State plan to control lake level and flood damages. The non-Federal
share of the cost of those authorized dikes is specified as 25 percent
in the Act.
2. Section 706, P.L. 99-662, authorizes the Secretary of the Army to
conduct a cooperative study of shoreline protection and beach erosion
control policy and related projects of the Secretary in view of the
situation in 1986 and expected long-term increases in the levels of the
Great Lakes. This study will include recommendations for new or
additional criteria for Federal participation in shoreline protection
projects along the Great Lakes and connecting channels.
C-1
ER 1165-2-130
15 Jun 89
APPENDIX C - Example Computations for Cost Sharing on a
Hurricane and Storm Damage Deduction Project
PUblic
PUblic
or
Private
Shore
ownership
Shores
Private
Shores Shores
Devel'd Devel'd
Non-Fed.
Public
No
Pub.
Not
Federal
(Park)
Use
Use
Devel
1
d
:Reach
1 2
3 4 5
LeMth
(1)
1,000
5,000
10,000
3,000
1,000
Benefits
Damaqe
:Reduction
Facilities
$2,000
$2,000(3)
$13,000
$4,000
$0
Land
Loss
3,000
4,000
3,000(4)
1,000(4)
3,000
:Recreation
(2)
(2,000)
(9,000)
(7
,000)
0
0
Total
$5,000
$6,000
$16,000
$5,000
$3,000
Federal
Share:
:Reach 1
11000
X
100%
=
o.oso
20,000
:Reach 2
51000
X
SO%
=
0.125
20,000
:Reach 3
101000
X
65%
=
0.325
20,000
:Reach 4
31000
X
0%
=
o.ooo
20,000
:Reach 5
11000
X
0%
=
o.ooo
20,000
Total
Federal
Share
=
o.soo
or
50%
(1)
Assumes
a
relatively
linear
distri.bution
of
costs.
(2)
No
costs
assigned
to
recreation
(benefits
incidental).
(3)
Assumes
facilities
subject
to
damaqe
serve
recreation
use.
(4)
Land
CXIDpOJlent
of
developed
properties
subject
to
damage.
Total
20,000
$21,00(
14,001
(18,00
$3S,OC