by Robert A. James
www.pillsburylaw.com | 3
2.2
Contractor Key Personnel and Organization
Chart. Contractor designates Contractor
Representative authorized to receive notices
and take actions required under this agreement.
Contractor not to redeploy key personnel without
Owner consent. Owner may be entitled to require
replacement of unsatisfactory personnel in defined
circumstances.
2.3
Subcontractor Status. Subcontractors are not
third-party beneficiaries of the EPC Agreement.
Contractor is liable for their performance or
nonperformance.
2.4
Subcontractors and Awards. List of previously
approved Subcontractors. Process for advertising
for new subcontracts, review of proposals by
Contractor, review of proposals and Contractor’s
recommendation by Owner, award by Contractor.
Ability of Contractor to award small Subcontracts
without formal process (where there is a fixed
EPC price). Owner may be entitled to require
replacement of unsatisfactory Subcontractor in
defined instances. Contractor may be required to
flow down clauses into Subcontracts, including
financer cooperation duties and execution of
conditional assignments.
2.5
Prior Engineering. Relation of the work under the
EPC Agreement to the “design basis” or “design
package,” or to the work performed under a front-
end engineering design (FEED) agreement or other
existing contracts.
2.6
Review of Documents. Contractor acknowledges
it has reviewed and accepts the scope descriptions
and risk allocations in the Project Documents.
2.7
Review of Conditions. Contractor acknowledges
it has reviewed the site conditions and industry
and economic conditions. Contractor may or may
not be entitled to rely on the Geotechnical Report,
land survey and other materials provided by Owner.
Special provisions for existing piles or foundations
and for subsurface conditions.
2.8
Review of Laws. Contractor acknowledges that it
has reviewed both Applicable Laws and other laws
(e.g., tax laws), that such laws may change, and
that it accepts the risk of such changes, subject to
the Change Order provisions.
3
CONTRACTOR’S RESPONSIBILITIES
3.1
Generally. Contractor performs all Work required
for Mechanical, Substantial and Final Completion
of the Project, all in accordance with Project
Documents, Requirements and Prudent Industry
Practice, so as to meet the Minimum Acceptance
Criteria and pass the Performance Test. Includes
all items or activities reasonably inferable from
Project Documents. Basic Project description
scope document included as Attachment is
illustrative. But Work excludes defined Owner-
furnished items (which may include Owner
Permits, Owner-supplied inputs such as turbine
supply, Geotechnical Report, and site survey).
3.2
Specifically. Contractor provides engineering,
procurement, construction, rectification of
defects, subcontractor award and responsibility,
inspection, Contractor Permits, information needed
or requested for Owner Permits, and training for
operation and maintenance (O&M) personnel or
contractor. May include or exclude responsibility
for receiving, installing and commissioning turbine
or other specialty equipment furnished under
separate contract to Owner.
3.3
Engineering. Contractor conducts all needed
design and engineering (subject to, or not subject
to, “design basis,” “design package” or FEED
agreement outputs), finishes site survey and
geotechnical investigations relying (or not relying)
on Owner’s site survey and Geotechnical Report,
reviews Owner-provided designs, prepares
Drawings and Specifications for Owner review per
timetable schedule (with Owner having x days to
respond, and a defined process for addressing its
comments), proposes value engineering options,
holds all needed engineering registrations and
licenses, uses proper computer-aided design
(CAD) and building information management (BIM)
systems and protocols, and prepares all piping
and instrumentation diagrams (P&IDs) and as-built
drawings.
3.4
Procurement. Contractor conducts all needed
procurement of materials and equipment (subject
to allowances in Contract Price for Owner spare
part decisions, and except Owner-procured items).
Contractor responsible for clearance of customs,
payment of duties and other charges for imports;
responsible for local content and hiring compliance,
and may request relevant information from Owner,
to be provided reasonably and promptly.
3.4.1
Process for proposing and securing Owner’s
approval to substitute “or equal” items for
items specified.
3.4.2
Provisions regarding transportation, delivery,
receipt and storage of materials and equipment.
Responsibility for protection and proper
storage. Shop inspections of offsite fabrication
or manufacturing. Receipt and use of Owner-
furnished items.
3.4.3
Contractor proposes spare parts list. Owner
decides which ones Contractor should
purchase. Adjustment via Change Order to