United States Government Accountability Office
Highlights of GAO-14-369, a report to
congressional requesters
April 2014
NATIONAL ENVIRONMENTAL POLICY ACT
Little Information Exists On NEPA Analyses
Why GAO Did This Study
NEPA requires all federal agencies to
evaluate the potential environmental
effects of proposed projects—such as
roads or bridges—on the human
environment. Agencies prepare an EIS
when a project will have a potentially
significant impact on the environment.
They may prepare an EA to determine
whether a project will have a significant
potential impact. If a project fits within
a category of activities determined to
have no significant impact—a CE—
then an EA or an EIS is generally not
necessary. The adequacy of these
analyses has been a focus of litigation.
GAO was asked to review issues
related to costs, time frames, and
litigation associated with completing
NEPA analyses. This report describes
information on the (1) number and type
of NEPA analyses, (2) costs and
benefits of completing those analyses,
and (3) frequency and outcomes of
related litigation. GAO included
available information on both costs and
benefits to be consistent with standard
economic principles for evaluating
federal programs, and selected the
Departments of Defense, Energy, the
Interior, and Transportation, and the
USDA Forest Service for analysis
because they generally complete the
most NEPA analyses. GAO reviewed
documents and interviewed individuals
from federal agencies, academia, and
professional groups with expertise in
NEPA analyses and litigation. GAO’s
findings are not generalizeable to
agencies other than those selected.
This report has no recommendations.
GAO provided a draft to CEQ and
agency officials for review and
comment, and they generally agreed
with GAO’s findings.
What GAO Found
Governmentwide data on the number and type of most National Environmental
Policy Act (NEPA) analyses are not readily available, as data collection efforts
vary by agency. NEPA generally requires federal agencies to evaluate the
potential environmental effects of actions they propose to carry out, fund, or
approve (e.g., by permit) by preparing analyses of different comprehensiveness
depending on the significance of a proposed project’s effects on the
environment—from the most detailed Environmental Impact Statements (EIS) to
the less comprehensive Environmental Assessments (EA) and Categorical
Exclusions (CE). Agencies do not routinely track the number of EAs or CEs, but
the Council on Environmental Quality (CEQ)—the entity within the Executive
Office of the President that oversees NEPA implementation—estimates that
about 95 percent of NEPA analyses are CEs, less than 5 percent are EAs, and
less than 1 percent are EISs. Projects requiring an EIS are a small portion of all
projects but are likely to be high-profile, complex, and expensive. The
Environmental Protection Agency (EPA) maintains governmentwide information
on EISs. A 2011 Congressional Research Service report noted that determining
the total number of federal actions subject to NEPA is difficult, since most
agencies track only the number of actions requiring an EIS.
Little information exists on the costs and benefits of completing NEPA analyses.
Agencies do not routinely track the cost of completing NEPA analyses, and there
is no governmentwide mechanism to do so, according to officials from CEQ,
EPA, and other agencies GAO reviewed. However, the Department of Energy
(DOE) tracks limited cost data associated with NEPA analyses. DOE officials told
GAO that they track the money the agency pays to contractors to conduct NEPA
analyses. According to DOE data, its median EIS contractor cost for calendar
years 2003 through 2012 was $1.4 million. For context, a 2003 task force report
to CEQ—the only available source of governmentwide cost estimates—
estimated that a typical EIS cost from $250,000 to $2 million. EAs and CEs
generally cost less than EISs, according to CEQ and federal agencies.
Information on the benefits of completing NEPA analyses is largely qualitative.
According to studies and agency officials, some of the qualitative benefits of
NEPA include its role in encouraging public participation and in discovering and
addressing project design problems that could be more costly in the long run.
Complicating the determination of costs and benefits, agency activities under
NEPA are hard to separate from other required environmental analyses under
federal laws such as the Endangered Species Act and the Clean Water Act;
executive orders; agency guidance; and state and local laws.
Some information is available on the frequency and outcome of NEPA litigation.
Agency data, interviews with agency officials, and available studies show that
most NEPA analyses do not result in litigation, although the impact of litigation
could be substantial if a single lawsuit affects numerous federal decisions or
actions in several states. In 2011, the most recent data available, CEQ reported
94 NEPA cases filed, down from the average of 129 cases filed per year from
calendar year 2001 through calendar year 2008. The federal government prevails
in most NEPA litigation, according to CEQ and legal studies.
View GAO-14-369. For more information,
contact Anne-Marie Fennell at (202) 512-3841
or