Standby power Solutions, LLC
paul@standbypowersolutions.com
Load Test Form
Date:
Location:
Customer:
Technician:
Model:
Serial #:
kW Rating
Voltage:
Unit
Hours:
Rotation:
CW
CCW
Engine
Amps
time
temp - F
oil - PSI
Leg A
Leg B
Leg C
Voltage
Freq.
%Load
kW
Exhaust
Temp
Start:
+15 min
+30 min
+45 min
+1 hr
+1 hr 15 min
+1 hr 30 min
+1 hr 45 min
+2 hrs
Engine
Amps
time
temp - F
oil - PSI
Leg A
Leg B
Leg C
Voltage
Freq.
%Load
kW
Exhaust
Temp
+2 hrs 15 min
+2 hrs 30 min
+2 hrs 45 min
+3 hrs
+3 hrs 15 min
+3 hrs 30 min
+3 hrs 45 min
+4 hrs
Passed
Failed
4-hour load test per NFPA 110, chapter 8.4.9, 2010 edition
Diesel Generators
Connect the loadbank to the system leaving the building load connected.
Start the EPS using a transfer switch then transfer all transfer switches to the generator.
Add supplemental load to 30%. Run the EPS for 3 hours at a minimum of 30% load.
Add load to 75% minimum for the final hour.
It is OK if the building load exceeds the above load up to 100% of the EPS nameplate rating.
Gas Generators
Start the EPS using a transfer switch then transfer all transfer switches to the generator. No loadbank is
required. Available load is all that is needed.
Instructions
4-hour load test per NFPA 110, chapter 8.4.9, 2010 edition
Diesel Generators
Connect the loadbank to the system leaving the building load connected.
Technician’s initials_____________
Start the EPS using at least one transfer switch then transfer all transfer switches to the
generator. The generator company must locate and identify all transfer switches, both
automatic and manual.
Technician’s initials_____________
Add supplemental load to 30% of the nameplate rating. Run the EPS for 3 hours at a
minimum of 30% load.
Technician’s initials_____________
Increase load to 75% minimum for the final hour.
Technician’s initials_____________
It is OK if the building load exceeds the above load up to 100% of the EPS nameplate rating.
Gas Generators (Natural gas or LPG)
Start the EPS using a transfer switch then transfer all transfer switches to the generator.
No loadbank is required. Available load is all that is needed. Run the system for 4 hours
and take readings every 15 minutes.
If during the Load Test a transfer switch door is left open or any electrical hazard is present,
an attendant must be stationed in the area to keep other persons not directly involved in the
task away from potential danger. NFPA 70E, article 130.7 (E) (3)
Technician’s signature: ______________________________________
Date: ____________________________________________________
Witnessed by: _____________________________________________
Owner’s representative:______________________________________