Tables of Fees
TABLE 1
FEES FOR APPLICATIONS FOR PLANNING PERMISSION AND FOR APPLICATIONS FOR APPROVAL,
CONSENT OR AGREEMENT REQUIRED BY A CONDITION IMPOSED ON A GRANT OF PLANNING
PERMISSION IN PRINCIPLE
Category of development
Fee payable
RESIDENTIAL DEVELOPMENT
(a) where the number of dwellinghouses to be created by the
development does not exceed 10, £600 for each dwellinghouse,
(b) where the number of dwellinghouses to be created by the
development is fewer than 50, £600 for the first 10 dwellinghouses, and
£450 for each dwellinghouse thereafter,
(c) where the number of dwellinghouses to be created by the
development is 50 or more, £600 for the first 10 dwellinghouses, £450 for
each dwellinghouse in excess of 10 up to 49 dwellinghouses, and £250
for each dwellinghouse in excess of 50, subject to a maximum total of
£150,000.
New dwellings
1. Construction of buildings, structures or erections for use as
residential accommodation (other than development within
categories 2 to 6).
Existing dwellings
2. The carrying out of operations which will result in the
enlargement, improvement or other alteration of an existing
dwelling.
Where the application relates to
(a) one dwelling, £300,
(b) 2 or more dwellings, £600.
3.
(a) The carrying out of operations, including the erection of a
building within the curtilage of an existing dwellinghouse, for
purposes ancillary to the enjoyment of the dwellinghouse as
such, or
£300.
(b) the erection or construction of gates, fences, walls or other
means of enclosure along a boundary of the curtilage of an
existing dwellinghouse.
£300.
OFFICIAL
OFFICIAL
Category of development
Fee payable
NON-RESIDENTIAL BUILDINGS
4. The construction of buildings, structures or erections including
extensions (other than construction within categories 1, 5, and 6).
(a) where no floor area is created or the gross floor space created does
not exceed 50 square metres, £300,
(b) where the gross floor space created exceeds 50 square metres, £600
in respect of any gross floor space up to 100 square metres,
(c) where the gross floor space exceeds 100 square metres, £600 plus
£600 per 100 square metres in respect of any gross floor space
exceeding 100 square metres and up to 4,000 square metres,
(d) where the gross floor space exceeds 4,000 square metres, £24,000
plus £300 per 100 square metres in respect of any gross floor space
exceeding 4,000 square metres, subject to a maximum of £150,000,
(e) where no buildings are to be created, £600 per 0.1 hectare of site
area, subject to a maximum of £150,000.
Agricultural buildings
5. The erection, on land used for the purposes of agriculture, of
buildings to be used for agricultural purposes (other than
buildings in category 6).
(a) Where the ground area to be covered by the development does not
exceed 500 square metres, £500,
(b) Where the ground area to be covered by the development exceeds
500 square metres, £500 plus £500 for each 100 square metres in
excess of 500 square metres, subject to a maximum of £25,000.
Glasshouses and polytunnels
6. The erection of glasshouses or polytunnels to be used for
agricultural purposes.
£100 for each 100 square metres of ground area to be covered by the
development subject to a maximum of £5,000.
ENERGY GENERATION
7. The erection of wind turbines and the carrying out of other
operations in connection with the construction of the generating
station, including the construction or installation of any means of
access to the generating station, pipes or other conduits, and
overhead lines.
(a) Where the number of turbines does not exceed 3
(i) where none of the turbines have a ground to hub height
exceeding 15 metres, £1,250,
(ii) where one or more of the turbines has a ground to hub
height exceeding 15 metres, but not exceeding 50
metres, £2,500,
(iii) where one or more of the turbines has a ground to hub
height exceeding 50 metres, £5,000.
OFFICIAL
OFFICIAL
Category of development
Fee payable
(b) Where the number of turbines does exceed 3, £500 for each 0.1
hectare of site area, subject to a maximum of £150,000.
8. The construction of a hydro-electric generating station and the
carrying out of any other operations in connection with the
construction of the generating station, including the construction
or installation of any means of access to the generating station,
pipes or other conduits, and overhead lines.
£500 for each 0.1 hectare of site area, subject to a maximum of £25,000.
9. The construction of a solar electric generating station and the
carrying out of any other operations in connection with the
construction of the generating station, including the construction
or installation of any means of access to the generating station,
pipes or other conduits, and overhead lines.
£500 for each 0.1 hectare of site area, subject to a maximum of £25,000.
10. The carrying out of any operations connected with the
exploratory drilling for oil or natural gas.
(a) Where the site area does not exceed 0.1 hectares, £1,000,
(b) Where the site area exceeds 0.1 hectares, £1,000 in respect of the
first 0.1 hectares of site area, plus £500 for each 0.1 hectare of site area
in excess of 0.1 hectares, subject to a maximum of £150,000.
FISH AND SHELLFISH FARMING
11. The placing or assembly of equipment in any part of any
marine waters for the purposes of fish farming.
£200 for each 0.1 hectare of the surface area of the marine waters to be
used in relation to the placement or assembly of any equipment for the
purposes of fish farming and £75 for each 0.1 hectare of the sea bed to
be used in relation to such development, subject to a maximum of
£25,000.
12. The placing or assembly of equipment in any part of any
marine waters for the purposes of shellfish farming.
£200 for each 0.1 hectare of the surface area of the marine waters to be
used in relation to the placement or assembly of any equipment for the
purposes of shellfish farming, subject to a maximum of £25,000.
13. The erection, alteration or replacement of plant or machinery. (a) Where the site area does not exceed 5 hectares, £500 for each 0.1
hectare of site area,
(b) Where the site area exceeds 5 hectares, £25,000 plus £250 for each
0.1 hectare of the site area in excess of 5 hectares, subject to a
maximum of £150,000.
OFFICIAL
OFFICIAL
Category of development
Fee payable
14. The construction of car parks, service roads and other means
of access on land used for the purposes of a single undertaking,
where the development is required for a purpose incidental to the
existing use of the land.
£500
15. Operations for the winning and working of minerals (not
including peat).
(a) Where the site area does not exceed 0.1 hectare, £1,000,
(b) Where the site area exceeds 0.1 hectare, but does not exceed 15
hectares, £1,000 plus £500 for each 0.1 hectare of the site area in
excess of 0.1 hectare,
(c) Where the site area exceeds 15 hectares, £75,000, plus £250 for
each 0.1 hectare of site area in excess of 15 hectares, subject to a
maximum of £150,000.
16. Operations for the extraction of peat. (a) £500 for each 0.1 hectare of site area, subject to a maximum of
£6,000.
17. The carrying out of any operations not coming within any of
the above categories.
(a) Where the site area does not exceed 0.1 hectare, £1,000,
(b) Where the site area exceeds 0.1 hectare, but does not exceed 15
hectares, £1,000 plus £500 for each 1 hectare of the site area in excess
of 0.1 hectare,
(c) Where the site area exceeds 15 hectares, £8,500 plus £250 for each
0.1 hectare of the site area in excess of 15 hectares, subject to a
maximum of £150,000.
USE OF LAND
18. The use of land for the disposal of refuse or waste materials
or for the deposit of material remaining after minerals have been
extracted from land.
(a) Where the site area does not exceed 0.1 hectare, £1,000,
(b) Where the site area exceeds 0.1 hectare, but does not exceed 15
hectares, £1,000 plus £500 for each 1 hectare of the site area in excess
of 0.1 hectare,
(c) Where the site area exceeds 15 hectares, £8,500 plus £250 for each
0.1 hectare of the site area in excess of 15 hectares, subject to a
maximum of £150,000.
19. The use of land for the storage of minerals in the open. (a) Where the site area does not exceed 0.1 hectare, £1,000,
(b) Where the site area exceeds 0.1 hectare, but does not exceed 15
hectares, £1,000 plus £500 for each 1 hectare of the site area in excess
of 0.1 hectare,
OFFICIAL
OFFICIAL
Category of development
Fee payable
(c) Where the site area exceeds 15 hectares, £25,500 plus £250 for each
0.1 hectare of the site area in excess of 15 hectares, subject to a
maximum of £150,000.
CHANGE OF USE OF BUILDINGS OR LAND
20. The change of use of a building to use as one or more
dwellinghouses.
(a) Where the number of dwellinghouses to be created by the
development does not exceed 10, £600 for each dwellinghouse,
(b) Where the number of dwellinghouses to be created by the
development is fewer than 50, £600 for the first 10 dwellinghouses, and
£450 for each dwellinghouse thereafter,
(c) Where the number of dwellinghouses to be created by the
development is 50 or more, £23,550 plus £250 for each dwellinghouse in
excess of 50.
21. A material change in the use of a building (other than a
change of use referred to in category 20).
(a) Where the gross floor space does not exceed 100 square metres,
£600,
(b) Where the gross floor space exceeds 100 square metres, £600 plus
£600 per 100 square metres up to 4,000 square metres,
(c) Where the gross floor space exceeds 4,000 square metres, £24,000
plus £300 per 100 square metres in respect of any gross floor space
exceeding 4,000 square metres, subject to a maximum of £150,000.
22. A material change in the use of land (other than
(a) a change of use within category 21, or
(b) a change of use within categories 18 or 19, or
(c) a change in the use of equipment placed or assembled in
marine waters for the purposes of fish farming or shellfish
farming).
(a) £500 per 0.1 hectare of site area subject to a maximum of £5,000.
OFFICIAL
OFFICIAL
TABLE 2
FEES FOR APPLICATIONS FOR PLANNING PERMISSION IN PRINCIPLE
Category of development
Fee payable
RESIDENTIAL DEVELOPMENT
New dwellings
1. Construction of buildings, structures or
erections for use as residential
accommodation.
(a) where only one dwellinghouse is to be created, £600,
(b) where more than one dwellinghouse is to be created and the site area does not exceed 2.5
hectares, £600 for each 0.1 hectare of the site area,
(c)where more than one dwellinghouse is to be created and site area exceeds 2.5 hectares,
£600 for each 0.1 hectare up to 2.5 hectares of the site area, and then £300 for each 0.1
hectare in excess of 2.5 hectares, subject to a maximum of £75,000.
NON-RESIDENTIAL BUILDINGS
2. The construction of buildings, structures
or erections including extensions.
£600 for each 0.1 hectare up to 2.5 hectares of the site area, and then £300 for each 0.1
hectare in excess of 2.5 hectares, subject to a maximum of £75,000.
OFFICIAL
OFFICIAL
TABLE 3
FEES FOR APPLICATIONS FOR A CERTIFICATE OF LAWFUL USE OR DEVELOPMENT UNDER SECTION
150 OR A CERTIFICATE OF PROPOSED USE OR DEVELOPMENT UNDER SECTION 151 OF THE 1997
ACT
Category of development
Fee payable
CERTIFICATES OF LAWFULNESS OF EXISTING
USE OR DEVELOPMENT
1. An application under section 150(1)(a) or (b) of
the 1997 Act (or both as the case may be).
The amount that would be payable in respect of an application for planning permission
to institute the use or carry out the operations specified in the application (or an
application to do both, as the case may be).
2. An application under section 150(1)(c) of the
1997 Act.
£300.
CERTIFICATES OF LAWFULNESS FOR
PROPOSED USE OR DEVELOPMENT
3. An application under section 151(1) of the 1997
Act (apart from one within category 4).
Half the amount that would be payable in respect of an application for planning
permission to institute the use or carry out the operations specified in the application
(or an application to do both, as the case may be).
4. An application under section 151(1)(a) where the
use specified is use as one or more separate
dwellinghouses.
£600 for each dwellinghouse, subject to a maximum of £150,000.
OFFICIAL
OFFICIAL
TABLE 4
FEES FOR A DETERMINATION AS TO WHETHER THE PLANNING AUTHORITY’S PRIOR APPROVAL IS
REQUIRED IN RELATION TO DEVELOPMENT UNDER SCHEDULE 1 OF THE GENERAL PERMITTED
DEVELOPMENT ORDER
Category of development Fee
payable
1. An application made for determination as to whether the prior approval of the planning authority is required in relation to
£100.
2. An application made by virtue of paragraph (4A) of Class 18 of Part 6 (agricultural buildings and operations) of schedule 1 of
No fee.
3. An application made by virtue of paragraph (4) of Class 18B of Part 6 (agricultural buildings and operations) of schedule 1 of
£500.
4. An application made by virtue of paragraph (5) of Class 18C of Part 6 (agricultural buildings and operations) of schedule 1 of
£500.
5. An application made by virtue of paragraph (4) of Class 21A of Part 6A (fish farming) of schedule 1 of the General Permitted
£500.
6. An application made by virtue of paragraph (4) of Class 22A of Part 7 (forestry buildings and operations) of schedule 1 of the
£500.
7. An application made by virtue of paragraph (5) of Class 22B of Part 7 (forestry buildings and operations) of schedule 1 of the
£500.
8. An application made by virtue of paragraph (4) of Class 22 of Part 7 (forestry buildings and operations) of schedule 1 of the
General Permitted Development Order.
No fee.
9. An application made by virtue of sub-paragraph (23) of Class 67 of Part 20 (development by electronic communications code
£500.
OFFICIAL