PUBLIC SERVICE COMMISSION
OF MARYLAND
TEN-YEAR PLAN
(2011 – 2020)
OF ELECTRIC
COMPANIES
IN MARYLAND
Prepared for the
Maryland Department of Natural Resources
In compliance with Section 7-201
of the Maryland Public Utilities Article
February 2012
State of Maryland
Public Service Commission
Douglas R. M. Nazarian, Chairman
Harold D. Williams, Commissioner
Lawrence Brenner, Commissioner
Kelly Speakes-Backman, Commissioner
W. Kevin Hughes, Commissioner
David J. Collins Gregory V. Carmean H. Robert Erwin
Executive Secretary Executive Director General Counsel
6 St. Paul Street
Baltimore, MD 21202
Tel: (410) 767-8000
www.psc.state.md.us
This report was drafted by the Commission’s Energy Analysis and Planning Division (Crissy Godfrey,
Director), in cooperation with the Engineering Division (Jerry Hughes, Chief Engineer). Electric
companies under the Commission’s jurisdiction provided most of the data in the Appendix.
TABLE OF CONTENTS
I. INTRODUCTION ...............................................................................................................................1
II. MARYLAND UTILITY AND PJM ZONAL LOAD FORECASTS...............................................3
A. Introduction...................................................................................................................................... 3
B. PJM Zonal Forecast.......................................................................................................................... 4
C. Maryland Company Forecasts.......................................................................................................... 5
III. REGIONAL GENERATION AND SUPPLY ADEQUACY IN MARYLAND..............................7
A. Introduction...................................................................................................................................... 7
B. Maryland Generation Profile: Age and Fuel Characteristics........................................................... 9
C. Potential Generation Additions in Maryland.................................................................................. 13
D. CPCN Exemptions for Generation................................................................................................. 15
IV. TRANSMISSION INFRASTRUCTURE: PJM, MARYLAND, AND NATIONAL...................19
A. Introduction.................................................................................................................................... 19
B. Eastern Interconnection Planning Collaborative............................................................................ 19
C. The Regional Transmission Expansion Planning Protocol ............................................................ 20
D. Transmission Congestion in Maryland........................................................................................... 22
E. High Voltage Transmission Lines in PJM ..................................................................................... 24
V. DEMAND RESPONSE AND CONSERVATION AND ENERGY EFFICIENCY....................26
A. Statutory Requirements.................................................................................................................. 26
B. Demand Response Initiatives......................................................................................................... 28
C. Energy Efficiency and Conservation Programs ............................................................................. 34
D. Advanced Metering Infrastructure / Smart Grid ............................................................................ 37
E. Mid-Atlantic Distributed Resources Initiative ............................................................................... 42
VI. ENERGY, THE ENVIRONMENT, AND RENEWABLES...........................................................42
A. The Regional Greenhouse Gas Initiative........................................................................................ 42
B. The Renewable Energy Portfolio Standard Program ..................................................................... 44
C. Solar Power Requirements in Maryland ........................................................................................ 49
VII. ELECTRIC DISTRIBUTION RELIABILITY IN MARYLAND.................................................51
A. Electric Distribution Reliability Reporting, Operation and Maintenance ...................................... 51
B. Distribution Reliability Issues........................................................................................................ 53
C. Managing Distribution Outages ..................................................................................................... 58
D. Distribution Planning Process........................................................................................................ 60
VIII. MARYLAND ELECTRICITY MARKETS....................................................................................63
A. Status of Retail Electric Choice in Maryland................................................................................. 63
B. Standard Offer Service................................................................................................................... 65
IX. REGIONAL ENERGY ISSUES AND EVENTS ............................................................................66
A. Overview of PJM, OPSI, and Reliability First............................................................................... 66
B. PJM Summer Peak Events of 2010 and 2011 ................................................................................ 68
C. PJM’s Reliability Pricing Model.................................................................................................... 69
D. Region-Wide Demand Response in PJM Markets......................................................................... 71
X. PROCEEDINGS BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION.....72
i
APPENDIX
Table A-1: Utilities Providing Retail Electric Service in Maryland................................. 74
Table A-2: Number of Customers by Customer Class as of December 31, 2010............ 75
Table A-3: Typical Monthly Electric Bills in Maryland (Winter 2010)........................... 76
Table A-4(a): System Wide Peak Demand Forecast as of December 31, 2010 (MW) (Net
of DSM Programs).................................................................................................... 77
Table A-4(b): Maryland Peak Demand Forecast as of December 31, 2010 (MW) (Net of
DSM Programs)........................................................................................................ 78
Table A-4(c): System Wide Peak Demand Forecast as of December 31, 2010 (MW)
(Gross of DSM Programs) ........................................................................................ 79
Table A-4(d): Maryland Peak Demand Forecast as of December 31, 2010 (MW) (Gross
of DSM Programs).................................................................................................... 80
Table A-5(a): System Wide Energy Sales Forecast (GWh) (Net of DSM Programs)...... 81
Table A-5(b): Maryland Energy Sales Forecast (GWh) (Net of DSM Programs) ........... 82
Table A-6: Maryland Licensed Electric/Natural Gas Suppliers and Brokers as of
December 1, 2011..................................................................................................... 83
Table A-7: Transmission Enhancements by Service Area ............................................... 89
Table A-8: Renewable Projects Providing Capacity and Energy to Maryland Customers
as of December 31, 2010 .......................................................................................... 94
Table A-9: Power Plants in the PJM Process for New Electric Generating Stations in
Maryland as of December 31, 2010.......................................................................... 95
ii
LIST OF MAPS, FIGURES, TABLES, AND CHARTS
Map I.1: Maryland Utilities and their Service Territories in Maryland............................. 2
Figure II.A.1: PJM Maryland Forecast Zones................................................................... 3
Table II.B.1: Summer Peak Load (MW) Growth Rates .................................................... 4
Table II.B.2: Winter Peak Load (MW) Growth Rates....................................................... 5
Table II.C.1: Comparison of Maryland Peak Demand Forecasts....................................... 6
Table II.C.2: Comparison of Maryland Energy Sales Forecast.......................................... 6
Table III.A.1: State Electricity Imports (Year 2009) (GWh)............................................. 8
Table III.B.1: Maryland Generating Capacity Profile (Year 2010)................................... 9
Table III.B.2: Maryland Electric Power Generation Profile (Year 2009) ....................... 11
Table III.B.3: Generation by Owner, County, and Capacity (Year 2010)....................... 12
Table III.C.1: PJM Transmission Queue Active New Generating Capacity................... 15
Table III.D.1: Construction Approvals for CPCN Exempt Generation........................... 17
Table III.D.2: Number and Capacity in MW of CPCN Exempt Generating Units by
Energy Resource....................................................................................................... 18
Table V.B.1: Utilities’ Incentives to DLC Program Participants .................................... 29
Table V.B.2: Utilities’ Direct Load Program Installations; Program-to-Date as of
December 31, 2010................................................................................................... 30
Table V.B.3: Direct Load Control Program Bids into PJM BRA (MW) ........................ 30
Table V.B.4: Peak Load Reduction Forecast (MW)........................................................ 34
Table VI.A.1: Annual State CO
2
Allowance Budgets (2009 – 2014).............................. 43
Table VI.B.1: Eligible Tier 1 and Tier 2 Renewable Resources ..................................... 45
Table VI.B.2: Annual RPS Percentage Requirements by Tier........................................ 46
Table VI.B.3: RPS Alternative Compliance Fee Schedule ($/MWh) ............................. 47
Table VI.B.4: RPS Supplier Annual Report Results as of December 31, 2010.............. 48
Chart VI.B.5: Maryland RPS Eligible Capacity by State................................................ 49
Table VIII.A.1: Residential Customers Enrolled in Retail Supply.................................. 64
Table VIII.A.2: Electric Choice Enrollment in Maryland as of September 30, 2011 ..... 65
Table IX.B.1: Summer 2010 and 2011 Coincident Peaks and Zone LMP...................... 69
Table IX.C.1: RPM “Net Load” Price and Cost.............................................................. 71
iii
LIST OF ACRONYMS AND DEFINITIONS USED
ACP Alternative Compliance Penalty
AMI Advanced Metering Infrastructure
ARR Auction Revenue Right
ARRA American Recovery and Reinvestment Act of 2009
BGE Baltimore Gas and Electric Company
BRA Base Residual Auction
C&I Commercial and Industrial
CAIDI Customer Average Interruption Duration Index
CETL Capacity Emergency Transfer Limit
CETO Capacity Emergency Transfer Objective
CIS Customer Information System
CO
2
Carbon Dioxide
CPCN Certificate of Public Convenience and Necessity
CSP Curtailment Service Provider
DLC Direct Load Control
DOE United States Department of Energy
DPL Delmarva Power & Light Company
DR Demand Response or Demand Resource
DSM Demand-Side Management
DY Delivery Year
EDC Electric Distribution Company
EE&C Energy Efficiency and Conservation
EFORd Equivalent Demand Forced Outage Rate
EIA Energy Information Administration
EIPC Eastern Interconnection Planning Collaborative
EISA Energy Independence and Security Act of 2007
EISPC Eastern Interconnection State Planning Council
ELRP Economic Load Response Program
EMAAC Eastern Mid-Atlantic Area Council
EMS Energy Management System
EM&V Evaluation, Measurement, and Verification
EPA United States Environmental Protection Agency
ETR Estimated Time of Restoration
FERC Federal Energy Regulatory Commission
FTR Financial Transmission Right
GATS Generation Attributes Tracking System
GIS Geographic Information System
GW/GWh Gigawatt/Gigawatt-hours
HVAC Heating, Ventilation, and Air Conditioning
HVCS High Volume Call Service
HVDC High Voltage Direct Current
IOU Investor-Owned Utility
IRM Installed Reserve Margin
ISAC Independent State Agency Committee
ISO Independent System Operator
iv
IVR Interactive Voice Response
kV Kilovolt
kW/kWh Kilowatt/Kilowatt-hours
LDA Load Deliverability Area
LMP Locational Marginal Price
LSE Load Serving Entity
MAAC Mid-Atlantic Area Council
MADRI Mid-Atlantic Distributed Resources Initiative
MAPP Mid-Atlantic Power Pathway
MDE Maryland Department of the Environment
MDS Mobile Dispatch System
MEA Maryland Energy Administration
MW/MWh Megawatt/Megawatt-hours
NERC North American Electric Reliability Council
O&M Operation and Maintenance
OATT Open Access Transmission Tariff (PJM)
OMS Outage Management System
OPC Office of People’s Counsel (Maryland)
OPSI Organization of PJM States, Inc.
PATH Potomac-Appalachian Transmission Highline
PE The Potomac Edison Company
Pepco Potomac Electric Power Company
PJM PJM Interconnection, LLC (Pennsylvania-Jersey-
Maryland)
PJM-EIS PJM – Environmental Information Services, Inc
PSC/ MD PSC Maryland Public Service Commission
PTR Peak-Time Rebate
PUA Public Utilities Article, Annotated Code of Maryland
REC Renewable Energy Credit
RFP Request for Proposal
RGGI Regional Greenhouse Gas Initiative
RPM Reliability Pricing Model (PJM)
RPS Renewable Energy Portfolio Standard
RTEP Regional Transmission Expansion Plan
RTO Regional Transmission Organization
SAIDI System Average Interruption Duration Index
SAIFI System Average Interruption Frequency Index
SCADA Supervisory Control and Data Acquisition
SEIF Maryland Strategic Energy Investment Fund
SGIG Smart Grid Investment Grant
SMECO Southern Maryland Electric Cooperative, Inc.
SOS Standard Offer Service
SWMAAC Southwest Mid-Atlantic Area Council
TEAC Transmission Expansion Advisory Committee (PJM)
TrAIL Trans-Allegheny Interstate Line
WMS Work Management System
v
I. INTRODUCTION
Section 7-201 of the Public Utilities Article, Annotated Code of Maryland
(“PUA”), requires the Maryland Public Service Commission (“Commission” or “PSC” or
“MD PSC”) to forward a Ten-Year Plan of Electric Companies in Maryland (“Ten-Year
Plan”) to the Secretary of Natural Resources on an annual basis. This report constitutes
that effort for the 2011 – 2020 timeframe and, with exceptions as noted in the text, the
referenced data and information is as it existed as of December 31, 2010. It is a
compilation of information on long-range plans of Maryland electric utilities. This report
also includes summaries of events that have affected or may affect the electric utility
industry in Maryland in the near future.
A principal focus of the Commission is the reliability of Maryland’s electricity
supply, delivered at reasonable rates. Achieving reliability is a complex undertaking
which requires consideration of factors affecting both supply and demand. To address
these elements the Commission is taking action on several fronts: challenging wholesale
power policies at the Federal Energy Regulatory Commission (“FERC”); working with
the wholesale independent market monitor to effectuate positive market results;
evaluating the need for procuring new generation in the State; directing new utility
investment in demand response programs to reduce peak electricity demand; evaluating
conservation and energy efficiency programs to meet EmPower Maryland peak and
overall energy reductions;
1
and encouraging better use of emergency generation within
the State to promote adequate, economical, and efficient delivery of electricity services.
Section II of this plan addresses the peak demand load forecast for Maryland and
establishes the baseline load requirements for the next ten years. Section III provides
information on generation, including certificates of public convenience and necessity
(“CPCNs”), and forecasts the availability of generation to meet load requirements.
Section IV reviews transmission issues impacting Maryland, including the Department of
Energy’s National Interest Electric Transmission Corridors. Section V addresses the
options of energy efficiency, conservation, and demand response as part of Maryland’s
supply resources, and discusses the effort required to meet EmPower Maryland goals.
Proposals to deploy advanced metering infrastructure also are discussed in this section.
Because environmental issues continue to play an increasingly important role in energy
decisions, Section VI discusses Maryland’s involvement in the Regional Greenhouse Gas
Initiative and other issues involving the impact of renewable generation growth. Section
VII provides information on distribution reliability, the manner in which utilities have
managed outages, and how utilities plan to meet load requirements.
Beginning with Section VIII, we broaden our perspective and review Maryland’s
Electricity Market in general terms and its relation to Commission efforts that are
currently underway or anticipated. Section IX discusses PJM Interconnection, LLC
1
See EmPower Maryland Energy Efficiency Act of 2008, codified within MD. CODE ANN., PUB.
UTIL. § 7-211 (2011) (“EmPower Maryland”).
1
(“PJM”)
2
and the impact that market rule changes have had both regionally and in
Maryland. Section X reviews national issues and the impact generated by FERC rulings
and U.S. Department of Energy actions. Also included in the Ten-Year Plan is an
Appendix that contains a compilation of data provided by Maryland’s utilities
summarizing, among other things, demand and anticipated sales over the next 15 years.
Maryland is geographically divided into thirteen electric utility service territories.
Four of the largest are investor-owned utilities (“IOUs”), four are electric cooperatives
(two of which serve only small areas of Maryland), and five are electric municipal
operations.
3
Table A-1 in the Appendix lists the utilities providing retail electric service
in Maryland and Map I.1 below provides a geographic picture of the utilities’ service
territories.
4
Map I.1: Maryland Utilities and their Service Territories in Maryland
Source: Cumulative Environmental Impact Report 15, MD. DEPT OF NATURAL RES., Figure 2-12,
http://esm.versar.com/pprp/ceir15/Report_2_3.htm (last updated Feb. 25, 2010).
2
PJM is a regional transmission organization that coordinates the movement of wholesale
electricity in all or parts of 13 states and the District of Columbia.
3
The St. Michaels Utilities Commission service territory was transferred to Choptank Electric
Cooperative, Inc. in October 2006.
4
The Potomac Edison Company no longer uses its “doing business name” of “Allegheny Power”
and any references within the Ten-Year Plan to Allegheny Power should be read as referencing
Potomac Edison.
2
II. MARYLAND UTILITY AND PJM ZONAL LOAD FORECASTS
A. Introduction
The foundation of an analysis for meeting Maryland’s electricity needs starts with
a forecast of the anticipated demand over a relevant planning horizon. The Commission
routinely evaluates forecasts from individual utilities, as well as the PJM forecast, which
provides separate estimates for the transmission zones shown in Figure II.A.1.
Figure II.A.1: PJM Maryland Forecast Zones
Source: PJM Load Forecast Report, PJM PLANNING (Jan. 2011),
http://www.pjm.com/planning/resource-adequacy-planning/~/media/documents/reports/2011-pjm-
load-report.ashx.
PJM sub-regions, known as zones, generally correspond with the IOU service
territories. The PJM zones include adjacent municipal and rural electric cooperatives. The
four IOUs operating in Maryland are Baltimore Gas and Electric Company (“BGE”),
Potomac Electric Power Company (“Pepco”), Delmarva Power & Light Company
(“DPL” or “Delmarva”), and The Potomac Edison Company (“PE”). PJM zones for
three of the four IOUs traverse state bounds and extend into other jurisdictions. Pepco,
DPL, and PE company data are a subset of the PJM zonal data, since PJM’s zonal
forecasts are not limited to Maryland. The BGE zone, alone, resides solely within the
State of Maryland.
PJM operates the wholesale power market that includes the entire mid-Atlantic
region and dispatches power plants to serve load on an economic bid basis, subject to
transmission capacity availability. PJM’s load forecasts drive the need for generation,
3
which impacts electric consumer prices at the retail level. The Commission closely
monitors the development of PJM regional forecasts.
While forecasts can rely on similar economic data, projections of peak demand
and energy usage can vary based upon the underlying assumptions used to generate the
forecasts. In general, the expected growth in peak demand and electricity usage is due
primarily to expected increases in population and economic activity, which have a direct
impact on electricity consumption levels. Key forecast variables include economic and
non-economic variables. Economic variables used in forecast models can include gross
domestic product, employment, energy prices, and population. Non-economic variables
can include weather normalized variables, monthly seasonal variables, ownership of
appliances, and building codes.
B. PJM Zonal Forecast
PJM’s 2011 Load Forecast Report includes long-term forecasts of peak loads and
net energy for the entire wholesale market region and each PJM sub-region (i.e., zone) –
including the four sub-regions in which Maryland resides.
5
The 2011 Load Forecast
Report concludes that the PJM region will, in aggregate, experience higher peak usage in
the summer throughout the forecast period ending 2026.
6
Tables II.B.1 and II.B.2
present comparisons in expected growth for the four PJM zones containing Maryland.
7
The 2011 Load Forecast is compared to the 2009 and 2010 Load Forecasts on a very
broad macro level for the four PJM regions roughly corresponding with the four IOU
service territories that serve Maryland. When compared, the 2011 Load Forecast shows
significant reductions in both Summer and Winter peak demand growth rates from the
previous year’s Load Forecast. The PJM zones containing BGE, DPL, and Pepco
experience their peak demands during the summer while the PJM region containing PE
experiences peak demands in the winter.
8
Table II.B.1: Summer Peak Load (MW) Growth Rates
PJM Zone
2009-2019* 2010-2020** 2011-2021***
PE 1.5% 1.4% 1.0%
BGE 1.8% 1.8% 1.3%
DPL 2.1% 1.4% 1.1%
Pepco 1.2% 1.2% 1.0%
5
PJM Load Analysis Subcommittee, PJM, available at: http://www.pjm.com/committees-and-
groups/subcommittees/las.aspx.
6
PJM Load Forecast Report, PJM, 37 (January 2011), available at:
http://www.pjm.com/committees-and-groups/subcommittees/~/media/documents/reports/2011-
pjm-load-report.ashx. The PJM RTO summer peak is forecasted to be 182,904 MW in 2026, a 15-
year increase of 28,521 MW. Id.
7
For Maryland, the four PJM regions contain all four of the State’s investor-owned utilities, the five
municipal systems, and Maryland’s four rural electric cooperatives. Id.
8
Id.
4
Table II.B.2: Winter Peak Load (MW) Growth Rates
PJM Zone 2009-2019* 2010-2020** 2011-2021***
PE 1.3% 1.3% 1.0%
BGE 1.0% 1.1% 0.8%
DPL 1.5% 1.0% 0.8%
Pepco 1.1% 1.2% 1.0%
Sources: * PJM Load Forecast Report, January 2009, Tables B-1 and B-2.
** PJM Load Forecast Report, January 2010, Tables B-1 and B-2.
***PJM Load Forecast Report, January 2011, Tablets B-1 and B-2.
C. Maryland Company Forecasts
Maryland’s electric utilities annually submit responses to Commission data
requests that include forecasts of peak and annual energy demand. The forecast
information provided by each company is summarized in the Appendices as Tables A-
4(a) – (d) and Tables A-5(a) – (b). Data requests for the current Ten-Year Plan include
responses that expand beyond a ten-year period – from 2011 through 2025. The prior
year’s submissions began and terminated one year earlier, that is, from 2010 through
2024. A comparison of the electric utility submissions for the first and last years of the
forecast period is provided to indicate, on an aggregate basis, current expectations for
peak usage in the State for electricity. The utility forecasts reflect: short-term
recessionary impacts, the utilities’ current expectations with regard to nascent demand-
side management (“DSM”) and energy efficiency programs, and the expected reductions
in energy usage attributable to these programs. Precision and certainty diminish the
longer the time period over which a forecast is generated. Comparisons are first
presented for the State in aggregate for four common future years: 2011, 2016, 2021, and
2024.
9
Additional analysis pertaining to 2011 and the period 2011 through 2021 also are
explored.
Table II.C.1 compares Maryland peak demand forecasts on an aggregate basis and
includes utility-provided estimates of currently-approved DSM and energy efficiency
measures. Actual peak demand in 2011 net of DSM programs compared to the 2010
forecasted peak demand net of DSM programs indicates that peak demand increased by
1.1%. Peak demand forecasts for this Ten-Year Plan period compared to the 2010 – 2019
Ten-Year Plan forecasted peak demand indicate that peak demands are estimated to
increase by 0.7% in 2016, 0.7% in 2021, and 0.8% in 2024.
10
9
Additional data for the 2011 to 2025 period can be located in Tables A-4 and A-5 of this Ten-Year
Plan Appendix. Corresponding data considering the 2010 to 2024 time period can be located in
last year’s Ten-Year Plan Appendix Tables A-5 and A-6.
10
Increases are a comparison strictly to last year’s submissions and not considered on a per capita
basis in keeping with the goals of EmPower Maryland.
5
Table II.C.1: Comparison of Maryland Peak Demand Forecasts
(Net of DSM Programs; MW)
2010 - 2019 2011 - 2020
Ten-Year Plan Ten-Year Plan
2011
13,638 13,786 148 1.1
2016
13,812 13,914 102 0.7
2021
14,801 14,900 99 0.7
2024
15,381 15,511 130 0.8
Year Change %
Sources: Ten-Year Plan (2010-2019) of Electric Companies in Maryland, MD PSC,
6 (Aug. 2011), available at: http://webapp.psc.state.md.us/Intranet/Reports/2010-
2019%20Ten%20Year%20Plan.pdf. See Appendix Table A-4(b).
Table II.C.2 compares utility forecasted energy sales within the State of
Maryland. When compared to utility estimates provided last year, the electric utility
forecasts, in aggregate, project additional increases in overall annual electricity sales in
the State. During the timeframe examined, increases in energy usage trend upward
11
between 0.6% and 1.4% when compared to last year’s electric utility submissions.
Table II.C.2: Comparison of Maryland Energy Sales Forecast
(Net of DSM Programs; GWh)
2010 - 2019 2011 - 2020
Ten-Year Plan
(GWh)
Ten-Year Plan
(GWh)
2011
63,651 64,012 361 0.6
2016
66,954 66,887 -67 -0.1
2021
71,111 72,056 945 1.3
2024
73,848 74,865 1,017 1.4
Year Change %
Sources: Ten-Year Plan (2010-2019) of Electric Companies in Maryland, MD PSC,
6 (Aug. 2011), available at: http://webapp.psc.state.md.us/Intranet/Reports/2010-
2019%20Ten%20Year%20Plan.pdf. See Appendix Table A-5(b).
As reflected in Table II.C.1 and Table II.C.2, utility projections of peak demand
and of annual energy sales are currently moving in similar directions: peak demand is
increasing and annual energy sales are increasing when compared to utility estimates
provided last year. Historically, peak demand and annual energy sales have moved in
tandem.
Numerous changes have occurred or have been proposed to PJM demand
response (“DR”) programs recently. These changes include implementing a more
accurate method of measuring and verifying the quantity of demand reductions provided
11
Although the comparison of 2016 forecasted energy sales between the 2010 – 2019 TYP and the
2011 – 2020 TYP indicates a 0.1% reduction, utility data for the 2011 – 2020 TYP reflects an
increase in forecasted State energy sales in the aggregate when compared to the 2010 – 2019 TYP
forecast. See Appendix Table A-5(b).
6
and proposals to significantly expand both the time period and the seasons during which
DR participants must reduce load. The uncertainty associated with such changes leads to
less aggressive projections of future DR participation and DSM impacts.
III. REGIONAL GENERATION AND SUPPLY ADEQUACY IN MARYLAND
A. Introduction
The Commission recognizes that in order to maintain electric system reliability
and an adequate supply of electricity for customers in the future, access to adequate
electric capacity must be available to meet customer demand.
A critical requirement for reliable electric service is an appropriate level of
generation and transmission capacity to meet Maryland consumers’ energy needs. While
reliability needs may be partially met through local demand side management programs
and the import of electricity using high-voltage transmission lines, local generation must
be maintained and is essential to keeping the lights on and the power grid operating
effectively and economically. All load serving entities in the PJM region are required to
ensure they have sufficient capacity contracts to provide reliable electric service during
periods of peak demand. As of 2010, Maryland’s net summer generating capacity was
approximately 12,516 MW.
12
Maryland’s peak demand forecast for 2011 with utility
demand-side management and energy conservation measures is approximately 13,786
MW.
13
According to PJM’s established margin for necessary reserves, an additional
2,137 MW
14
is required and would result in a cumulative estimated reliability
requirement of 15,923 MW. Therefore, 3,407 MWs of estimated capacity in the
transmission system serves to meet Maryland’s requirements during periods of peak
usage in the system.
All major utility systems in the eastern half of the United States and Canada are
interconnected and operate synchronously as part of the Eastern Interconnection. PJM
operates, but does not own, the transmission systems in: (1) Maryland; (2) all or part of
12 other states; and (3) the District of Columbia. With FERC approval, PJM undertakes
this task in order to coordinate the movement of wholesale electricity and provide access
to the transmission grid for utility and non-utility users alike. Within the PJM region,
power plants are dispatched to meet load requirements without regard to operating
company boundaries. Generally, adjacent utility service territories import or export
12
See Tables III.B.1 and III.B.3.
13
See Appendix Table A-4(b).
14
The example uses an installed reserve margin (“IRM”) of 1.155 for 2010/2011, which is
applicable for planning reserves on a regional basis for the entire pool of PJM resources. IRM
establishes a level of installed capacity resources that will provide acceptable reliability levels for
the PJM region – and not on an individual state basis – considering demand forecasts, available
unforced capacity from existing generation, and the probability that a generating unit will not be
available (i.e., Equivalent Demand Forced Outage Rate (“EFORd”)). See PJM, Resource
Adequacy Planning, 2009 PJM Reserve Requirements Study, Table I - 1: Historical RRS
Parameters, 3, available at:
http://www.pjm.com/planning/resource-adequacy-
planning/~/media/documents/reports/2009-pjm-reserve-requirement-study.ashx
.
7
wholesale electricity as needed to reduce the total amount of installed capacity required
by balancing retail load and generation capacity over a regional, diversified system.
Within eastern PJM, the District of Columbia, Maryland, Delaware, New Jersey,
and Virginia continue to be net importers of electricity. Maryland imported about 40
percent of its electricity in 2009.
15
On a percentage basis, Maryland was the fifth largest
electric energy importer in the United States – surpassed by the District of Columbia,
Delaware, and Virginia in the immediate PJM area.
16
Much of the East Coast is
dependent on generation exported from states to the west of the region – many with low-
cost, largely depreciated, coal-fired generation assets. Prominent states within the PJM
region currently exporting more electricity in aggregate than consumed within each state
are Illinois, Indiana, Pennsylvania, and West Virginia.
17
Table III.A.1: State Electricity Imports (Year 2009) (GWh)
State Retail Sales
Losses & Direct
Use
Generation Net Imports
Percent Retail
Sales Imported
DC 12,199 785 35 (12,984) 106%
Delaware 11,258 1,298 4,842 (7,714) 69%
Idaho 22,754 2,635 13,100 (12,333) 54%
Virginia 108,462 8,338 70,082 (46,719) 43%
Maryland 62,589 5,924 43,775 (24,738) 40%
California 259,584 31,858 204,776 (84,137) 32%
New Jersey 75,780 5,630 68,811 (19,598) 26%
Massachusetts 54,359 3,216 38,967 (14,036) 26%
Tennessee 94,650 7,137 79,717 (22,070) 23%
Wisconsin 66,286 5,825 59,959 (12,153) 18%
Minnesota 64,004 6,891 52,492 (10,611) 17%
North Carolina 127,658 11,672 118,407 (20,922) 16%
Louisiana 78,670 24,670 90,994 (12,346) 16%
Ohio 146,300 11,550 136,090 (21,755) 15%
Georgia 130,766 15,814 128,698 (17,881) 14%
Florida 224,750 21,646 217,952 (28,444) 13%
Colorado 51,036 4,345 50,566 (4,815) 9%
Mississippi 46,049 5,563 48,701 (2,911) 6%
New York 140,034 3,026 133,151 (7,606) 5%
Alaska 6,270 770 6,702 (337) 5%
Kentucky 88,809 5,397 90,630 (3,576) 4%
Hawaii 10,126 1,166 11,011 (282) 3%
Michigan 98,121 10,076 101,203 (1,357) 1%
Texas 345,296 54,439 397,168 (2,456) 1%
Source: State Electricity Profiles 2009, U.S. ENERGY INFORMATION ADMINISTRATION, Table 10, (April 15,
2011) available at: http://www.eia.gov/cneaf/electricity/st_profiles/sep2009.pdf.
15
State Electricity Profiles 2009, U.S. ENERGY INFORMATION ADMINISTRATION, Table 10, (April 15,
2011) available at: http://www.eia.gov/cneaf/electricity/st_profiles/sep2009.pdf.
16
Id.
17
Id.
8
B. Maryland Generation Profile: Age and Fuel Characteristics
Most electric generating capacity in Maryland is provided by coal-fired power
plants, which contribute approximately 39 percent of the summer peak capacity available
in-State. The vast majority of the State’s coal-fired generation capacity, approximately
70 percent, is provided by power plants thirty-one or more years old. Approximately 41
percent of all capacity in Maryland burns oil or gas as a fuel source, and the majority of
these facilities are aging. Overall, approximately 67 percent of Maryland generating
capacity has been in operation for over 30 years. As indicated in Table III.B.1, only
about 16 percent of the State’s summer generating capacity has been constructed in the
past 20 years, and only about 7 percent has been constructed in the last 10 years.
Table III.B.1: Maryland Generating Capacity Profile (Year 2010)
Primar
y
Fuel
Type
Summer
(MW)
Pct. Of
Total
1-10
Years
11-20
Years
21-30
Years
31+
Years
Coal 4886 39.04% 0.0% 16.7% 13.0% 70.3%
Oil & Gas 5126 40.96% 14.2% 21.0% 13.3% 51.5%
Nuclear 1705 13.62% 0.0% 0.0% 0.0% 100.0%
Hydroelectric 590 4.71% 0.0% 0.0% 0.0% 100.0%
Other &
Renewables
209 1.67% 43.9% 25.9% 30.2% 0.0%
TOTAL 12516 100.00% 6.5% 15.6% 11.0% 66.9%
Capacity Age of Plants, by % of Fuel Type
Source: Report EIA-860: “GenY10” Excel, U.S. ENERGY INFORMATION ADMINISTRATION, (Nov. 30, 2011),
available at: http://www.eia.gov/cneaf/electricity/page/eia860.html.
In the past few years several older generating units in the eastern PJM region have
requested deactivation. These older generating units are located in Delaware,
Pennsylvania, New Jersey, Virginia, and the District of Columbia. These older
generation units typically have operated only a limited number of hours each year
recently and generate electricity at relatively high marginal costs. However, the units
also may be helpful in ensuring reliable electric service in the region. PJM undertakes an
analysis to determine the parameters under which units may deactivate or continue to
operate.
18
The following paragraphs summarize the pending deactivations of generating
facilities in the PJM region; several official owner requests for retirement date back to
2007.
In 2007, owners of power plants requested deactivation of units at locations in
D.C.: two Buzzard Point plants with a combined capacity of 240 MW; and two Benning
site power plants, 550 MW. The reliability issues have been identified for all units and
18
Manual M-14D: Generator Operational Requirements, Revision: 17, PJM (effective date Jan. 1,
2010), available at: http://www.pjm.com/~/media/documents/manuals/m14d.ashx.
9
are expected to be resolved to meet the requested deactivation dates.
19
All the units are
scheduled for deactivation on May 31, 2012.
In 2009, owners of power plants requested deactivation of units at three locations
in New Jersey and Pennsylvania: two Cromby units (Pennsylvania) with a combined
capacity of 345 MW; two Eddystone units (Pennsylvania), 588 MW; and two units at the
Kearny (New Jersey) site, 250 MW. On May 31, 2011, one Cromby unit and one
Eddystone unit were deactivated
20
; the remaining four units have requested deactivation
dates between May of 2011 and June of 2012. Reliability impacts were identified with
the Eddystone unit and with the Cromby unit. The requested deactivation date for the
Eddystone unit has been delayed from May 31, 2011 to May 31, 2012, and the requested
deactivation date for the Cromby unit has been delayed from May 31, 2011 to December
31, 2011. Additionally, a reliability analysis remains underway for both Kearny units.
21
In 2010, owners of power plants requested deactivation of five units that remain
pending: one Kearney unit with a capacity of 21 MW; a Cromby Diesel unit, 2.7 MW;
the Ingenco Petersburg plant, 2.9 MW; an Indian River unit, 169.7 MW; and one Sporn
unit, 440 MW. The reliability analysis remains underway for the Kearney unit, with a
projected deactivation timeline reaching into May of 2015. The reliability analyses were
completed for the other four units, and all issues are expected to be resolved to meet the
requested deactivation dates.
22
Depending on the unit, deactivation is projected between
May of 2011 and December of 2013.
In 2011, owners of power plants requested deactivation of nineteen units: two
State Line units with a combined capacity of 515 MW; one Vineland unit, 23 MW; one
Viking Energy unit, 16 MW; five Potomac River units, 482 MW; four Chesapeake units,
576 MW; one Yorktown unit, 159 MW; one Bergen unit, 21 MW; one Burlington unit,
21 MW; one National Park unit, 21 MW; one Mercer unit, 115 MW; and one Sewaren
unit, 111 MW. The reliability analyses remain underway for the majority of the units,
although results are available for both State Line units, the Vineland unit, the Viking
Energy unit, and all five Potomac River units. The reliability issues identified in the
completed analyses are expected to be resolved to meet the requested deactivation
dates.
23
Depending on the unit, deactivation is projected between 2012 and 2015.
Several requests for deactivation were filed in the opening months of 2012. One
noteworthy request is an application submitted on January 26, 2012 by FirstEnergy
19
Pending Deactivation Requests, PJM PLANNING (Feb. 6, 2012), available at:
http://www.pjm.com/planning/generation-retirements/~/media/planning/gen-retire/pending-
deactivation-requests.ashx.
20
PJM Generator Deactivations, PJM PLANNING (Jan. 10, 2012), available at:
http://www.pjm.com/planning/generation-retirements/~/media/planning/gen-retire/generator-
deactivations.ashx.
21
Pending Deactivation Requests, PJM PLANNING (Feb. 6, 2012), available at:
http://www.pjm.com/planning/generation-retirements/~/media/planning/gen-retire/pending-
deactivation-requests.ashx.
22
Id.
23
Id.
10
(formerly Allegheny Power) that references two units located in this State; R. Paul Smith
3 has been in service for 64 years and represents a 28 MW capacity, while R. Paul Smith
4 has been in service for 43 years and represents a capacity of 87 MW. The reliability
analysis is underway, and PJM has listed a projected deactivation date of September 1,
2012 for both R. Paul Smith units.
24
The Maryland generating profile differs considerably from its capacity profile.
Coal and nuclear facilities generate over 88 percent
25
of all electricity produced in
Maryland, even though they represent little more than half of in-State capacity.
26
In
contrast, oil and gas facilities, which tend to operate as mid-merit or peaking units that
come on-line only when needed, generate less than 6 percent of the electricity produced
by in-State resources, while representing approximately 41 percent of in-State capacity.
27
Table III.B.2 summarizes Maryland’s in-State fuel-mix in MWh by generating sources
for 2009. In 2009, Maryland plants produced 43,774,832 MWh of electricity.
Table III.B.2: Maryland Electric Power Generation Profile (Year 2009)
Source MWh
Share
(%)
Coal 24,162,345 55.2
Oil & Gas 2,366,927 5.4
Nuclear 14,550,119 33.2
Hydroelectric 1,888,769 4.3
Other & Renewables 806,671 1.9
Total 43,774,832 100.0
Source: Maryland Electricity Profile, U.S. ENERGY INFORMATION
ADMINISTRATION, Table 5, (April 15, 2011), available at:
http://www.eia.gov/cneaf/electricity/st_profiles/maryland.html.
The total summer capacity of Maryland generators is approximately 12,516
MW,
28
of which approximately 80 percent of the in-State generation capacity is owned
by two companies or their subsidiaries: Constellation Energy Group and GenOn Energy,
Inc. (“GenOn”). Constellation Energy Group owns about 43 percent of this capacity, and
GenOn owns about 37 percent.
29
Nearly two-thirds (65 percent) of the State’s power
plant capacity resides in one of four counties: Prince George’s, 21 percent; Anne
Arundel, 18 percent; Calvert, 14 percent; and Charles, 12 percent. Table III.B.3 lists
Maryland generating units by owner, county, and capacity.
24
Id.
25
See Table III.B.2. In 2009 coal facilities generated 55.2% of Maryland’s electricity and nuclear
facilities generated 33.2%, for a total representative of 88.4% of Maryland’s electric power
generation profile in 2009. Id.
26
See Table III.B.1. Coal facilities represented 39.04% of the in-State capacity in 2010 while
nuclear facilities represented 13.62% of the capacity in 2010. Therefore, coal and nuclear
facilities combined for 52.66% of Maryland’s generating capacity profile in 2010. Id.
27
Id.
28
See Table III.B.3.
29
Id.
11
Table III.B.3: Generation by Owner, County, and Capacity (Year 2010)
Operator/Owner Plant Name County
Name Plate Summer
Pct. Summer
A & N Electric Smith Island
Somerset 1.7 1.6 0.01%
AES Warrior Run AES Warrior Run
Allegany 229 180 1.44%
Allegheny Energy R Paul Smith
Washington 109.5 115 0.92%
American Sugar Domino Sugar
Baltimore City 17.5 17.5 0.14%
Town of Berlin Berlin
Worcester 9 9 0.07%
BP Piney & Deep Creek LLC Deep Creek
Garrett 20 18 0.14%
Calpine Mid-Atlantic Generation LLC Crisfield Somerset 11.6 10.4 0.08%
Constellation Calvert Cliffs Calvert 1828.7 1705
Constellation Brandon Shores Anne Arundel 1370 1273
Constellation C P Crane Baltimore 415.8 399
Constellation Gould Street Baltimore City 103.5 97
Constellation Herbert A Wagner Anne Arundel 1058.5 975.9
Constellation Notch Cliff Baltimore 144 116.7
Constellation Perryman Harford 404.4 353.6
Constellation Philadelphia Baltimore City 82.8 60.9
Constellation Riverside Baltimore 257.2 228
Constellation Westport Baltimore City 121.5 115.8
Constellation Solar Maryland, LLC McCormick & Co. Inc. at Belcamp Hartford 1.4 1.4 0.01%
Covanta Montgomery, Inc. Montgomery County Resource Recovery Montgomery 67.8 54 0.43%
Criterion Power Partners LLC Criterion Wind Project Garrett 70 70 0.56%
Eastern Landfill Gas LLC Eastern Landfill Gas LLC Baltimore 3 3 0.02%
Easton Utilities Comm Easton Talbot 33.6 31.9
Easton Utilities Comm Easton 2 Talbot 38.8 37
Energy Recovery Operations, Inc Harford Waste to Energy Facility Harford 1.2 1.1 0.01%
Exelon Power Conowingo Harford 506.8 572 4.57%
GenOn Chalk Point LLC Chalk Point LLC Prince Georges 2,647 2,347
GenOn Mid-Atlantic LLC Morgantown Generating Plant Charles 1,548 1,477
GenOn Mid-Atlantic LLC Dickerson Montgomery 930 844
Industrial Power Generating Company LLC Wicomico Wicomico 5.4 5.4 0.04%
Maryland Environmental Service Eastern Correctional Institute Somerset 5.8 4.6 0.04%
NAEA Rock Springs LLC NAEA Rock Springs LLC Cecil 772.6 652 5.21%
NewPage Corporation Luke Mill Allegany 65 60 0.48%
NRG Vienna Operations Inc Vienna Operations Dorchester 183 170 1.36%
Panda-Brandywine LP Panda Brandywine LP Prince Georges 288.8 230 1.84%
Power Choice/Pepco Energy Serv NIH Cogeneration Facility Montgomery 22 21.2 0.17%
Prince George's County Brown Station Road Plant I Prince Georges 6.7 5.6 0.04%
RG Steel LLC RG Steel Sparrows Point, LLC Baltimore 120 152.3 1.22%
SCE Engineers Montgomery County Oaks LFGE Plant Montgomery 2.4 2.3 0.02%
Solo Cup Co Solo Cup Co Baltimore 11.2 11.2 0.09%
Trigen Inner Harbor East, LLC Inner Harbor East Heating Baltimore City 2.1 2.1
Trigen-Cinergy Solutions College Park UMCP CHP Plant Prince Georges 27.4 20.8
Wheelabrator Environmental Systems Wheelabrator Baltimore Refuse Baltimore City 64.5 61.3 0.49%
Worcester County Renewable Energy LLC Worcester County Renewable Energy Worcester 2 2 0.02%
13,611.20 12,515.60 100.00%
0.18%
0.55%
Capacity Statistics (MW)
42.55%
37.30%
Source: Report EIA-860: “GenY10” Excel, U.S. ENERGY INFORMATION ADMINISTRATION, (Nov. 30,
2011), available at: http://38.96.246.204/cneaf/electricity/page/eia860.html.
12
C. Potential Generation Additions in Maryland
Siting for central station generation in Maryland continues to be an important
concern. There are reliability, environmental, and competitive issues that must be
resolved when finding an appropriate location for a new generator. Generation is largely
deregulated and currently the responsibility of independent power producers. Generation
companies have proposed various projects, but they are typically either expansions of
existing sites or conjoined locations with other industrial or government facilities.
Without the financial assurances that were typically available through utility ownership,
it has become increasingly difficult for generation companies to secure potential new
sites, long-term sales contracts, and the funding necessary to build new generation.
Other sources of generation have benefited from the Commission’s small
generation interconnection rules. Distributed generation from solar facilities and
combined heat and power installations are examples of small scale generation. Co-
locating smaller generation facilities with other industrial process facilities provides an
alternative to increasing central station generation capacity.
However, regardless of the growth in distributed generation, there will still be a
need for central power stations that can be acceptably developed. Areas in or near the
State that may be considered for new generation include projects in the Atlantic Ocean,
the Nanticoke River area around Vienna on the Lower Eastern Shore, the Calvert Cliffs
area in Southern Maryland, various brownfield sites in the Central Maryland area, and
wind power sites in the mountains of Western Maryland. Upgrades and additions to
existing sites (i.e., brownfield deployment) offer advantages over new, undeveloped
greenfield sites with respect to licensing, transmission facilities, and environmental
concerns.
Although no significant generation has been constructed in Maryland within the
past few years, the Commission has granted both CPCNs and approvals for construction
for those who quality for CPCN exemptions for new generation. Furthermore, no units
have been retired recently. The Commission currently has before it several applications
for construction of new generation and transmission. When and if constructed, these
projects will make available additional electricity for use in Maryland and the PJM
region, and should ease congestion substantially.
In 2009, the Commission initiated a new proceeding (Case No. 9214) to consider
proposals for new electric generation facilities in Maryland. On September 29, 2011, the
Commission issued a Notice of Approval of Request for Proposals for New Generation to
be issued by Maryland Electric Distribution Companies. Attached to that notice was a
Request for Proposals inviting interested persons to submit proposals to the Commission
to construct new generation facilities that would produce and sell electricity to
Maryland’s regulated electric distribution companies. Proposals were due to the
Commission January 20, 2012. Additionally, the Commission set for comment whether
new generation is needed to meet the long-term anticipated demand in Maryland for
13
standard offer service and other electric supply and if so, the quantity of generation
needed. A hearing on the comments was held January 31, 2012.
The status of Commission proceedings covering proposed new electric generator
facilities in Maryland (projects ineligible for CPCN exemptions as discussed in Section
III.D.) that were active cases in late 2009 through 2011, is as follows :
CN9206: A CPCN application from Constellation Power Source Generation Inc.
authorizing the modification of the C.P. Crane generating station for the use of
sub-bituminous coal in Baltimore County. Testimony filed January 13, 2010. In-
service June 9, 2010.
CN9218: A CPCN application from UniStar, LLC authorizing the modification of
the Calvert Cliffs Unit 3 nuclear project for ancillary equipment that will increase
air emissions. In-service April 26, 2010.
CN9199: A CPCN Application from Energy Answers International, Inc. to
construct a 120 MW Generating Facility in Baltimore using processed waste for
fuel. On December 29, 2011, Energy Answers filed a motion to toll its
construction deadline contained in the CPCN.
CN9229: A CPCN Application from Mirant for STAR, a processor for flyash at
the Morgantown Power Plant in Charles County. In-service November 4, 2010.
In addition to the aforementioned CPCN applications, Maryland is experiencing
an uptick in the amount of solar generation capacity both planned and already available to
the State. Section VI.C. details the Commission’s efforts to spur small-scale solar
generator interconnection throughout Maryland. On the utility-scale, plans for new solar
generation also began taking shape in 2011; Case Number 9272 was opened for the
CPCN application of Maryland Solar LLC to construct a 20 MW solar photo-voltaic
generating facility in Hagerstown, Maryland. The Commission granted approval on
October 8, 2011 for construction of the Hagerstown facility in Order No. 84369. Other
notable examples of planned new solar generation include the October 26, 2011
Commission approval for SMECO Solar LLC to construct a Type IV solar generator in
Hughesville.
30
Additionally, on December 14, 2011, the Commission granted approval to
Constellation Solar Holding, LLC to construct a solar photovoltaic generation project
located at Mount St. Mary’s University comprising two solar arrays with capacities of
1.25 MW and 250 kW, respectively.
31
The number of projects for which a transmission interconnection request (capacity
or energy) has been filed with PJM provides an indication of potential generation
capacity additions in Maryland. Table III.C.1 lists the new generation projects located in
Maryland for which a transmission interconnection request has been made to PJM and
that are categorized as under study, under construction, providing partial service, or
30
The Commission granted approval of SMECO Solar LLC’s application for an exemption of the
CPCN requirement. Letter Order, Maillog No. 134380.
31
The Commission granted approval of Constellation Solar Holding, LLC’s application for an
exemption of the CPCN requirement. Letter Order, Maillog No. 135780.
14
currently suspended. The Table demonstrates the diversity of projects being pursued
throughout the State. The vast majority (about 89%) of proposed new generation
capacity would be located within the Southern Maryland Electric Cooperative, Inc.
(“SMECO”) and Pepco service territories, and would use primarily natural gas or nuclear
fuel. Additional generation capacity, especially from renewable sources, has been
proposed for the DPL and PE service territories.
Table III.C.1: PJM Transmission Queue Active New Generating Capacity
BGE
290
DPL
478
PE
259
PEPCO
28
SMECO
-
TOTAL
205
Service
Territory
3,060 - 11,474 2010-2017
- 1,640 1,640 2017
8,520 - 8,548 2012-2017
- - 259 2009-2013
- - 478 2009-2017
259 - 549 2012-2015
Other &
Renewable Total
In-service
DatesNuclearNatural Gas
Plant Capacity (MW) By Fuel
Source
: See Appendix Table A-9.
D. CPCN Exemptions for Generation
Pursuant to Public Utilities Article § 7-207.1, certain power generating stations
are exempt from the requirement to obtain a CPCN, subject to Commission approval,
prior to commencing construction of the generating station. These approvals are
available to generating stations that are designed to provide on-site generated electricity
and that meet the following qualifications:
32
1. The capacity of the generating station does not exceed 70 MW; and
2. The electricity that may be exported for sale from the generating station to
the electric system is sold only on the wholesale market pursuant to an
interconnection, operation, and maintenance agreement with the local
electric company.
33
32
PUA § 1-101(s) defines “On-site generated electricity” as electricity that: (1) is not transmitted or
distributed over an electric company’s transmission or distribution system; or (2) is generated at a
facility owned or operated by an electric customer or operated by a designee of the owner who,
with the other tenants of the facility, consumes at least 80% of the power generated by the facility
each year.
33
The Statute also provides for an exemption from the CPCN process for a generating station that
does not exceed 25 MW if electricity that may be exported for sale from the generating station to
the electric system is sold only on the wholesale market pursuant to an interconnection, operation,
and maintenance agreement with the local electric company, and at least 10% of the electricity
generated at the generating station each year must be consumed on-site. MD. C
ODE ANN., PUB.
UTIL. § 7-207.1 (2011).
15
For wind-powered generating stations with a capacity up to 70 MW, there are two
additional qualifications that must be met in order to be granted approval without
obtaining a CPCN. The first is that the generating station must be land-based; therefore,
any off-shore facility within State waters will be required to obtain a CPCN. The second
qualification is that the Commission must provide an opportunity for public comment at a
public hearing.
The Commission’s PUA § 7-207.1- approved application requires the applicant to
select one of four specific types of generating stations: Type I, Type II, Type III, or Type
IV. With the exception of Type I, all generators are required to obtain an
Interconnection, Operation, and Maintenance Agreement (“Interconnection Agreement”)
with the local Electric Distribution Company (“EDC”). Type I generators must obtain a
letter from the local EDC that states an Interconnection Agreement is not necessary.
A Type I generator is not synchronized with the local electric company’s
transmission and distribution system and will not export electricity to the electric
system.
34
An emergency or back-up generator is the most common Type I generator. A
Type II generator is synchronized with the electric system; however, it will not export
electricity to the electric system. Generators used for peak-load shaving or generators
participating in a demand response program are the most common form of Type II
generators. Type III generators are synchronized with the electric system and export
electricity for sale on the wholesale market. A Type IV generator is a generator that is
synchronized with the electric system, but utilizes the disconnect feature of an inverter to
prevent export of power in the event of a power failure on the utility’s grid.
In order to obtain approval to construct a generator under PUA § 7-207.1, an
applicant must submit a completed application. In addition, the generator will need a
wholesale sales agreement with PJM if the generator is selling electricity on the
wholesale market. It is important to note that the approval does not exempt an applicant
from complying with other regulations or from obtaining all other necessary State and
local permits, such as those required by the Air and Radiation Management
Administration at the Maryland Department of the Environment (“MDE”).
Table III.D.1 provides an overview of the number and capacity of generators that
have applied for PUA § 7-207.1 approvals on an annual basis. The number of
applications has generally been increasing over time, and these generators have a
cumulative generation capacity of over 1,300 MW.
34
PUA § 1-101(h) defines “Electric company,” with certain exclusions, as a person who physically
transmits or distributes electricity in the State to a retail electric customer.
16
Table III.D.1: Construction Approvals for CPCN Exempt Generation
Period Approved Applications No. of Units Total (MW)
Calendar Year 2001 4 7 35.4
Calendar Year 2002 9 26 68.3
Calendar Year 2003 21 29 43.4
Calendar Year 2004 36 58 77.1
Calendar Year 2005 36 70 94.4
Calendar Year 2006 31 55 91.4
Calendar Year 2007 40 62 67.3
Calendar Year 2008 72 130 212.1
Calendar Year 2009 102 153 269.2
Calendar Year 2010 101 152 167.2
Calendar Year 2011 78 138 188.6
Total 530 880 1314.4
Pending 10 16 16.0
Total (Including Pending) 540 896 1330.4
Source: PSC database.
Note
: 2011 data is current as of October 31, 2011. Each application may contain multiple generation units.
Table III.D.2 reflects that fossil fuel generators were 92.6% of the 896 generator
units reported. These fossil fuel generators provided 1070.0 MW (80.4%) of the total
1330.4 MW of generating capacity reported. Oil remained the dominant fuel source for
new generators. Oil-fired generators were 930.1 MW (69.9%) of the total generation
reported. Wind-powered units provided 189.6 MW (14.3%) of total CPCN exempt
capacity. Solar-powered units provided 44.7 MW (3.4%) of total CPCN exempt
capacity.
17
Table III.D.2: Number and Capacity in MW of CPCN Exempt
Generating Units by Energy Resource
Energy Resource
Total
Approved
Percent of
Total
Approved
GENERATOR UNITS
Oil
790 88.2%
Natural Gas
38 4.2%
Fossil
Propane
2 0.2%
Fossil Total 830 92.6%
Biomass
1 0.1%
Digester Gas
3 0.3%
Landfill Gas
3 0.3%
Solar
56 6.3%
Renewable
Wind
3 0.3%
Renewable Total 66 7.4%
Grand Total 896 100.0%
CAPACITY (MW)
Oil
930.1 69.9%
Natural Gas
139.8 10.5%
Fossil
Propane
0.2 0.0%
Fossil Total 1070.0 80.4%
Biomass
19.8 1.5%
Digester Gas
3.2 0.2%
Landfill Gas
3.1 0.2%
Solar
44.7 3.4%
Renewable
Wind
189.6 14.3%
Renewable Total 260.3 19.6%
Grand Total 1330.4 100.0%
Source: PSC database.
Note: Data is current as of November 1, 2011.
18
IV. TRANSMISSION INFRASTRUCTURE: PJM, MARYLAND, AND
NATIONAL
A. Introduction
Transmission facilities in PJM and Maryland have continued to play a key role in
energy supply. With Maryland’s dependence on energy imports, it is necessary that
adequate transmission facilities be available to reliably provide electricity supplies.
While all network systems can experience congestion at times, portions of the Mid-
Atlantic States -- including central Maryland and the Delmarva Peninsula -- have
continued to experience significantly higher levels of congestion than the rest of PJM.
This, in turn, has led to higher energy and capacity costs in portions of Maryland and the
surrounding states since local, but more expensive, generation resources had to be
deployed to meet load. Adequate capacity and reliable supplies of electricity are
continually monitored, managed, and, when necessary, supplemented with additional
infrastructure.
B. Eastern Interconnection Planning Collaborative
During 2011, the Eastern Interconnection Planning Collaborative (“EIPC”)
completed the first phase of its work identifying a broad range of alternative futures to be
analyzed by a production cost model. Eight futures were modeled under varying
assumptions. The futures modeled were:
1. Business as Usual – This Future continues today’s policies.
2. National Carbon Policy/National Implementation – This Future envisions a
national Carbon Emission Mitigation policy to be fulfilled by constructing
no/low carbon – emitting energy generation facilities in the most productive
generation resource areas and building transmission to connect those
generation facilities to customers in the Eastern Interconnection.
3. National Carbon Policy/Regional Implementation – This Future concentrates
on fulfilling a national Carbon Emission Mitigation Policy by constructing
generation and transmission within each region to serve the customers within
that region.
4. High Energy Efficiency/Demand Response/Distributed Generation/Smart
Grid – This Future focuses on developing local programs to avoid the need for
large generation and transmission construction.
5. National RPS/National Implementation – Imposes a 30% Renewable Portfolio
Standard which may be fulfilled by importing renewable from the areas of the
Eastern Interconnection with the highest renewable energy resource potential.
6. National RPS/Regional Implementation – The RPS is assumed to be fulfilled
using renewable energy resource potential within each region of the Eastern
Interconnection.
19
7. Nuclear Resurgence – This Future looks at incenting the construction of
nuclear technologies as an option on other generation technologies.
8. National Carbon Policy/National Implementation with high
Efficiency/Demand Response – This Future combines Future Nos. 2 and 4.
The results from these modeling runs, which include what type of generation is
built, where it will be located, how much is needed, and at what cost, can be found at
www.eipconline.com. Next, EIPC identified three future scenarios for which a complete
transmission build-out will be designed. This exercise will provide an estimate of the
transmission costs associated with each scenario. The results of the transmission build-
out should be available in early 2012.
C. The Regional Transmission Expansion Planning Protocol
Planning the enhancement and expansion of transmission capability on a regional
basis is one of the primary functions of the wholesale market operator, PJM. PJM
implements this function pursuant to the Regional Transmission Expansion Planning
Protocol set forth in Schedule 6 of the PJM Operating Agreement.
PJM annually develops the Regional Transmission Expansion Plan (“RTEP”) to
meet system enhancement requirements for new backbone transmission lines and
interconnection requests for new generation. To establish a starting point for
development, PJM performs a “baseline” analysis of system adequacy and security. The
baseline is used for conducting feasibility studies on behalf of all proposed generation
and transmission projects. Subsequent System Impact Studies for those potentially viable
projects provide recommendations that become part of the RTEP Report.
PJM’s RTEP looks at a 15-year projection of the grid to predict reliability
problems. The system is planned for the probability of loss of load to be one day in ten
years. Single contingency analysis allows for the grid to function with the loss of any
one line. In some cases, double contingency analysis is used. PJM’s 15-year planning
horizon process has predicted that the congestion on the eastern and western interfaces
may cause both load deliverability and generator deliverability issues in central
Maryland.
35
Deliverability issues can be a result of significant load growth and the
retirement of existing generation.
36
Ideally, these problems can be solved with a
combination of new generation, transmission projects, and demand response.
The RTEP process applies reliability criteria over a 15-year horizon to identify
transmission constraints and reliability concerns. PJM uses CETO/CETL
37
analysis to
determine the import capabilities of the transmission system to supply the peak load
requirements for sub-regions within PJM. There are currently 23 sub-regions or load
35
The central Maryland region of the Mid-Atlantic area generally includes northern Virginia and the
Baltimore/Washington region.
36
Generation slated for retirement includes Benning Road, Buzzard Point, Potomac River, and Gude
Landfill in Washington, DC; and Indian River on the Eastern Shore.
37
Capacity Emergency Transfer Objective/ Capacity Emergency Transfer Limit.
20
deliverability areas (“LDAs”) in PJM. The Transmission Expansion Advisory
Committee (“TEAC”) is the primary forum for stakeholders to discuss the RTEP results.
The Commission is an active participant in the RTEP and regularly attends the TEAC
meetings.
1. Baseline Reliability Assessment
PJM establishes a baseline from which the need and responsibility for
transmission system enhancements can be determined. PJM performs a comprehensive
load flow analysis of the ability of the grid to meet reliability standards, taking into
account forecasted loads, imports and exports to neighboring systems, existing generation
and transmission assets, and anticipated new generation and generation retirements. The
baseline reliability assessment identifies areas where the planned system is not in
compliance with standards required by the North American Electric Reliability
Corporation (“NERC”)
38
and the regional reliability councils. The baseline assessment
develops and recommends enhancement plans to achieve compliance.
2. Inter-regional Planning
PJM is engaged in planning processes that address issues of mutual concern to
PJM and neighboring transmission grid systems: the Midwest Independent System
Operator (“ISO”); ISO New England; the New York ISO; the Tennessee Valley
Authority; and the North Carolina Planning Collaborative (added in 2009). The Inter-
regional Planning Stakeholder Advisory Committee facilitates stakeholder review and
input into the Coordinated System Plan. Coordinated regional transmission expansion
planning across seams is expected to reduce congestion on an inter-Regional
Transmission Organization (“RTO”) basis, and enhance the physical and economic
efficiencies of congestion management. Inter-regional ties are a benefit for reliability,
especially when load centers peak at different times (referred to as “load diversity”).
This kind of forum has been important for addressing problems such as loop flows
around Lake Erie.
3. Obligation to Build RTEP Projects
PJM’s Transmission Owners’ Agreement obligates transmission owners to
proceed with building transmission projects that are needed to maintain reliability
38
Since 1968, NERC has been committed to ensuring the reliability of the bulk power system in
North America.
To achieve that goal, NERC develops and enforces reliability standards; assesses
adequacy annually via a 10-year forecast and winter and summer forecasts; monitors the bulk
power system; audits owners, operators, and users for preparedness; and educates, trains, and
certifies industry personnel. NERC is a self-regulatory organization, subject to oversight by
FERC. As of June 18, 2007, FERC granted NERC the legal authority to enforce reliability
standards with all U.S users, owners, and operators of the bulk power system, and made
compliance with those standards mandatory and enforceable. NERC's status as a self-regulatory
organization means that it is a non-government organization which has statutory responsibility to
regulate bulk power system users, owners, and operators through the adoption and enforcement of
standards for fair, ethical, and efficient practices.
21
standards as approved by the PJM Board of Directors. Transmission owners can
voluntarily build these projects, or PJM can file with FERC to request FERC to order the
project to be built. In Maryland, CPCNs are required for transmission lines above 69,000
volts or modifications to existing facilities.
4. PJM’s Authority
FERC approved PJM as an Independent System Operator in 1997. Since that
time, PJM has administered its RTEP as described in Schedule 6 of the Operating
Agreement. PJM has subsequently received authority from FERC for procedures and
rules for transmission expansions needed to enable the interconnection of new and
expanded generation and merchant transmission facilities. PJM has amended the RTEP
to include the development of transmission projects to support competition in wholesale
electric markets, allowing it to justify projects for economic reasons as well as reliability.
PJM received final FERC approval as an RTO in 2002. As an RTO, PJM is the
administrator of the Open Access Transmission Tariff (“OATT”) as approved by FERC.
The OATT is the basis for PJM to collect charges to recover the costs of projects owned,
constructed, or financed by the transmission owners. Transmission owners file rate
schedules with FERC to recover transmission investments made pursuant to the RTEPs
approved by the PJM Board. The OATT enables generation to be sold anywhere in the
system.
D. Transmission Congestion in Maryland
1. PJM’s Definition of Congestion
PJM’s Locational Marginal Pricing (“LMP”) system takes account of congestion
in determining electricity prices. It reflects the value of the energy at the specific location
and time it is delivered. Theoretically, if the lowest-priced electricity could
simultaneously be distributed across the entire 13 states and the District of Columbia
(thereby encompassing the entire PJM wholesale market), prices would be the same
across the entire PJM grid. However, the capital investments that would be required for
such an expansive transmission system would be cost prohibitive. Therefore, more
expensive but advantageously located power plants that generate electricity are required
to meet the demand. As a result, LMPs are higher in the congested areas and lower at the
source of cheaper power. Congestion costs vary significantly during the course of a day,
seasonally, and from year to year. Persistent patterns of high LMPs can indicate future
reliability problems and the need for new generation, new transmission, and/or demand
response.
2. Location of Congestion
In 2010, the PE South interface continued to be the largest contributor to
congestion costs for the third consecutive year. This one constraint’s costs were nearly
22
double the sum of all remaining constraint costs. The PE South interface continues to be
the primary west-to-east transfer constraint.
39
3. Costs of Congestion
Congestion reflects the underlying characteristics of the power system, including
the nature and capability of transmission facilities and the cost and geographical
distribution of generation facilities. Total PJM congestion costs increased by $709.1
million (or 99%) from $719 million in calendar year 2009 to $1,428 billion in calendar
year 2010. Maryland utilities shared in these increased congestion costs.
Zone
2010 Total Annual
Zonal Congestion
Costs ($ million)
40
2009 Total Annual
Zonal Congestion
Costs ($ million)
41
Allegheny Power (Potomac Edison) 282.7 95.3
Baltimore Gas and Electric 91.6 33.5
Delmarva Power 47.2 31.1
Potomac Electric Power 98 58.4
Wholesale prices for electricity are determined in PJM’s Reliability Pricing
Model (“RPM”) Base Residual Auctions (“BRAs”). Blocks of capacity are sold
regionally for future delivery. The data below summarizes the annual capacity price for
Maryland in 2014/2015 compared to the 2013/2014 delivery year.
42
Zone
2014/2015
$/MW-Day
2013/2014
$/MW-Day
Western Maryland (PE) 125.94 27.73
Central Maryland (BGE) 136.50 226.15
Central Maryland (PEPCO) 136.50 247.14
Delmarva (DPL) 136.50 245.00
Delmarva South 136.50 245.00
Transmission expansion for the bulk electric system can act to reduce the
differences from zone to zone and support reliability requirements and economic
concerns.
39
Data for 2010. The zones for Allegheny (Potomac Edison), DPL, and Pepco include territory
outside of Maryland (Delaware, District of Columbia, Pennsylvania, New Jersey, West Virginia,
Virginia). Monitoring Analytics, LLC, 2010 State of the Market Report for PJM, Table 7-13
(March 10, 2011), available at:
http://www.monitoringanalytics.com/reports/PJM_State_of_the_Market/2010.shtml.
40
Id. at Table 7-19.
41
Data for 2009. The zones for Allegheny (Potomac Edison), DPL, and Pepco include territory
outside of Maryland (Delaware, District of Columbia, Pennsylvania, New Jersey, West Virginia,
Virginia). Monitoring Analytics, LLC, 2009 State of the Market Report for PJM, Table 7-17
(March 11, 2010), available at: http://monitoringanalytics.com/reports/PJM
_State_of_the_Market/2009.shtml.
42
2014-2015 RPM Pricing Points, PJM (May 13, 2011), available at:
http://www.pjm.com/markets-and-operations/rpm/rpm-auction-user-info.aspx#Item08.
23
Financial Transmission Rights (“FTRs”) and Auction Revenue Rights (“ARRs”)
give transmission service customers and PJM members an offset against congestion costs
in the Day-Ahead Energy Market. An FTR provides the holder with revenues, or
charges, equal to the difference in congestion prices in the Day-Ahead Energy market
across the specific FTR transmission path. An ARR provides the holder with revenues,
or charges, based on the price differences across the specific ARR transmission path that
results from the annual FTR auction. In PJM, FTRs have been available to network
service and long-term, firm, point-to-point transmission service customers as a hedge
against congestion costs since the inception of locational marginal pricing on April 1,
1998. FTRs became available to all transmission service customers and other PJM
members with the introduction of the annual FTR auction effective June 1, 2003.
In the 2009 to 2010 planning period, all ARRs and FTRs hedged more than 96.2%
of the congestion costs within PJM. During the first seven months of the 2010 to 2011
planning period, total ARR and FTR revenues hedged 78.7% of the congestion costs
within PJM.
43, 44
For the planning period 2009 to 2010, Potomac Edison and BGE were
hedged at greater than 100%, DPL at 55.2%, and Pepco at 19.7%.
Congestion of the electricity transmission grid continues to affect the
Baltimore/Washington area and to warrant attention. During the summer of 2010 overall
congestion rose by 99%, yet was still lower than congestion costs of 2005. This has
resulted primarily from reduced demand and the absence of significant generation or
transmission outages. The PJM metered peaks increased for 2010, but 2008 and 2009
were lower than the peaks in 2007 and 2006. This was due to the relatively mild weather,
the slowing economy, and increased diversity (non-coincident regional peaks).
For the 2014/2015 capacity auction, PJM announced an increase from the prior
2013/2014 auction in cleared Demand Resources of 4836.5 MW (or 52.1%).
E. High Voltage Transmission Lines in PJM
PJM’s 2010 Regional Transmission Expansion Plan was not published until
February 2011. However, the PJM Board approved over 400 individual bulk electric
system upgrades in 2010. Determined via PJM’s RTEP process, the upgrades are
required to support reliable electricity flows and ensure the power supply system meets
national standards through 2024. The PJM Board has approved more then $19.022
billion of bulk electric system upgrades since the inception of the RTEP process in 1997,
ensuring that PJM is compliant with NERC reliability criteria.
43
The ARR and FTR revenue adequacy results are aggregate results and all those paying congestion
charges were not necessarily hedged. Aggregate numbers do not reveal the underlying distribution
of FTR holders, their revenues, or those paying congestion premiums. The FTR markets can be
risky and have resulted in defaults for some participants. Financial entities own about 77% of all
Monthly Balance of Planning Period FTRs.
44
PJM Financial Transmission and Revenue Rights: 2010 State of the Market Report for PJM
(March 10, 2011), available at:
http://www.monitoringanalytics.com/reports/PJM_State_of_the_Market/2009/2009-som-pjm-
volume2-sec8.pdf.
24
The deep recession experienced by the country, which began in 2008, continues to
have a substantial impact on PJM’s RTEP. Load growth is a fundamental driver of
resource adequacy and transmission expansion plans. The slow economic recovery has
caused PJM to dramatically adjust its backbone transmission line project plans. In
particular, the 2011 load forecast issued in January 2011 forecasts significantly lower
load growth in the near term than in previous forecasts. Projects of interest to Maryland
which have been affected include:
Potomac-Appalachian Transmission Highline (“PATH”) is a 765-kV transmission
line that would extend 300 miles from the Amos Substation (Charleston, WV) to
the Kemptown Substation in Frederick County, Maryland. This project was
docketed as Case No. 9233. Although included in the 2010 RTEP as a baseline
transmission project, in an RTEP update for events since December 2010, PJM
stated, “Preliminary 2011 PJM RTEP process analysis suggests that the need for
the PATH line has moved several years into the future beyond 2015. This has led
the PJM Board to direct owners to suspend efforts on the PATH line pending a
more complete analysis in the 2011 RTEP.” PJM 2010 RTEP 2/28/2010, p. 1.
Mid-Atlantic Power Pathway (“MAPP”) is a 500-kV line that would connect the
Possum Point Substation in Virginia and the generation plants in southern
Maryland to Vienna and then to Indian River on the Delmarva Peninsula. The
portion under the Chesapeake Bay will be a submarine high-voltage direct current
line (“HVDC”). This project is docketed as Case No. 9179 at the MD PSC. On
Friday August 19, 2011 PHI announced that the new transmission line will be
delayed, suggesting that the new in-service date could be between 2019 and 2021.
Trans-Allegheny Interstate Line (“TrAIL”), 502 Junction to Loudon. Construction
was completed on TrAIL in 2011, and its in-service date was June 2011. This
500 kV transmission line runs from near the border of Pennsylvania and West
Virginia to northern Virginia.
Susquehanna to Roseland is a 500-kV line, approximately 130 miles from
northern Pennsylvania to northern New Jersey. Although its in-service date
technically remains 2012, permitting difficulties will delay this project.
The PJM RTEP requires that cost responsibility for transmission enhancements be
established. The cost of transmission facilities in PJM that operate at a voltage of 500 kV
and above are currently socialized across all PJM load. The backbone projects listed
above have secured incentive rate adders from FERC.
45
To make this determination,
45
For the MAPP project, FERC granted Pepco a 12.8% return on equity (including incentives), and
no rehearing was sought; as well, FERC granted BGE a 12.8% return on equity (including
incentives), and denied rehearing. The TrAIL project settled for a 12.7% return on equity
(including incentives). FERC granted PATH a 14.3% return on equity (including incentives);
however, rehearing remains pending.
25
FERC requires the applicant to satisfy its nexus test (non-routine project with advanced
technology) and address the rebuttable presumption standard (a project required by PJM).
Transmission projects not highlighted above but identified by the transmission
owners are listed in Table A-7 of the Ten-Year Plan for Maryland. For instance, the
Southern Maryland Electric Cooperative is continuing with plans for its 230 kV loop in
Southern Maryland.
V. DEMAND RESPONSE AND CONSERVATION AND ENERGY
EFFICIENCY
The Commission recognizes the potential of demand-side management ("DSM")
as a powerful tool to bolster energy efficiency and conservation efforts in our State.
Furthermore, DSM supports system reliability, energy security, energy and capacity price
mitigation (i.e., reducing overall energy costs), and enhanced energy market
competitiveness, and limits environmental impacts. The Commission encourages energy
service providers to offer DSM programs to customers where appropriate. Distribution
companies have been tasked with providing cost-effective DSM programs, particularly
for mass market residential and small commercial customers. As part of EmPower
Maryland,
46
the Commission has required the utilities to implement aggressive and cost-
effective demand management and energy conservation programs.
A. Statutory Requirements
Recognizing energy efficiency as one of the least expensive ways to meet
growing electricity demands in the State, the EmPower Maryland Energy Efficiency Act
(“Act”) was enacted on April 24, 2008. By statute, each utility
47
is required to develop
and implement cost-effective programs and services that encourage and promote the
efficient use and conservation of energy by consumers and utilities alike. EmPower
Maryland also establishes long-term reduction goals for electric consumption and
demand, based on a per capita and 2007 energy consumption baseline. The Act
specifically states at § 7-211(g)(1) and (2):
(1) To the extent that the Commission determines that cost-
effective energy efficiency and conservation programs and
services are available, for each affected class, require each electric
company to procure or provide for its electricity customers cost-
effective energy efficiency and conservation measures programs
and services with projected and verifiable energy electricity
savings that are designed to achieve the following a targeted
reduction of at least 5% by the end of 2011 and 10% by the end of
2015 of per capita electricity consumed in the electric company’s
service territory during 2007; and
46
See MD. CODE ANN., PUB. UTIL. § 7-211 (2011).
47
The term “Utilities” used in this Section refer to: BGE; DPL; Pepco; PE; and SMECO.
26
(2) require each electric company to implement a cost-effective
demand response program in the electric company’s service
territory that is designed to achieve a targeted reduction of at least
5% by the end of 2011, 10% by the end of 2013, and 15% by the
end of 2015, in per capita peak demand of electricity consumed in
the electric company’s service territory during 2007.
The Act also states at § 7-211(i)(1):
(1) In determining whether a program or service encourages and
promotes the efficient use and conservation of energy, the
Commission shall consider the: (i) cost–effectiveness; (ii) impact
on rates of each ratepayer class; (iii) impact on jobs; and (iv)
impact on the environment.
Prior to July 1 of each program planning phase (2008, 2011, 2014), the Act
requires each utility to consult with the Maryland Energy Administration (“MEA”),
Maryland Public Service Commission Staff (“Staff”), and other stakeholders regarding
the design and adequacy of the programs proposed by the utility. The 2011 planning
phase began in the summer of 2010 with requests for stakeholder input and progressed
through various stages of discussion and refinement. All plans were required to be
submitted by September 1, 2011 and hearings regarding the EmPower process took place
between October 12, 2011 and October 21, 2011. On December 22, 2011 the
Commission approved, with some modifications, the utilities' proposed plans in
Commission Order No. 84569.
The Commission’s December 22 Order provided increased guidance and
framework for the 2012-2014 program cycle. This included standardization of incentive
structures, the transition of Limited Income Energy Efficiency programs to the Maryland
Department of Housing and Community Development, the creation of various
workgroups to enhance and expand program offerings, and necessary updates to budgets
and surcharges associated with the EmPower Maryland program.
Commission Order No. 84569 also changes the reporting process for the 2012-
2014 cycle. Previously, utility reporting was done on a quarterly basis with an annual
summary report filed in January of the following year. The new requirements set forth a
semi-annual, formal filing process with required metric submissions filed informally with
Staff each quarter. The PSC, in consultation with MEA, will continue to provide an
annual report to the General Assembly regarding the status of the programs, a
recommendation for the appropriate funding level to adequately fund the programs and
services, and the per capita electricity consumption and peak demand for the previous
year.
27
B. Demand Response Initiatives
Demand Response is defined as changes in electric usage by end-use customers
from their normal consumption patterns either in response to changes in the price of
electricity over time or to incentive payments designed to induce lower electricity use at
times of high wholesale market prices and when system reliability is jeopardized. The
increase in electricity prices and changes in technology have spurred interest in finding
cost-effective means of reducing electricity consumption. Additionally, the price of
electricity in the wholesale markets serving the central and eastern portions of Maryland
is determined, in part, by the relative scarcity of generation and transmission capacities
serving those areas.
Demand Response initiatives comprise utility-run direct load control programs,
inclusive of their legacy demand response programs – the precursor of these Direct Load
Control (“DLC”) programs. These programs, although approved separately by the
Commission and, in many cases prior to the EmPower Maryland Energy Efficiency and
Conservation (“EE&C”) plans, are a critical component in meeting the EmPower
Maryland goals and as such are considered part of the EmPower Maryland umbrella
package.
1. DLC Programs
In 2008, the Commission approved the DLC programs of BGE, DPL, Pepco, and
SMECO.
48
These utilities filed revised DLC programs as part of the planning process for
the 2012-2014 program cycle. Pepco and DPL proposed to expand their respective DLC
programs to include Small Commercial as well as Residential, while BGE and SMECO
proposed other enhancements to their programs. However, Potomac Edison did not
propose a DLC program due to the non-economical projections associated with their
DLC program offerings; this decision was consistent with Potomac Edison's 2009-2011
planning proposals.
Each DLC program includes these common components: (1) all DLC programs
are voluntary; (2) upon receiving a customer request, the utility installs either a
programmable thermostat or a direct load control switch for a central air conditioning
system or an electric heat pump on a customer’s premise; (3) the utilities provide one-
time installation incentive and bill credits to the participants in the summer peak months;
and (4) with the exception of SMECO, customers can choose one of three cycling
choices, 50, 75, or 100 percent.
49
SMECO uses an initial 2 degree offset followed by 30
percent cycling for the thermostats, and a 50 percent cycling option followed by 30
48
The Commission approved BGE’s PeakRewards Program on November 30, 2007; Pepco and
DPL’s Energy Wise Programs on April 18, 2008; and SMECO’s CoolSentry Program on April 15,
2008. The utilities’ filings were documented in Case Number 9111. Potomac Edison/Allegheny
Power also filed its direct load control program, but it was not found to be cost-effective at the
time.
49
The cycling choices of 50%, 75%, and 100% represent the air conditioner compressor working
cycle reduced by 50%, 75%, and 100% under PJM- or utility- invoked emergency events during
summer peak season.
28
percent cycling for the switches during specified time periods. Utilities will invoke the
cycling process when PJM calls for an emergency event or a utility-determined event
during summer peak season.
The DLC incentives vary among utilities. The one-time installation incentive is
credited to the customer’s bill after installation is complete and an annual bill credit is
awarded for each participation year. Table V.B.1 summarizes the utilities’ incentives to
the program participants.
Table V.B.1 Utilities’ Incentives to DLC Program Participants
50% Cycling 75% Cycling 100% Cycling
Utility
Installation
Incentive
Annual
Bill
Credit
Installation
Incentive
Annual Bill
Credit
Installation
Incentive
Annual
Bill
Credit
Bill
Credit
Month
BGE $50 $50 $75 $75 $100 $100 Jun.
Sept.
DPL $40 $40 $60 $60 $80 $80 Jun.–
Oct.
Pepco $40 $40 $60 $60 $80 $80 Jun.–
Oct.
Installation incentive Annual Bill Credit
Thermostat Digital Switch Thermostat Digital Switch
Bill
Credit
Month
SMECO *** None $50 $50 Jun.–
Oct.
*** A participant in SMECO’s CoolSentry program can keep the installed thermostat for free after 12 months of
the installation; otherwise, the thermostat will be removed if the participant terminates the participation less than
12 months.
Source: Utilities’ EmPower Maryland Energy Efficiency Program Websites.
29
Table V.B.2 summarizes the progress in installing these devices for each utility
DLC program as of December 31, 2010--since each program’s inception. Installed
devices (programmable thermostats and digital switches) number 403,024 units.
Table V.B.2 Utilities’ Direct Load Program Installations;
Program-to-Date as of December 31, 2010
Utility
Installed
During 2010
Installed
PTD as of
12/31/2010
BGE 158,838 326,310
DPL 11,554 13,807
Pepco 36,057 39,987
SMECO 9,599 22,920
Total 216,048 403,024
Source: For BGE, PE and SMECO, Utilities 2010 Quarter 4 Report of EmPower
Maryland Program. For DPL and Pepco, Utilities refiling of 2010 made on August 26, 2011.
The DLC program resulted in 803 MW being bid for Delivery Year (“DY”) 2013-
2014 in the May 2010 PJM RPM auction, a 16 percent decrease from the 2009 bid of 952
MW for DY 2012-2013. To date, these programs have accounted for 3,050 MW of the
total capacity bid into PJM’s capacity market. Table V.B.3 summarizes the capacity bid
into PJM’s capacity market from the DLC program by utility and delivery year.
Table V.B.3: Direct Load Control Program Bids into PJM BRA (MW)
Utility DY 2013-
2014
DY 2012-
2013
DY
2011-
2012
DY 2010-
2011
DY
2009-
2010
Total
BGE
*
615 740 512.6 415.4 217.0 2,500
DPL 32.1 38.8 24.7 N/A** N/A 95
Pepco 124.1 148.7 99.2 N/A N/A 372
SMECO 31.9 25.0 25.0 N/A N/A 82
Total 803 952.5 661.5 415.4 217 3049.5
Source: Various data requests in Case Nos. 9111, 9154, 9155, 9156, and 9157.
Notes: *BGE’s bid includes both its current DLC and its legacy demand response program.
**N/A means data are not available because there was no program launched for these utilities.
a. Update on the DLC four programs
i. BGE
BGE launched its DLC program, PeakRewards, in June 2008. Popular to date,
PeakRewards installed a total of 158,838 air conditioning cycling devices from January 1,
2010 through December 2010. Approximately 30,000 more devices have been installed
through the third quarter of 2011. As of the end of the third quarter of 2011, a total of
30
356,000 devices (thermostats or switches) have been installed. BGE also has its legacy
demand response programs, which include air conditioner and water heater switches
installed in the customer premises, and is in the process of transferring these customers to
the PeakRewards program, if the customer decides to continue to participate. BGE plans
to phase out the legacy programs in 2011. Therefore, BGE’s bid currently includes both
the PeakRewards and legacy demand response programs.
Since the inception of PeakRewards, BGE has bid into PJM’s BRA for six
consecutive delivery years (see Table V.B.3). The total bid is approximately 2,500 MW,
although this total does not reflect the 2014-2015 bid year.
50
ii. Pepco
Pepco launched its Energy Wise program (similar in program design to
PeakRewards) in January 2009.
51
Pepco had installed 39,987 devices as of December
2010. The program made significant progress in 2010, with 36,057 devices installed in
the year 2010 alone. A further 30,790 devices were installed through the third quarter of
2011. The Company has installed 70,777 devices since the program inception.
Pepco has bid into the last four of PJM’s RPM BRAs, with a total bid of 372 MW
for all but the 2014-2015 bid year.
52
The Company bid 124 MW for DY 2013/2014 and
149 MW for DY 2012/2013 into PJM’s BRA.
iii. DPL
Concurrently with Pepco, DPL launched its Energy Wise program in January
2009. The Company had installed 13,807 devices by the end of December 2010.
Through the third quarter of 2011 the Company had installed an additional 7,115 devices.
Since the inception of the program DPL has installed 20,922 devices.
DPL has bid into the last four of PJM’s RPM BRA, with a total bid of 96 MW,
excluding the 2014-2015 bid year.
53
The Company bid 32.1 MW for DY 2013/2014,
38.8 MW for DY 2012/2013, and 24.7 MW for DY 2011/2012 into the PJM BRA.
iv. SMECO
SMECO launched its CoolSentry Program in November 2008. A customer may
elect to have installed either a thermostat or a digital switch on his/her air conditioner or
electric heat pump. SMECO offers a $50 annual bill credit to each participant, but if a
participant chooses to install a thermostat, the participant can also keep the thermostat for
free after 12 months of participation. No installation incentive is offered to a participant
50
This bid year is not included as bids have not been made public at this time.
51
Pepco and DPL entered into a contract with Comverge on January 20, 2009, and started the testing
phase with their own employee volunteers.
52
This bid year is not included as it has not been made public at this time.
53
This bid year is not included as it has not been made public at this time.
31
to choose a digital switch. SMECO has installed 30,811 devices since program inception,
including 11,347 through the third quarter of 2011.
SMECO bid a total of 81.9 MW into PJM’s RPM BRA over the last four years,
31.9 MW for DY 2013/2014, and 25 MW for each DY 2011/2012 and 2012/2013.
54
v. Suspension of White Rodgers Programmable Thermostat
Installation
In 2010, the Commission suspended the installation of the thermostats used by
Pepco, DPL, and SMECO due to a potential safety hazard with the devices. The
Commission issued Order No. 83588 on September 23, 2010 directing Pepco, DPL, and
SMECO
55
(“the Companies”) to cease the installation of the affected thermostats
immediately and appear before the Commission at a hearing on September 24, 2010. On
September 24, 2010, the Commission issued Order No. 83592 reinforcing the decision to
cease thermostat installation in Order No. 83588 and directed the Companies to notify the
Commission when the Consumer Protection Safety Commission (“CPSC”) issued a
decision on corrective actions for the safety issue with the thermostats.
On January 14, 2011 the Companies issued a press release providing further detail
about the Canadian CPSC ruling and a subsequent recall by White-Rodgers. On February
1, 2011 the Companies filed a motion to lift the stay, imposed by the Maryland PSC,
citing the steps outlined by White-Rodgers to rectify the problem as well as future
changes to the program to prevent this type of issue from remaining problematic. On
March 7, 2011 the Commission issued Order No. 83899, which lifted the stay on the
installation of White-Rodgers thermostats in the manner proposed by the Companies in
the February 1 filing.
b. July 22, 2011 DLC Activation Event
July 22, 2011 was the first time PJM had declared an emergency event since the
Utilities’ current DLC programs were approved by the Commission in 2008. BGE was
the only utility in Maryland to have an emergency event declared by PJM. This was
primarily due to the overheating of a transformer at one of BGE’s substations (forcing
BGE to take that transformer out of service) and extremely high temperatures. Because
of this emergency event, BGE initiated its DLC program at all three cycling levels for the
first time (50%, 75%, and 100%), so this was the first time that customers who signed up
for the 75% and 100% cycling options had their thermostat or switch cycling at the 75%
or 100% level.
56
The combination of the extreme high temperatures, cycling participants
for the first time at their selected cycling level, and the length of the event (7.75 hours)
57
54
The 2014-2015 bid year is not included as it has not been made public at this time.
55
SMECO also was installing the same White Rodgers programmable thermostats in its CoolSentry
program.
56
For non-PJM Emergency events, BGE cycles all participants at a 50 percent level.
57
This total of 7.75 hours was the average time the DLC program was activated, and consisted of
two events. The first event was the PJM-declared emergency which lasted for 6 hours and 34
minutes. For the second event, the Company switched all participants to cycle at the 50 percent
32
led to very high levels of calls to both the BGE call center and the DLC call center, which
led to longer than average wait times and customer dissatisfaction.
Pepco, DPL, and SMECO activated their DLC programs for economic reasons
and did not experience any above-average duration times or number of calls at their call
centers. Pepco, DPL, and SMECO also reported no problems with overloads on their
communication systems.
The major problems of the day were due to shortcomings in participant education
and communication. The following is a list of education and communication problems
and the proposed corrections to avoid these issues in future activations events:
1. Participants forgot what level of cycling they were signed up for - BGE
(and all the Utilities) need to remind the participants of their cycling level
prior to the summer season, when these devices are most likely to be
activated. Additionally, BGE should describe situations when a participant
might want to lower their cycling level, such as medical conditions or homes
with elderly people and small children.
2. Participants were unaware of the PJM emergency event – BGE should
attempt to contact participants the evening prior to an event (PJM Emergency
or BGE initiated), similar to the commitment BGE has made for customer
contact for Smart Energy Pricing. That way a participant will be aware of the
event beyond the message on the thermostat and light on the switch.
3. Participants had never been cycled at more than 50% prior to July 22
BGE may want to consider cycling participants at their selected cycling level
during BGE declared events. Since BGE declared events generally do not last
longer than four hours, a 100% participant, for example, may have a better
idea of the interior temperature change to expect for a potential PJM declared
emergency event.
4. Long time spent on hold while contacting call center – BGE has
committed, in its report, to increase call center staff during a PJM declared
emergency.
5. Paging signals to DLC devices unable to transmit due to system
overloading – BGE has indicated that it is already working with its signal
vendor to configure the system to enable the prioritization of system-wide
device commands.
BGE has been working on improving the education and communication issues
identified during the July 22 DLC activation event in order to provide more transparency
and be more responsive to program participants during future PJM declared emergency
events.
level in order to scale down from the emergency event. The second event lasted for 1 hour and 11
minutes.
33
2. Peak Load Reduction Forecast
Table V.B.4 demonstrates the impact of demand side management programs on
the utilities’ peak load forecast. The table presents the 10-year growth rate for gross of
demand side management programs and the impact, or net of, those programs during the
period of 2011 through 2020. Overall, the peak load forecast for the utilities listed in
Table V.B.4 is estimated to result in an 18 percent increase in demand by 2020 without
DSM programs. However, net of DSM programs, the overall forecast is expected to result
in a 13 percent increase in demand over the 10-year period. Therefore, holding all other
factors constant, it is forecasted that the DSM programs will reduce the peak demand
growth rate 5 percent by 2020.
Table V.B.4: Peak Load Reduction Forecast (MW)
Gross of DSM Net of DSM (MW)
2011
(MW)
2020
(MW)
10 Year
Growth
Rate
2011
(MW)
2020
(MW)
10 Year
Growth
Rate
10 Year
Growth
Rate
Variance
BGE
7,374 8,789 19% 6,699 7,589
13% 6%
DPL
1,249 1,447 16% 1,118 1,255
12% 4%
PE
1,441 1,712 19% 1,412 1,680
19% 0%
Pepco
3,712 4,230 14% 3,322 3,591
8% 6%
SMECO
871 1,080 24% 838 1,031
23% 1%
Total
14,647 17,258 18% 13,389 15,146
13% 5%
Source: Table A-4(a) Peak Summer Demand Forecast Breakdown 2010 in Company data responses to the
Commission's 2011 data request for the Ten-Year Plan.
The major contributors to the peak load reduction are: (1) the current direct load
control program (BGE, DPL, Pepco, and SMECO); (2) legacy load reduction program
(BGE and SMECO); (3) BGE’s Smart Grid Initiative,
58
and (4) energy efficiency and
conservation programs (BGE, DPL, Pepco, and PE).
59
C. Energy Efficiency and Conservation Programs
On December 31, 2008, the Commission preliminarily approved the utilities’
EmPower Maryland EE&C portfolios, contingent upon varying Commission-prescribed
alterations to their programs, budgets, and projected savings. Although BGE’s programs
were approved in whole, the Commission directed the other utilities to file their revised
portfolios, along with information confirming their final estimated costs and budgets
through completed request for proposals or finalized contracts by March 31, 2009.
Comments by the interveners, as well as a response by the utility, were filed in each
proceeding. As with the original series of proceedings, the Commission conducted
58
Pepco did not include demand reductions from its Commission-approved AMI initiative.
59
The contribution information is obtained through Staff communication with the utilities. SMECO
does not include energy-efficient demand reduction as part of its forecast.
34
hearings for each utility’s proposal. The remaining four utilities’ - PE, DPL, Pepco and
SMECO - programs were approved in August 2009.
1. EmPower Maryland Policy
The Commission contracted an Independent Evaluator in April 2010 to conduct
quality control and due diligence of the Utilities’ EM&V programs and contracted
evaluator.
60
In an effort to build a credible and reliable EM&V infrastructure,
stakeholders and their various evaluators collectively established the Strategic Evaluation
Plan in September 2010 which provided guidance on a variety of issues, but also laid out
expectations for the Utilities and their evaluator. A baseline study, conducted by KEMA,
was completed in 2010 and released in 2011 for use by the utilities and evaluators. 2011
also saw the release of the first round of cost-effectiveness testing. This was a joint effort
by the Utilities, stakeholders, Itron, and Navigant Consulting to gather and analyze
savings reported under the EmPower Maryland programs and provide an evaluation of
the costs and benefits realized by each Utility. Overall, cost-effectiveness testing
returned positive results; however, some programs struggled due to their transformative
nature. It was determined that these programs may need additional time and attention in
order to achieve minimum cost-effectiveness standards.
The five EmPower Maryland Utilities, MEA, the Office of the Peoples Counsel
(“OPC”) and Staff (hereafter referred to as the “Planning Group”) began preparations for
the 2012-2014 EmPower Plan filings in the summer of 2010. On September 2, 2010
Staff filed the “Invitation to Stakeholders to Propose New or Revised Programs,
Measures or Products” on behalf of the Planning Group (“Invitation”). The Invitation
clarified that all cost-effective programs would be considered; however the Utilities
would determine what they include in these filings and the utilities have the right to
modify, adapt, incorporate and/or implement as they deem appropriate any ideas
presented on this process and during the stakeholder sessions. The Invitation included a
template intended examine all elements for the implementation of a proposed program or
product. Proposals were submitted on October 4, 2010 to Staff and MEA.
Over thirty proposals were submitted. The majority came from organizations or
firms that had little or no prior association with demand side stakeholder or work group
activities in Maryland. The Planning Group scored proposals largely on the
completeness of information provided. Eight organizations or firms were rejected prior
to the presentation of proposals in most cases because proposals lacked cost or savings
estimates.
Four Work Group meetings starting November 1, 2010, open to all stakeholders,
were noticed to Staff’s contact list and in a planning framework filed with the
Commission. The Planning Group met a number of times during the winter to discuss the
merits of the proposals and whether they were likely to be included in some form in the
draft Plans. Planning and workgroup meetings continued into 2011 with a culmination in
July 2011. As required under the statute each utility and any parties wishing to take part
60
The Utilities also have their own EM&V evaluator, as does the OPC and the MEA.
35
in the hearing process were required to file proposals by September 1, 2011. The
subsequent EmPower Maryland hearing process lasted eight days and included
presentations from the five Utilities, DHCD, Technical Staff, OPC, and MEA, as well as
trade organizations and contractors.
2. EmPower Maryland EE&C Programs
On December 31, 2008, by Order Nos. 82383, 82384, 82385, 82386, and 82387,
61
the Commission partially approved the Energy Efficiency, Conservation, and Demand
Response Programs pursuant to the EmPower Maryland Energy Efficiency Act of 2008.
With the exception of BGE’s portfolio, which was approved as a whole, DPL, Pepco,
Potomac Edison and SMECO were all requested to make alterations to some program
designs as well as revise the total estimated cost and savings with the finalized RFPs.
The Commission approved these revised plans in Order Nos. 82825 on August 6, 2009,
and 82835, 82836 and 82837 on August 13, 2009. The approved programs are designed
for residential customers,
62
as well as small and large commercial businesses.
63
Generally, most programs are designed to provide a rebate to consumers to encourage the
purchase of energy-efficient products, equipment, or services.
64
a. BGE
As of the end of the third quarter of 2011 BGE has spent 89 percent of its
forecasted 2009-2011 EE&C budget ($149,207,339). The Commission approved BGE’s
2011 Residential EE&C EmPower Maryland Surcharge at $0.000730 per kWh effective
January, 2011. The Company’s EmPower Maryland EE&C Programs have achieved 26
percent of its 2011 energy savings goal (2,052,948 MWh) and 5 percent of the 2011 peak
reduction goal (513 MW) through the third quarter of 2011.
65
b. Pepco
As of the end of the third quarter of 2011 Pepco has spent 41 percent of the 2009-
2011 EE&C budget ($49.8 million). Pepco continued to use the 2010 combined
residential surcharge ($0.00187) as no other surcharge was filed for 2011. The Company
has filed a surcharge for 2012 that will encompass the 2010 and 2011 true ups. The
Company has achieved 18 percent of its EE&C 2011 energy savings goal (685,378
MWh) and 8 percent of its demand reduction goal (230 MW).
61
The Commission subsequently approved certain program revisions for BGE in Order No. 82674.
62
Residential programs include Lighting and Appliances; Home Performance with Energy Star,
Quick Home Energy Check-up, and Comprehensive Home Audits; Energy Star for New Homes;
Limited Income Energy Efficiency Program; Heating, Ventilation, and Air Conditioning
(“HVAC”) and Domestic Hot Water Heaters. Program availability varies slightly across service
territories.
63
Non-residential programs include the C&I Prescriptive; C&I Custom; Commissioning; C&I
HVAC. Program availability varies slightly across service territories.
64
All data in the following sections will be current as of the third quarter of 2011 unless otherwise
noted. All data is reported at the Wholesale Level.
65
These percentages do not reflect savings from Demand Response programs as these are not part of
the EE&C portfolio but are part of the DLC programs.
36
c. DPL
DPL has spent 29 percent of its three-year forecasted budget ($19.6 million).
Pepco continued to use its 2010 combined residential surcharge ($0.001822) during 2011.
The Company has filed a surcharge for 2012 that will combined the 2010 and 2011 true
ups. Energy savings from EE&C programs through the third quarter will amount to 12
percent of the 2011 goal (205,846 MWh) and will account for 4 percent of the 2011
demand reduction goal (73 MW).
d. SMECO
Program spending for Residential and C&I EE&C programs through the third
quarter accounts for 63 percent of its 2009-2011 forecast ($14.3 million). The
Commission approved a residential EE&C surcharge of $0.00145 effective February,
2011. Program-to-date results through the third quarter of 2011 account for 34 percent of
the 2011 goal (94,229 MWh) and 40 percent of the 2011 demand reduction goal (29
MW).
e. PE
Program spending, through the third quarter of 2011, for EE&C programs
accounts for 9 percent of the 2009-2011 forecasted budget. The Commission approved a
residential EE&C surcharge of $0.00010 effective for June, 2011. This was a follow up
surcharge in response to the approval of the merger with First Energy. Program-to-date
results through the third quarter of 2011 account for 30 percent of the 2011 energy
savings goal (122,664 MWh) and 15 percent of the 2011 demand reduction goal (49.4
MW).
D. Advanced Metering Infrastructure / Smart Grid
1. Background
“Smart grid” technology is generally defined as a two-way communication system
and associated equipment and software, including equipment installed on an electric
customer’s premise that uses the electric company’s distribution network to provide real-
time monitoring, diagnostic, and control information and services that can improve the
efficiency and reliability of the distribution and use of electricity. Advanced Metering
Infrastructure (“AMI”) is a component of smart grid and refers to the installation of
meters on a customer’s premises capable of being addressed by the utility. Soon the
technology will enable customers to see and respond to market-based pricing as well as
be more self-aware of their energy usage, assisting in grid reliability and reducing
environmental impacts. Reliability and power quality benefits can also accrue when AMI
is employed to reduce blackout probabilities and forced outage rates while restoring
power in shorter time periods. On September 28, 2007, the Commission issued Order
No. 81637, which established the following minimum technical standards for AMI. BGE,
37
Pepco and DPL subsequently filed, for Commission approval, plans seeking to establish
an AMI program.
2. Approved AMI Initiatives
a. BGE
On August 13, 2010, the Commission issued Order No. 83531 in Case No.
9208,
66
which authorized BGE to deploy its AMI Initiative. Some highlights of the
approved AMI Initiative are:
Install over 2 million electric meters and gas modules;
Deployment cost of $440 million in capital cost and $57 million in operational
costs;
Total cost over the life of the program of $641 million capital cost and $194
million in operational costs offset by $136 million
67
in federal grants from the
Department of Energy;
Total benefits over the life of the project are estimated at $2.7 billion; and
80 percent of all meters to be installed by 2014.
Order No. 83531 directs BGE to do the following:
1) Establish a regulatory asset for the AMI Initiative. Once the Company has
delivered a cost-effective AMI system, it may seek cost recovery in its base
rates, including incremental costs and net depreciation and amortization costs
relating to the meters;
2) Allow cost recovery for the replacement of legacy meters by smart meters to
be considered in a future depreciation proceeding;
3) Submit for Commission approval, an updated customer education plan;
4) Develop “a comprehensive set of installation, performance, benefits and
budgetary metrics that will allow the Commission to assess the progress and
performance of the Initiative;
68
and
5) Notify the Commission of whether it will proceed with the initiative. BGE
confirmed its intent to proceed with the initiative in a letter sent to the
Commission on August 16, 2010.
Since authorization, BGE, in conjunction with PHI, Staff and other stakeholders,
established a Smart Grid Collaborative Work Group per Commission direction. The
Work Group offers a venue to discuss issues such as the consumer education plan and the
66
In the Matter of Baltimore Gas and Electric Company for Authorization to Deploy a Smart Grid
Initiative and to Establish a Surcharge Mechanism for the Recovery of Cost.
67
BGE was awarded $200 million in American Recovery and Reinvestment Act funding. Of this,
$136 million funds AMI deployment and $64 million for Peak Rewards and Customer Care &
Billing.
68
Order No. 83531at 48.
38
comprehensive set of performance metrics. The Company provided an update on
deployment efforts at a status conference on December 15, 2010. The Company proposed
that deployment take place from 2011-2014, with installation of smart meters beginning
in October 2011.
b. Pepco
On September 2, 2010, the Commission issued Order No. 83571 in Case No.
9207,
69
authorizing Pepco to deploy its AMI Initiative contingent upon the Company
submitting an amended business case and a comprehensive consumer education plan.
Some highlights of the approved Smart Grid Initiative are:
Install 570,000 electric meters;
Deployment cost of $69.4 million in capital cost;
Total cost over the life of the program of $127 million in capital cost and
$1.038 million in annual incremental operational costs;
Total benefits over the life of the project are estimated at $311.6 million; and
Pepco awarded $104.8 million in Smart Grid Investment Grant funds.
Order No. 83571 directs and allows Pepco to do the following:
1) Submit an amended business case and associated benefits-to-costs analysis
that demonstrates the cost-effectiveness of the AMI proposal;
2) Submit a plan detailing how it intends to fund its proposed Critical Peak
Rebate dynamic pricing structure, including the manner in which it intends to
monetize peak demand and energy use reductions attributable to AMI;
3) Develop “a detailed and comprehensive customer education and
communications plan,” along with a corresponding customer education and
communications budget;
70
4) Develop a comprehensive set of metrics of the Company’s AMI proposal,
including: (a) installation and performance of the technology; (b) incremental
costs incurred; (c) incremental benefits realized; (d) effectiveness of customer
education and communications efforts to include customer satisfaction and
participation levels; and (e) customer privacy and cyber security;
5) Establish a regulatory asset for the incremental costs associated with the AMI
deployment, including start-up costs, which the Company may seek to
recover in a base rate proceeding;
6) Seek cost recovery for the replacement of legacy meters by smart meters to
be considered in a future depreciation proceeding.
The Order also prohibits the Company from implementing a Critical Peak
Pricing rate structure. A dynamic rate schedule will go in effect once AMI has
been installed. Further, the Commission ordered Commission Staff as well as
Pepco to convene an AMI working group, which is to include representatives
69
In the Matter of Potomac Electric Power Company and Delmarva Power and Light Company
Request for the Deployment of Advanced Meter Infrastructure.
70
Id. at 4.
39
from Pepco, BGE, and the Office of People’s Counsel to submit a proposal for
“uniformity of critical peak period seasons, times, frequency, and duration,
and other aspects of dynamic pricing implementation.”
71
Pepco filed with the Commission its Customer Education Plan on October 15,
2010 and an amended business case on December 13, 2010, in accordance with Order
No. 83571. Pepco provided cost-benefit analyses under three different post-deployment
scenarios, all of which yielded cost-effectiveness scenarios greater than 1.0. The filing
also included depreciation timetables for advanced metering infrastructure and estimated
costs for regulatory assets. The consumer education plan and amended business case’s
final budget—as well as the performance metrics required to be reported— will be
subject to the review of the Smart Grid Collaborative Work Group and to the approval of
the Commission. In its amended business case filed December 13, 2010, Pepco proposed
a time period of 15 months for AMI installation, and the starting month is projected to be
June 2011, with completion in August 2012.
c. DPL
In Order No. 83571, the Commission deferred the decision on DPL’s request to
proceed with deployment of its AMI Initiative. DPL’s request to establish a regulatory
asset for the incremental costs associated with its proposed AMI deployment was
deferred as well.
Order No. 83571:
1) Deferred DPL’s request to proceed with deployment of its AMI Initiative, and
directed the Company to submit an amended business case and associated
cost-benefit analysis demonstrating the cost-effectiveness of the proposal;
2) Required the Company to submit a plan detailing how it intends to fund its
proposed Critical Peak Rebate dynamic pricing structure, including the
manner in which it intends to monetize peak demand and energy use
reductions attributable to AMI;
3) Denied DPL’s request to establish a regulatory asset for the incremental costs
associated with AMI deployment, pending submission of a revised business
case of AMI system deployment that is agreeable to the Commission; and
4) Prohibited the Company from implementing a Critical Peak Pricing rate
structure.
DPL filed a revised business case for its AMI Initiative on December 14, 2010,
which includes forecast scenarios for all of the adjustments specified by Order No.
83571. The Commission reheard the case on August 17, 2011. At this time no order has
been issued by the Commission on this issue but one is expected in 2012.
71
Id. at 51.
40
3. AMI Pilots
a. SMECO
SMECO proposed a two-phase AMI Pilot Program to test the operational benefits
of AMI deployment, such as savings from eliminating meter readings and improved
outage restoration. Phase I of the pilot, approved by the Commission in December of
2009, includes the installation of 1,000 meters in one section of the service territory and
went into effect in 2010. The Cooperative will attempt to quantify the level of operational
benefits attainable through deployment of AMI, and the Cooperative will report the
results of Phase I to the Commission prior to implementing Phase II, which will be a
10,000 meter deployment across the entire service territory. At the time of this report,
SMECO had not yet submitted the report on Phase I of the project. SMECO notified
Commission Staff that Phase I will commence in mid-March 2011.
4. AMI Workgroups
a. BGE and Pepco
Following the Commission’s direction that workgroups be established to bring
stakeholders together with the utilities for the development of metrics, educational
programs, and security standards a number of initiatives were undertaken in 2010 and
2011. In a letter dated February 18, 2011 Pepco received approval from the Commission
to implement its “Proposed Phase 1” customer education plan. In a letter dated July 18,
2011 BGE received approval from the Commission to implement its “Smart Grid
Customer Education and Communication Plan.” In a letter dated August 18, 2011 the
Commission granted approval for the Phase 1 Metrics for both BGE and Pepco. The
workgroup continues to develop plans for cyber security, Phase II metrics, and Phase II
customer education and communication. It is expected that consensus filings and specific
plans will be filed for approval on each of these issues in 2012.
41
E. Mid-Atlantic Distributed Resources Initiative
The Mid-Atlantic Distributed Resources Initiative (“MADRI”) was established in
2004, and currently consists of seven PJM State Commissions, DOE and PJM.
72
Its goal
is “to develop regional policies and market-enabling activities to support distributed
generation and demand response in the Mid-Atlantic region.” Facilitation support is
provided by the Regulatory Assistance Project funded by DOE. There has been much
participation by a large number of stakeholders, including utilities, Commission Staff,
FERC, service providers, and consumers. During 2011, MADRI focused on time of use,
peak period and related pricing approaches that may be used following the
implementation of Smart Grid infrastructure.
VI. ENERGY, THE ENVIRONMENT, AND RENEWABLES
A. The Regional Greenhouse Gas Initiative
The Regional Greenhouse Gas Initiative (“RGGI”) is the first mandatory cap-and-
trade program in the United States for carbon dioxide (“CO
2
”). Under RGGI, ten
Northeastern and Mid-Atlantic states have jointly designed a cap-and-trade program that
limits permitted carbon dioxide emissions from fossil fuel power plants, and then
incrementally lowers that level or “cap” 10% by 2018. The first compliance period
spanned January 1, 2009 – December 31, 2011. Nine member states will continue
participation in the RGGI program for the second compliance period of January 1, 2012 –
December 31, 2014; New Jersey has formally withdrawn from the RGGI program,
effective January 1, 2012.
RGGI, Inc. is a nonprofit Delaware corporation formed to provide technical and
scientific advisory services to participating states in the development and implementation
of the carbon dioxide budget trading programs. The RGGI, Inc. offices are located in
New York City in space co-located with the New York Public Service Commission. The
RGGI Board of Directors is composed of two representatives from each member state,
with equal representation from the states’ environmental and energy regulatory agencies.
Agency Heads (two from each state), who also serve as RGGI Board members, constitute
a steering committee that provides direction to the Staff Working Group and allows
coordination of in-process projects for Board review.
Under RGGI, the participating states have agreed to use an auction of allowances
as the means to distribute CO
2
emissions allowances to electric power plants regulated
under coordinated state CO
2
cap-and-trade programs. All fossil fuel electric power plants
25 megawatts or greater must obtain allowances and adhere to RGGI guidelines. The
effective date for RGGI was January 1, 2009. From 2009 through 2014, the cap
stabilizes emissions at 2009 levels of approximately 188 million tons annually. These
initial base annual emissions budgets for the 2009-2014 periods are summarized in Table
VI.A.1.
72
The Commissions are Delaware, D.C., Illinois, Maryland, New Jersey, Ohio and Pennsylvania.
42
Table VI.A.1: Annual State CO
2
Allowance Budgets (2009 – 2014)
State
Carbon Dioxide Allowances
(in Short Tons)
Connecticut 10,695,036
Delaware 7,559,787
Maine 5,948,902
Maryland 37,503,983
Massachusetts 26,660,204
New Hampshire 8,620,460
New York 64,310,805
New Jersey 22,892,730
Rhode Island 2,659,239
Vermont 1,225,830
Total* 188,076,976
Source: Memorandum of Understanding, REGIONAL GREENHOUSE GAS INITIATIVE
(Dec. 20, 2005), available at http://www.rggi.org/design/history/mou.
*Note
: Following the withdrawal of New Jersey (effective Jan. 1, 2012), the total
annual regional cap will be adjusted to 165,184,246 allowances.
Beginning in 2015, the cap is reduced by 2.5% each year until 2018. This phased
approach, with initially modest emissions reductions, is intended to provide market
signals and regulatory certainty so that electricity generators may begin planning for, and
investing in, lower-carbon alternatives throughout the region while avoiding volatile
wholesale electricity price impacts and attendant retail electricity rate impacts. The
RGGI Memorandum of Understanding apportions carbon dioxide allowances
73
among
signatory states through a process that was based on historical emissions and negotiation
among the signatory states. Together, the emissions budgets of each signatory state
comprise the regional emissions budget, or RGGI “cap.”
In 2011, RGGI held four successful auctions for carbon dioxide allowances. As a
result of the fourteen auctions comprising the first compliance period, Maryland’s
Strategic Energy Investment Fund has received a cumulative total of $180,315,817
through December 2011; the Fund received almost $33 million in 2011 alone.
74
During 2011, auction clearing prices did not recover from the downward trend
that started in mid-2009. All allowances sold in 2011 auctions were purchased at the
auction floor price.
75
In 2011, the auction floor price was $1.89; the floor price will
increase to $1.93 in 2012 auctions.
73
An allowance is a limited permission to emit one ton of carbon dioxide.
74
See MD Proceeds by Auction, REGIONAL GREENHOUSE GAS INITIATIVE, available at
http://www.rggi.org/docs/MD_Proceeds_by_Auction.pdf (last updated Dec. 12, 2011).
75
See Auction Results, REGIONAL GREENHOUSE GAS INITIATIVE, available at
http://www.rggi.org/market/co2_auctions/results (last updated Dec. 12, 2011).
43
B. The Renewable Energy Portfolio Standard Program
The Renewable Energy Portfolio Standard (“RPS”) Program imposes an annual
requirement upon Maryland load serving entities (“LSEs”) to derive a percentage of
electricity sales from the renewable sources specified in the corresponding RPS Statute.
76
LSEs, which include both electricity suppliers and the utilities that provide Standard
Offer Service (“SOS”),
77
file compliance reports with the Commission verifying that the
renewable requirement for each entity is satisfied. The RPS obligation applies to anyone
who has completed an electricity sale at retail to customers in the State of Maryland.
Additional information regarding the status of the Maryland RPS is available in the
annual Renewable Energy Portfolio Standard Report submitted to the General
Assembly.
78
On an annual basis each supplier must present renewable energy credits (“RECs”)
equal to the percentage specified by the RPS Statute,
79
or pay the alternative compliance
fees equal to any shortfalls.
80
A REC is equal to one MWh of electricity generated using
specified renewable sources.
81
As such, a REC is a tradable commodity equal to one
MWh of electricity generated or obtained from a renewable energy generation resource.
Generators and suppliers are allowed to trade RECs using a system known as the
Generation Attributes Tracking System (“GATS”). GATS is a system designed and
operated by PJM Environmental Information Services, Inc. (“PJM-EIS”) that tracks the
ownership and trading of the generation attributes.
82
A REC has a three-year life during
which it may be transferred, sold, or redeemed.
83
Suppliers that do not meet the annual RPS requirement are required to pay
Alternative Compliance Payments (“ACPs”) or fees equal to any shortfalls.
84
Compliance fees are deposited into the Maryland Strategic Energy Investment Fund
(“SEIF” or “Energy Fund”) as dedicated funds to provide for loans and grants that can
76
MD. CODE ANN., PUB. UTIL. § 7-701(j) (2011).
77
Standard Offer Service (“SOS”) is electricity supply purchased from an electric company by the
company’s retail customers that cannot or choose not to transact with a competitive supplier
operating in the retail market. See M
D. CODE ANN., PUB. UTIL. §§ 7-501(n) and 7-510(c) (2011).
78
See Commission Reports, MARYLAND PUBLIC SERVICE COMMISSION, available at
http://webapp.psc.state.md.us/Intranet/psc/Reports_new.cfm (last visited Dec. 2011), for a listing
of available RPS Reports submitted in previous years.
79
MD. CODE ANN., PUB. UTIL. § 7-703(b) (2011).
80
Using the Tier 2 RPS requirement as an example, assume a hypothetical LSE operating in the
State had 100,000 MWh in retail electricity sales for 2008. In 2008, the Tier 2 requirement was
2.5%. Thus, the LSE would have to verify the purchase of 2,500 Tier 2 RECs in satisfaction of
the Tier 2 RPS obligation, or pay compliance fees for deficits. Similar requirements apply to Tier
1 and Tier 1 solar, the additional RPS tiers provided for in Maryland’s RPS Statute.
81
MD. CODE ANN., PUB. UTIL. § 7-701(i) (2011).
82
An attribute is “a characteristic of a generator, such as location, vintage, emissions output, fuel,
state RPS program eligibility, etc.” PJM Environmental Information Services, Generation
Attribute Tracking System Operating Rules, at 3 (September 30, 2010).
83
MD. CODE ANN., PUB. UTIL. § 7-709(d) (2011).
84
MD. CODE ANN., PUB. UTIL. § 7-705(b) (2011).
44
indirectly spur the creation of new renewable energy sources in the State.
85
The
Commission is responsible for creating and administering the RPS Program;
86
responsibility for developing renewable energy resources through loans and grants has
been vested with the Maryland Energy Administration.
Eligible fuel sources for Tier 1 RECs and Tier 2 RECs are listed in Table VI.B.1.
In order to verify that each LSE has met its RPS obligation, the Commission requires that
all licensed electricity suppliers and electric companies file a Supplier Annual Report no
later than April 1
st
of each year.
87
The April 1
st
deadline provides time for LSEs to
calculate electricity sales based on settlement data for the compliance year that ends on
December 31
st
. The April 1
st
deadline also allows LSEs time to purchase any RECs
needed to fulfill their respective RPS obligations.
Table VI.B.1: Eligible Tier 1 and Tier 2 Renewable Sources,
for Compliance Year 2010
Tier 1 Renewable Sources Tier 2 Renewable Sources
Solar (set-aside with separate standard)
Wind
Qualifying Biomass
Methane (landfill or wastewater treatment
plant)
Geothermal
Ocean Energy (waves, tides, currents, and
thermal differences)
Fuel Cells (which produce electricity
from biomass or methane under Tier 1)
Hydroelectric Power Plant (less than 30
MW capacity)
Poultry Litter-to-Energy
Hydroelectric Power (other
than pump storage
generation) at or above 30
MW
Waste-to-Energy
88
Source: MD. CODE ANN., PUB. UTIL. § 7-705(b) (2011).
Note: Tier 1 RECs may be used to satisfy Tier 2 obligations; Tier 2 RECs, however, may not be used to
satisfy Tier 1 obligations.
85
Chapters 127 and 128 of the Laws of 2008 repealed the Maryland Renewable Energy Fund and
redirected compliance fees paid into that fund into the Maryland Strategic Energy Investment
Fund. 2008 Md. Laws 846.
86
MD. CODE ANN., PUB. UTIL. § 7-703(a)(1)(i) (2011).
87
These reports have been filed pursuant to MD. CODE ANN., PUB. UTIL. § 7-705(a) (2011).
88
Effective October 1, 2011, new legislation reclassified “waste-to-energy” as a Tier 1 renewable
source. 2011 Md. Laws 3045. However, “waste-to-energy” was classified as a Tier 2 renewable
source during the 2010 compliance year as reported in this section.
45
LSEs are required to purchase specified minimum percentages of their electricity
resources via RECs from Maryland-certified Tier 1 and Tier 2 renewable resources. As
presented in Table VI.B.2, Tier 1 and the Tier 1 solar set-aside
89
requirements gradually
increase until they peak in 2022 at 18% and 2%, respectively, and are subsequently
maintained at those levels. Maryland’s Tier 2 requirement remains constant at 2.5%
through 2018, after which it sunsets.
Table VI.B.2: Annual RPS Percentage Requirements by Tier
Compliance
Year Tier 1
Tier 1
Solar Tier 2
2010 3.00% 0.025% 2.50%
2011 4.95% 0.050% 2.50%
2012 6.40% 0.100% 2.50%
2013 8.00% 0.200% 2.50%
2014 10.00% 0.300% 2.50%
2015 10.10% 0.400% 2.50%
2016 12.20% 0.500% 2.50%
2017 12.55% 0.550% 2.50%
2018 14.90% 0.900% 2.50%
2019 16.20% 1.200%
2020 16.50% 1.500%
2021 16.85% 1.850%
2022 18.00% 2.000%
Source: MD. CODE ANN., PUB. UTIL. § 7-703(b) (2011).
Note:
Schedule reflects increased percentage requirements effective January 1, 2011 for the Tier 1 Solar
category.
Electricity suppliers not meeting the RPS requirement for any or all tiers of
resources pay an ACP on each MW of shortfall.
90
Table VI.B.3 presents the ACP
schedule separated by tiers for each year of the RPS from 2010 to 2023 and beyond.
Compliance fees, as previously mentioned, are deposited into the SEIF and dedicated to
supporting the development of new Tier 1 renewable resources in Maryland.
89
"Tier 1 solar set-aside" refers to the set-aside (or carve-out) of Tier 1 for energy derived from
qualified solar energy facilities. The Tier 1 solar set-aside requirement applies to retail electricity
sales in the State by LSEs and is a sub-set of the Tier 1 standard.
90
MD. CODE ANN., PUB. UTIL. § 7-705(b) (2011).
46
Table VI.B.3: RPS Alternative Compliance Fee Schedule ($/MWh)
Compliance
Year
Tier 1
(non-solar)
Tier 1
Solar
Tier 2
IPL*
Tier 1
2010 $20 $400 $15 $5
2011 $40 $400 $15 $4
2012 $40 $400 $15 $4
2013 $40 $400 $15 $3
2014 $40 $400 $15 $3
2015 $40 $350 $15 $2.50
2016 $40 $350 $15 $2.50
2017 $40 $200 $15 $2
2018 $40 $200 $15 $2
2019 $40 $150 $2
2020 $40 $150 $2
2021 $40 $100 $2
2022 $40 $100 $2
2023 + $40 $50 $2
Source: MD. CODE ANN., PUB. UTIL. § 7-705(b) (2011).
*Note: A supplier sale from Industrial Process Load (“IPL”) is required to meet the entire Tier 1
obligation for electricity sales, including solar. However, the ACP for an IPL Tier 1 non-solar
shortfall and a Tier 1 solar shortfall is the same. For IPL, there is no compliance fee for Tier 2
shortfalls.
Calendar year 2010 marked the fifth compliance year for the Maryland RPS, and
the third year for LSEs to comply with the solar Tier 1 set-aside. GATS and the RPS
compliance reports submitted to the Commission by LSEs provide information regarding
the RECs retired and the underlying renewable energy facilities (e.g., type and location)
utilized by electricity suppliers to comport with Maryland RPS obligations.
91
RPS
compliance reports were filed by 58 electricity suppliers, including 33 competitive
suppliers, 14 brokers or wholesale electricity suppliers with zero retail electricity sales,
and 11 electric companies, of which four are investor-owned utilities. In compliance year
2010, there were approximately 65.6 million MWh of total retail electricity sales in
Maryland; 64.1 million MWh of electricity sales were subject to RPS compliance, and
1.5 million MWh were exempt.
92
91
According to § 7-709, a REC can be diminished or extinguished before the expiration of three
years by: the electricity supplier that received the credit; a nonaffiliated entity of the electricity
supplier that purchased or received the transferred credit; or demonstrated noncompliance by the
generating facility with the requirements of § 7-704(f). In the PJM region, the regional term of art
is “retirement,” and describes the process of removing a REC from circulation by the REC owner,
i.e., the owner “diminishes or extinguishes the REC.” PJM Environmental Information Services,
Generation Attribute Tracking System (GATS) Operating Rules, at 54 – 56 (September 30, 2010).
92
According to Article § 7-703(a)(2), exceptions for the RPS requirement may include: industrial
process load which exceeds 300,000,000 kWh to a single customer in a year; regions where
residential customer rates are subject to a freeze or cap (under Article § 7-505); or electric
cooperatives under a purchase agreement that existed prior to October 1, 2004, until the expiration
of the agreement.
47
For the 2010 compliance year, electricity suppliers retired 3,569,569 RECs, a
quantity greater than the overall RPS obligation for the year by almost 30,000 RECs.
According to the compliance reports filed with the Commission, the cost of RECs retired
totaled $7,630,526 for the 2010 compliance year. For each of the five compliance years,
Table VI.B.4 displays: the breakdown of RECs submitted for each tier in MWh; the
number of RECs retired in the year by tier in MWh; and the cumulative tiered shortfalls,
in terms of the ACP amount required in dollars per MWh.
93
Table VI.B.4: RPS Supplier Annual Report Results as of December 31, 2010
RPS Compliance Year
Tier 1
(non-solar) Tier 1 Solar Tier 2 Total
RPS Obligation (MWh)
520,073 - 1,300,201 1,820,274
Retired RECs (MWh)
552,874 - 1,322,069 1,874,943
2006
ACP Required ($/MWh)
$13,293
-
$24,917
$38,209
RPS Obligation (MWh)
553,612 - 1,384,029 1,937,641
Retired RECs (MWh)
553,374 - 1,382,874 1,936,248
2007
ACP Required ($/MWh)
$12,623
-
$23,751
$36,374
RPS Obligation (MWh)
1,183,439 2,934 1,479,305 2,665,678
Retired RECs (MWh)
1,184,174 227 1,500,414 2,684,815
2008
ACP Required ($/MWh)
$9,020
$1,218,739
$8,175
$1,235,934
RPS Obligation (MWh)
1,228,521 6,125 1,535,655 2,770,301
2009
Retired RECs (MWh)
1,280,946 3,260 1,509,270 2,793,475
ACP Required ($/MWh)
$395 $1,147,600 $270 $1,148,265
RPS Obligation (MWh)
1,922,070 15,985 1,601,723 3,539,778
2010
Retired RECs (MWh)
1,931,367 15,451 1,622,751 3,569,569*
ACP Required ($/MWh)
$20 $217,600 $0 $217,620
Sources: Annual Utility RPS Filings with the Commission in years 2007, 2008, 2009, 2010, and 2011.
Commission Reports, M
ARYLAND PUBLIC SERVICE COMMISSION, available at
http://webapp.psc.state.md.us/Intranet/psc/Reports_new.cfm (last visited Dec. 2011).
*Note
: Some electricity suppliers retired more RECs than required by individual RPS obligations.
In 2010 there was a shortfall of 544 MWh in RECs for the Tier 1 Solar
requirement of 15,985 MWh—significantly lower than the 2009 Tier 1 Solar REC
shortfall of 2,865 MWh. Therefore, the reliance by electricity suppliers on ACPs to
fulfill the Tier 1 Solar requirement decreased dramatically between 2009 and 2010.
However, the shortfalls associated with the RPS solar obligation still contributed over
99% of the total ACPs due for the 2010 compliance year. The degree to which solar
technologies are available to provide renewable output plays a role in the Tier 1 Solar
compliance option selected.
93
The RPS obligation is the total obligation for electricity sales in MWh, which is equal to the
number of RECs required for compliance. The number of retired RECs is the actual number of
RECs retired for RPS compliance in each corresponding compliance year. The ACP required is
calculated by multiplying the difference between the RPS obligation and the actual retired RECs
(i.e., the shortfalls) by the applicable ACP. All ACPs are denominated in U.S. dollars.
48
Chart VI.B.5 presents the geographical location and the total generating capacity
(5,615 MW) for all Maryland RPS-certified facilities, regardless of tier.
94
RPS
requirements also exist in the surrounding states, which generally support out-of-state and
regional market participation. Of the renewable facilities that are eligible to participate
and potentially provide renewable energy to Maryland, 68 percent are located in the Mid-
Atlantic states.
95
The locations of the remaining eligible resources span seven states and
in total contribute the remaining 32 percent of the State’s eligible capacity.
96
Chart VI.B.5: Maryland RPS Eligible Capacity by State
461.7
180.1
44.6
0.6
0.0
122.5
300.0
738.6
1,325.7
1,187.0
438.6
109.6
705.9
-
200
400
600
800
1,000
1,200
1,400
PA MD IL DE VA WV IN NY NJ OH WI DC NC
State
Capacity (MWs)
Source: PJM-EIS, Generation Attribute Tracking System, Database query, August 2011.
C. Solar Power Requirements in Maryland
In 2008, the Commission laid the foundation for an active solar market in
Maryland. Regulations were enacted which established a small generator interconnection
standard supported by an expedited process for the interconnection of solar facilities.
Additionally, regulations were adopted that established a mechanism for creating solar
renewable energy credits (“SRECs”) and a corresponding tracking site. To further
streamline the process, an on-line Solar Renewable Energy Facility application form was
introduced to the Commission’s website. Also, in 2009 the Commission approved
94
The information in this figure comes from PJM GATS, and does not include Commission
authorized renewable energy facilities that have not established a REC account with PJM GATS.
Facilities are classified as “MD Certified” if they have applied to the Commission and received an
approval number that is recorded in GATS.
95
For this discussion, the Mid-Atlantic states are classified as Pennsylvania, Maryland, Delaware,
Virginia, New Jersey, and the District of Columbia (“D.C”). The combined capacity of these Mid-
Atlantic state facilities is 3,803.5 MW, or approximately 68% of the total generating capacity of
Maryland RPS-certified facilities.
96
The other six states referenced in the text are: Illinois, West Virginia, Indiana, New York, Ohio,
Wisconsin, and North Carolina. The combined capacity of these facilities is 1,811.5 MW, or
approximately 32% of the total generating capacity of Maryland RPS-certified facilities.
49
modifications to the solar regulations to reduce the filing requirements for small solar
facilities.
For compliance year 2010, an LSE subject to Maryland RPS compliance
97
was
obligated to purchase a minimum of 0.025% of its electricity resources from eligible solar
sources.
98
The solar RPS obligation increases incrementally each year until reaching the
required 2.000% by 2022.
99
If an LSE fails to offset the applicable percentage of retail
electricity sales with electricity derived from solar resources or from the purchase of
SRECs, then the LSE is responsible for making an alternative compliance payment as set
forth in the RPS statute.
100
An electricity supplier seeking to satisfy its solar RPS obligation may choose to
accumulate credits from a renewable on-site generator for purposes of RPS
compliance.
101
The rated capacity of the renewable on-site generator governs the
minimum contract terms by which the LSE and solar electricity generator must generally
abide.
The Maryland Solar RPS grants customers the rights to the SRECs each system
earns, and requires contract terms to be a minimum of 15 years when the renewable
energy credits are purchased by an electricity supplier directly from the solar electricity
generator. For facilities that are greater than 10 kW in rated capacity, the stipulation
associated with an LSE purchasing SRECs directly from a renewable on-site generator to
meet the solar component of the Maryland RPS is that the contract terms for the SRECs
must be for no less than 15 years.
102
An LSE that purchases SRECs directly from a solar renewable on-site facility that
is less than 10 kW in rated capacity must do so through a contract that provides for an up-
front lump sum payment for at least 15-years’ worth of SRECs at a price that is
determined by the Commission. The up-front purchase of SRECs is intended to aid in
financing the construction of this type of solar installation. The current proposed level of
payment for the SRECs is the net present value of the 15-years’ worth of RECs using
80% of the compliance fee schedule,
with a discount rate that is equal to the Federal
Secondary Credit Interest Rate.
103
Beginning January 1, 2012, electricity generated from a Tier 1 solar renewable
source must be connected with the electric distribution grid serving Maryland in order for
the generation to be eligible to create Maryland SRECs after that date. Until January 1,
2012, SRECS from non-Maryland Tier 1 solar renewable energy facilities located in PJM
are eligible for the Maryland RPS only to the extent that there is a shortage of SRECs
derived from facilities interconnected with the Maryland grid. All Maryland-based Tier 1
97
See supra Section VI.B. (discussing entities subject to the RPS obligation).
98
MD. CODE ANN., PUB. UTIL. § 7-703(b) (2011).
99
See supra Table VI.B.2.
100
MD. CODE ANN., PUB. UTIL. § 7-705(b) (2011). See supra Table VI.B.3.
101
MD. CODE ANN., PUB. UTIL. § 7-709(a) (2011).
102
MD. CODE ANN., PUB. UTIL. § 7-709 (2011).
103
See COMAR 20.61.
50
solar renewable energy facilities must be certified by the Commission as a Maryland
renewable energy facility, prior to the facility being eligible to create Maryland-eligible
SRECs. As of August 2011, GATS had registrations for 1,585 solar facilities in
Maryland with a total capacity of 25.83 MW.
The decisions made in surrounding states regarding RPS requirements, ACP
levels, and the availability of state grants or subsidized loans may potentially impact the
Maryland RPS program. The prices that Maryland LSEs will need to offer to obtain
RECs in the spot market and under longer term arrangements may reflect the decisions of
surrounding states.
VII. ELECTRIC DISTRIBUTION RELIABILITY IN MARYLAND
The Commission supervises and regulates public service companies to promote
the economical and efficient delivery of utility services in the State. Economical and
efficient delivery of electricity depends on a well-planned, maintained, and operated
distribution system.
A. Electric Distribution Reliability Reporting, Operation and
Maintenance
Electric utilities serving 40,000 or more Maryland customers are required to file
an Annual Reliability Report with the Commission. For each utility, the reports contain
measurements of reliability for the preceding calendar year of the System Average
Interruption Duration Index (“SAIDI”), the System Average Interruption Frequency
Index (“SAIFI”) and the Customer Average Interruption Duration Index (“CAIDI”).
104
Each investor-owned utility also reports the reliability measurements for a group of the
least reliable electric feeders in its system for the year, together with the remedial actions
it has taken to improve the reliability of those feeders. The same feeders are not
permitted to appear on a utility's least reliable list in any two successive years under a
COMAR provision designed to gradually increase over time the reliability of all feeders
in the least performing range. The large electric cooperatives report the operating district
with the least reliability for the year, together with the remedial actions taken to improve
reliability within those districts.
Routine inspection and maintenance of existing distribution system equipment
must be performed periodically to help maintain a baseline level of reliability. All
electric companies serving Maryland have developed written operation and maintenance
(“O&M”) procedures pursuant to COMAR 20.50.02.04. The O&M procedures must list
the specific inspection and maintenance tasks to be performed and the frequency with
which the tasks are to be performed. The six largest electric utilities operating in
Maryland are required to maintain their written O&M procedures with the Commission
and to file annual updates of any changes that are made to those procedures. While the
procedures vary somewhat from utility to utility, there are many common practices, since
104
CAIDI is calculated by dividing SAIDI by SAIFI.
51
the procedures should be based on utility experience and accepted good practice within
the industry.
With respect to substations, periodic attention is typically given to power
transformers, various electrical relays and circuit breakers used primarily for equipment
protection, and devices used for controlling voltage such as capacitors and voltage
regulators.
For distribution feeder lines, inspection and maintenance attention is typically
focused on the electrical conductors in general, capacitors and other voltage regulators,
automatic re-closers, electronic monitoring/control devices, vegetation management, and
support poles for overhead equipment. Utilities have ongoing, proactive programs for
replacement of aged underground electrical conductors, in addition to such activity in
reaction to service interruptions. Some utilities inject conditioners into existing
underground cable to increase its life expectancy.
The electric distribution system is a large-scale array of electric power circuits
and, increasingly, electronic sensing and control circuits. Excessive heat, whether
generated internally or by a hot day, is one of the greatest threats to the proper operation
of electric and electronic circuits. Electric utilities use infrared imaging technology in
performing periodic inspections to identify substation equipment that is operating at a
temperature higher than the normal range for proper operation. Some utilities include
distribution feeder equipment in such inspections. The value in this procedure is that
abnormally hot spots in electric conductors or equipment can often be detected and
corrected long before they fail due to overheating.
Each utility is required by COMAR to keep sufficient records to demonstrate
compliance with its O&M procedures. The Commission’s Engineering Division
conducts yearly inspection visits to the electric utilities to examine these records, in a
continuing effort to assure basic distribution system reliability.
In recent years, electric distribution utilities have made efforts to raise the
baseline level of service reliability by increasing the automation of distribution feeders,
with the potential to reduce both frequency and duration of sustained electric service
interruptions. For example, some feeders can be connected with other feeders by
switches that are normally off (open), but can be closed so that one of the feeders may
temporarily supply part or all of a feeder experiencing an outage. Currently, many of
these switches are manually operated, and require a utility crew to operate the switches to
restore power. If the operation of such a switch is automated, either with local electronic
intelligence or through remote operation from the distribution system control or
operations center, service outage time to customers can be reduced.
Although electric service interruptions cannot be totally avoided, new utility
operating methods that could serve to improve reliability include more aggressive
attempts to reduce the threat of large privately- and publicly- owned trees or large
branches falling on overhead power lines. Utilities work to gain tree owner cooperation
52
to allow the removal of large trees near the lines or large branches overhanging the lines,
which would help reduce the frequency of service outages, particularly during storms.
Other efforts involve limiting the number of customers exposed to any given outage that
does occur.
As members of Mutual Assistance Groups, the utilities share restoration crew
manpower and other resources when outages increase beyond levels thought to be
manageable using the utility's normal resources. Such assistance serves to reduce outage
duration, one common measure of reliability. In addition to crew sharing, the groups
hold conference calls for storm preparation for storm damage assessment, and to discuss
overall restoration resource availability.
The four large investor-owned electric utilities operating in Maryland are
members of the Mid-Atlantic Mutual Assistance group and the Southeastern Electrical
Exchange. Another similar group, Maryland Utilities, includes municipal and
cooperative electric utilities. These groups and others will continue to be important
alliances in the years to come, as effective distribution outage management and storm
restoration requires not only a community-wide effort, but sometimes also a regional or
national effort.
B. Distribution Reliability Issues
1. Rulemaking No. 43
The Commission instituted Rulemaking No. 43 to adopt service quality and
reliability standards. During the pendency of the Rulemaking, the Legislature enacted
Chapter 167 of the 2011 Laws of Maryland also requiring the institution of service
quality and reliability standards. The Commission convened a working group in this
Rulemaking to make recommendation, which recommendations were presented to the
Commission on October 27, 2011. The Commission considered the working group’s
recommendations and other comments submitted thereon and adopted a set of
comprehensive service quality and reliability standards.
The standards include several major categories. The Commission adopted, for
publication in the Maryland Register for notice and comment,
105
system-wide SAIDI and
SAIFI reliability metrics for each of the four investor-owned utilities and the two largest
electric cooperatives. The SAIDI and SAIFI metrics are for calendar years 2012-2015,
after which the Commission will institute company proceedings to determine future
SAIDI and SAIFI reliability metrics. To ensure that groups or pockets of customers do
not experience poor reliability, the Commission adopted standards to monitor utility
feeders and protective devices that activate multiple times. These two reliability
standards require the utilities to improve the performance of the poorest three percent of
the utility’s feeders and protective devices that operate five or more times.
105
The term “adopted” in this subsection means “adopted for notice and comment.” These standards
have not been finally adopted as of December 31, 2011.
53
Additionally, the Commission adopted standards governing a utility’s effort to
restore service interruptions. The service interruption standards call for electric service to
be restored within certain time periods during normal conditions and when major outage
events occur. Major outage events are weather-related or other events that cause an
interruption in electric service to 100,000 or 10 percent of a utility’s customers,
whichever is less.
106
To ensure adequate utility response to downed electric wires, the
Commission also adopted standards to direct utility response to hazardous downed wire
events.
The reliability and service quality standards also establish customer
communication metrics related to how long it takes a utility representative to answer a
customer’s calls, how many calls are abandoned and how much telephone line capacity is
maintained for customer inquires. These standards establish the minimum level of
expected service quality. Finally, the Commission adopted comprehensive vegetation
management and periodic equipment maintenance standards. These two categories
establish minimum practices for utilities when maintaining and operating their electric
facilities.
The electric utilities are required to submit annual performance reports to the
Commission summarizing electric service quality and reliability results. By July 1
st
of
each year, the Commission shall determine whether each company met its service quality
and reliability standards. The first review will be concluded by July 1, 2013 after
considering utility performance during 2012.
107
If a utility fails to meet one or more of
its standards, the utility must file a corrective action plan if it fails a standard. The
Commission will under take appropriate corrective action against a utility that fails to
meet a standard, including imposition of appropriate civil penalty.
Electric utilities will need to develop implementation plans or supplement existing
plans to ensure their level of performance meets or exceeds the new service quality and
reliability standards discussed above.
2. In the Matter of an Investigation into the Reliability and Quality of the
Electric Distribution Service of Potomac Electric Power Company – Case
No. 9240
As reported in the 2010 Annual Report, on August 12, 2010, the Commission
initiated the docketed Case No. 9240 for the purpose of investigating the reliability of
Pepco’s electric distribution system and the quality of electric distribution service that
Pepco is providing to its customers. The initiation of the investigation was based on the
unusually large number of complaints from Pepco’s customers and their elected officials
alleging frequent and lengthy service outages during and after storm events as well as
during “blue sky” conditions. Further, customers expressed frustration with the failure of
106
The interruption must last for 24 or more hours.
107
The standards adopted by the Commission are anticipated to become effective on July 1, 2012.
Thus, the first performance review will cover the portion of 2012 during which the standards are
effective.
54
Pepco’s communications system during storm events, which resulted in the customers
being unable to obtain estimated times of restoration or report outages. The Commission,
in addition to holding a legislative-style hearing in August 2010 for the purpose of
questioning the Company’s senior executive responsible for system reliability, storm
restoration, and customer communications:
held two evening hearings for public comment to permit members
of the public and elected officials to provide their views on
Pepco’s service quality and reliability;
issued extensive data requests to the Company to produce
documents and information;
required Pepco to hire an independent consultant to evaluate
Pepco’s distribution system and communication system
(“Consultant”), and directed the Consultant to submit a report
of the its findings and recommendations to the Commission;
and
held four days of evidentiary hearings at which the Consultant
presented its findings and all parties, as well as the
Commission, were able to cross-examine the consultant, the
Company’s witnesses and the other parties’ witnesses on their
pre-filed testimony.
Prior to the hearings in August 2010, the Company submitted its Reliability
Enhancement Plan for Montgomery County, Maryland (“REP”). According to the
Company, the REP was designed to significantly increase the reliability of its distribution
system in Maryland over a five-year period and included the following six-point
reliability programs: enhanced vegetation management; priority feeders; load growth;
distribution automation; URD cable replacement; and selective undergrounding. The
Company committed to making adjustments to plan as necessary, as the plan was
implemented.
In May 2010, Montgomery County filed its Pepco Work Group Final Report,
which contained a series of findings and recommendations by a 12-member Work Group
assembled by Montgomery County tasked with investigating the causes of Pepco’s
frequent electricity outages in the County. The filing of this Work Group Report resulted
in a contentious discovery dispute between Pepco and the County. After holding a
hearing on the discovery dispute, the Commission issued a subpoena compelling
Montgomery County to present a witness or panel of witnesses at the evidentiary hearing
to sponsor and answer questions related to the Work Group Report. Montgomery County
also responded to the discovery requests.
In addition to the Company’s witnesses’ pre-filed testimony and the Work Group
Report, pre-filed testimony was submitted by Technical Staff of the Commission,
Maryland Office of People’s Counsel, Maryland Energy Administration, and the City of
Gaithersburg. The City of Gaithersburg did not sponsor a witness and its testimony was
55
not admitted into the administrative record. The Apartment and Office Building
Association of Metropolitan Washington intervened in the matter, but did not file
testimony. The Office of People’s Counsel of the District of Columbia petitioned to
intervene, but was ultimately granted status as an interested person rather than a party.
On December 21, 2011, the Commission issued Order No. 84564 in which it
concluded that, as alleged by its customers, Pepco had failed to provide an acceptable of
reliable service during 2010 as well as several of the preceding few years. Similar to the
findings of the Consultant, the Commission found that a direct cause of Pepco’s low level
of reliability was its poor and ineffective maintenance of the vegetation surrounding its
sub-transmission and distribution system. Specifically, the Commission pointed to the
evidence in the record that Pepco failed to adequately fund its vegetation management,
failed to meet its own annual tree trimming goals, and failed to adopt a more aggressive
tree trimming practice similar to the practices adopted by other Maryland electric
companies after 2001. Moreover, the Commission cited the decline of Pepco’s SAIFI
figures (adjusted for major outages) during each year from 2004 to 2010 as proof of the
steadily deteriorating level of reliability which coincided with Pepco’s poor vegetation
management practices. These documented failures and deteriorating level of reliability as
measured by SAIDI and SAIFI were evidence of the Company’s neglectful conduct and
poor engineering practices sufficient to constitute a violation of its obligations to provide
reliable service to its customers. Further, the Commission found that Pepco failed to
conduct periodic inspections of its sub-transmission and distribution lines or to direct
after-storm inspections or patrols as required by the National Electrical Safety Code
(“NESC”) and COMAR 20.50.02.02. Although the Commission held that NESC Rule
214 does not require any precise intervals between inspections, it does require that the
Company inspect at intervals experience shows is necessary. The lack of any procedure
establishing an interval for periodic inspections reflected that the Company was not
complying with the NESC rules or COMAR. Accordingly, based on Pepco’s failure to
provide its customers reliable service and its violation of the regulations requiring it to
periodically inspection its sub-transmission and distribution line, the Commission
assessed Pepco a civil penalty of $1 million.
Many of the parties in the matter requested that the Commission, in addition to
fining the company, reduce Pepco’s authorized return on equity, restrict its payment of
dividends to PHI, direct Pepco to waive its monthly customer charge, or modify or
revoke Pepco’s authority to exercise its franchise. The Commission declined to adopt
any of these additional penalties, but it agreed with the Maryland Energy Administration,
Office of People’s Counsel and Montgomery County that it is
inequitable for Pepco to have caused significant reliability problems
and escalating EIVM costs as a result of years of poorly executed and
underfunded vegetation management programs and for the Company’s
ratepayers to be burdened with full repayment for the EIVM programs
that are now required as a direct result of the company’s
imprudence.
108
108
Order No. 84564 at 59.
56
Specifically, the Commission found that Pepco acted imprudently by: failing to
execute adequate vegetation management; by neglecting to conduct periodic inspection or
after-storm patrols; by engaging in uncertain and at times contradictory tree trimming
practices between 1999 and 2010; and by refusing to transition to a four-year tree
trimming cycle, consistent with other Maryland utilities and the recommendations of the
tree Trimming Working Group.
109
Because the Commission found that it was highly
probably this imprudence increased the cost to ratepayers of the Company’s vegetation
management programs beyond what they should have been if Pepco had acted prudently,
the Commission determined that, in a future rate case, it will disallow recovery of any
incremental amounts expended for Pepco’s vegetation management programs that is
demonstrated to have been caused by Pepco’s imprudence.
Additionally, the Commission designed a series of reporting requirements to
ensure that Pepco is implementing its REP in a manner that is significantly increasing
reliability. Also, in light of the Commission’s finding that Pepco’s ineffective
communications system contributed to significantly to customer dissatisfaction, the
Commission directed quarterly reports on Pepco’s effort to reform its communications
issues. The Commission did not modify Pepco’s REP, as requested by certain of the
parties, but encouraged Pepco to consider that comments or suggestions of these parties
as it conducts its annual review of the REP to determine further updates that will improve
reliability. Finally, the Commission warned Pepco that, in the event the periodic reports
filed by the Company did not reflect improvement of service reliability, the Commission
may consider a larger civil penalty or other additional penalties as justified by the
circumstances.
3. Electric Service Interruptions Due to Hurricane Irene
According to the United States Department of Energy (“DOE”), Hurricane Irene
made landfall near Cape Lookout, North Carolina as a Category 1 hurricane at 8:00 a.m.
EDT on August 27, 2011. In September 2011, the Commission initiated Case No. 9279
to investigate the electric service interruptions due to Hurricane Irene. Maryland’s four
investor-owned utilities,
110
along with SMECO and Choptank Electric Cooperative filed
major storm reports, pursuant to Commission Order No. 84306 and in compliance with
COMAR 20.50.07.07 in an effort to detail the utility’s response and preparation efforts
regarding Hurricane Irene.
According to data provided by utilities, customers began losing power at 7:50
a.m. EDT on August 27, 2011. Power was not restored to more than 99.9% all affected
customers until 11:30 p.m. EDT on September 4, 2011.
111
The utilities dispatched
approximately 11,882 employees to restore power as a result of Hurricane Irene, with
109
Id.
110
BGE, Pepco, Delmarva, Potomac Edison
111
BGE restored power to 756,016 of the 756,395 affected customers at the declared end of the storm
at 11:30 p.m. EDT on Sept. 4. See Baltimore Gas and Electric Company Major Storm Report –
Hurricane Irene August 27 through September 4, 2011 p 34 for detailed explanation.
57
nearly half of the employees coming from outside the utility. Out of all of the impacted
utilities, BGE experienced the highest peak of customer outages with 476,664; followed
by Pepco, 194,516; SMECO, 104,328; Delmarva, 63,597; Choptank, 11,990
112
; and
Potomac Edison, peaking with 8,554 customer outages.
On October 31, 2011 the Commission issued Order No. 84445 in the matter of the
electric service interruptions due to Hurricane Irene in the State of Maryland beginning
August 27, 2011. As a result of this Order, the four IOUs as well as Choptank and
SMECO were directed to undertake three specific categories of actions: (1) submit
implementation plans in regard to the “lessons learned” issues identified in the respective
post-Irene Major Storm Report; (2) participate in a work group tasked with developing
standards to provide customers reasonable and reliable estimated time of restoration
(“ETR”) information; and (3) file with the Commission the protocols used in determining
restoration priority.
113
C. Managing Distribution Outages
An important tool developed in recent years for managing electric distribution
system outages is the computerized Outage Management System (“OMS”). When an
outage occurs, a fully developed OMS accepts information inputs from several sources,
including customers and systems internal to the utility, and uses that information to help
develop output information as to the location and type of equipment that needs attention
in order to end the outage. This output information can then be used to generate work
orders for repairs or dispatch repair crews by way of a Mobile Dispatch System (“MDS”)
using two-way radio communication. After repairs are made or other actions taken to
end the outage, related outage information is entered as additional input into the OMS.
The OMS then can identify what customers were affected by the outage, usually what
caused the outage, and when it started and ended.
1. Typical Information Inputs to the OMS
Customer Information System (“CIS”):
When a customer calls in an
outage, the customer interacts with elements within the utility that
have access to the CIS, such as a Customer Service Representative, an
automated Interactive Voice Response (“IVR”) unit, or a High Volume
Call Service (“HVCS”). The CIS contains the customer's address, can
identify the distribution system transformer that serves the customer,
and passes this information on to the OMS. The OMS then can be
used, with assistance from the next two listed inputs, to identify the
location of the customer, both in terms of electrical position in the
system diagram and geographic position.
112
See Choptank Electric Cooperative Major Storm Report – Hurricane Irene Sept. 21 at 1. The
utility explains that it believes the maximum number of peak outages is 11,990 members but the
utility’s outage management software (OMS), which malfunctioned, reported 8,862 outages. The
OMS was used to calculate the Storm Timeline and the data in Figure 1.
113
See Commission Order No. 84445, pg. 1-2.
58
The traditional CIS function will be transformed as some utilities
begin to implement elements of Advanced Metering Infrastructure.
Advanced electric service meters and associated two-way communications
systems between the customer and utility provide an information channel
with the potential for use by both parties to make important decisions
related to the efficient supply and use of electricity. AMI also promises
faster detection of and more accurate utility response to electric service
outages, and may largely replace the role of outage detection provided by
customer calls within the traditional CIS.
Energy Management System (“EMS”): The EMS includes an electronic
diagram of the electric system showing how elements are connected
electrically. The EMS also uses remote monitoring devices such as those
of the Supervisory Control and Data Acquisition (“SCADA”) system, so
that information related to the operational condition of important, major
pieces of electric system equipment can be passed on to the OMS.
Geographic Information System (“GIS”): The GIS includes a map of key
landmarks such as streets, and it shows the location of important elements
of the electric system relative to those landmarks. This relationship is
clearly important in the effort to get repair crews to the heart of the matter.
In addition to providing information to the OMS, both the EMS electric
system diagram and the GIS map can be displayed on computer monitors
and are used by dispatchers to direct the efforts of repair crews.
Mobile Dispatch System and Work Management System (“WMS”): After
an outage is cleared, a work order is closed out within the WMS, and in
some cases the repair crew can directly close the outage with, and enter
related information directly into, the OMS using the MDS. The WMS or
MDS information usually includes the time of restoration and the cause of
the outage. After this information input is made, the OMS then contains
an archive of important information about the entire history of the outage.
2. Typical Information Outputs from the OMS
Information about the type of equipment involved in the outage and its
location is passed to the WMS or MDS so that crews can be effectively
dispatched to clear the outage.
Prior to the clearing of an outage, an Estimated Time of Restoration
(“ETR”) and other information can be fed back to the CIS, so customers
calling in who are affected by a particular ongoing outage may be kept
informed.
59
Information concerning outages can be extracted from the OMS in near
real-time to feed Internet websites containing outage reports or outage
maps.
The OMS can be queried for outage information to be used to generate
reports concerned with reliability statistics for the entire distribution
system or any part thereof.
The four large investor-owned electric utilities operating in Maryland and the
large electric cooperatives, Choptank and SMECO, have implemented OMS, each with
functionality developed generally to the extent described above.
Improvements and efforts to increase the functionality of the OMS elements are
ongoing. As with most computer and software-based systems, the OMS evolves with
each new software upgrade, and as utilities learn how to best utilize the systems.
Furthermore, the OMS is expected to evolve in the next few years as a result of the
Commission’s Order No. 84445 in the matter of the electric service interruptions due to
Hurricane Irene in the State of Maryland beginning August 27, 2011. The Order directs
the four investor-owned electric utilities and SMECO to participate in a work group
tasked with developing standards to provide customers reasonable and reliable ETR
information; ETR information is a typical information output from an OMS system.
114
Additionally, Pepco’s system tasked with providing customers and emergency
management personnel timely outage-related information remains under review in Case
No. 9240.
D. Distribution Planning Process
The role of an electric distribution system planner begins with identification of
customer needs, both for the near term and the longer term. Once identified, those needs
are translated into a flexible plan involving the engineering and operations functions
necessary to meet those needs. Short term planning typically focuses on system
expansion to keep pace with electric load growth and maintenance or improvements
related to reliability or safety of the system, with a forecast horizon of a few years.
Longer term planning, with a forecast horizon of 10 to 20 years, may include
expectations of new technologies and altered business climate, in addition to
considerations of expanded load growth, reliability, and safety of the system.
A sampling of the largest electric distribution system projects and programs,
ongoing, planned, or in development by Maryland's large electric companies, follows.
114
See Commission Order No. 84445, pg. 1-2.
60
1. PE
In 2012, PE expects to complete construction of two substations, to serve the
town of Keedysville and surrounding area, and to serve the area of Lappans
Crossroads.
PE plans to complete a major upgrade of facilities at its Urbana substation in 2012
to provide additional capacity to serve the town of Urbana and the surrounding
area.
PE plans to complete construction in 2013 of a substation to serve the town of
Walkersville and the surrounding area.
In 2014, PE plans to upgrade three substations. The substations supply an area
west of Frederick, an area south of Frederick, and the Taneytown area.
PE plans to complete the construction of a new substation to serve an area around
Deep Creek Lake by 2014.
PE expects to complete a capacity upgrade of a substation serving an area south of
Mt. Airy in 2017.
PE plans to construct a new substation to serve the area southwest of Frederick in
2019.
2. BGE
BGE plans to construct three additional new substations by the end of 2012. The
substations are to serve the Fallston area of Harford County, the Laurel area of
Howard County, and the Sykesville area of Carroll County.
BGE expects to finish the rebuilding of a substation serving northern Baltimore
City/Baltimore County in 2012. The utility also expects to complete work to
transfer load between feeders and substations to benefit the Westport area of
Baltimore City in 2012. The work will retire aging facilities and increase
reliability of the network distribution system in the area.
In 2013, BGE plans to build a new substation to serve load growth in the Konterra
Town Center and to relieve other existing substations in the Laurel area. Plans for
2013 also include completing a capacity upgrade in a substation serving Prince
George's County.
BGE plans to complete the construction of two new substations and the rebuilding
of two others in 2014. The rebuilding efforts will retire aging facilities and
increase electric capacity. These efforts will benefit the Cockeysville and Towson
areas of Baltimore County, and the Carroll/Calverton area of Baltimore City.
Between 2015 and 2016, BGE intends to build five new substations and rebuild
two others. The work would provide additional electric capacity to three areas in
Harford County, three areas in Baltimore City, and the Hampstead area of Carroll
County.
61
3. Choptank
Choptank expects load growth to occur along the U.S. Route 301 corridor in
Kent and Queen Anne Counties, Chestertown, Cambridge, Easton, the west
side of Salisbury, and the east side of Berlin.
Construction of a new substation to serve the Cambridge area is planned for
completion by the end of 2012. Currently, most of Choptank's electrical load
in Dorchester County is supplied by one substation, which constitutes a single
point of connection to the transmission grid. The addition of the new
substation would create a backup delivery point in addition to providing
increased capacity.
4. DPL
DPL plans to complete the construction of a substation to serve southern
Talbot County in 2012.
To serve southwestern Kent County, DPL plans to construct a substation and
extend two feeders in 2013. The utility also intends to complete construction
of a new substation that year to serve growing electrical load in Harford
County.
DPL expects to complete the construction of a substation and the extension of
three feeders in 2014 to serve Cecil County.
During 2017, DPL intends to complete construction of a new substation to
serve the Queenstown area of Queen Anne's County, and the rebuilding of a
substation to serve the Salisbury area.
5. Pepco
During 2012, Pepco plans to build two new feeders and to extend two others to
serve the Lanham area of Prince George's County. Plans for the year also
include extending and increasing the capacity of an existing feeder to serve the
Greenbelt Station Project.
By the close of 2012, Pepco plans to complete construction of a new feeder
and the extension of another to meet the electricity needs of the National
Harbor Development and the Gaylord National Hotel and Conference Center.
Pepco’s plans for 2013 include a capacity upgrade of a substation serving the
Colesville, Rossmoor, and Fairland areas of Montgomery County.
Pepco plans to complete the construction of a substation in 2014 to supply the
Westphalia Town Center and the Melwood and Forestville areas of Prince
George's County.
62
To accommodate the projected demand for electricity in the Hunting Hill,
Shady Grove, and Fernwood Road areas of Montgomery County, Pepco plans
to complete the construction of two substations by mid-2015. By the close of
that year, the utility intends to extend three feeders to serve the Woodmount
area of Montgomery County.
Pepco plans to complete the construction of a new substation in 2017 to
accommodate load growth in the Beltsville area of Prince George's County.
6. SMECO
During 2013, SMECO plans to purchase an additional mobile substation to be
used to provide backup power during outage contingency situations in areas
where providing backup power through distribution feeder switching is difficult
or impossible.
VIII. MARYLAND ELECTRICITY MARKETS
The Electric Customer Choice and Competition Act of 1999 (“Electric Choice
Act”) established the legal framework for the restructuring and revised regulation of the
electric industry in Maryland. The Electric Choice Act altered the Commission’s role
relative to electricity generation and provided that retail electric choice would be
available to all customers. Beginning on July 1, 2000, all retail electric customers of
IOUs in the State were given the opportunity to choose their electricity supplier. Since
July 1, 2003, customers of Maryland’s electric cooperatives have had the right to choose
suppliers under a separate schedule adopted by the Commission. Customers of
Maryland’s municipal electric utilities will be allowed to choose suppliers on a timetable
established in part by the municipal utilities.
A. Status of Retail Electric Choice in Maryland
Customers shopping for electricity in Maryland may choose to buy electricity
from a competitive supplier or to take standard offer service from their local electric
company. This framework was established by the Electric Choice Act of 1999. This Act
deregulated the pricing of electric generation and opened retail markets to competitive
suppliers. Opening retail markets for competition has attracted competitive suppliers to
Maryland. As of December 1, 2011, Maryland has 65 licensed electricity suppliers and
146 licensed electricity brokers.
115
As of December 1, 2011, the following numbers of
companies had registered on the Commission’s website as actively soliciting new
customers in any Maryland service territory: 32 serving residential load, 65 serving
industrial load, 70 serving commercial load, and 18 serving other types of load (such as
government).
115
See Table A-6.
63
An examination of the number of customers using a competitive supplier indicates
that the transition from utility-supplied generation service to electric competition in
Maryland shows that a smaller percentage of residential customers have switched to retail
suppliers than non-residential customers. As of September 30, 2011, 19.2% of residential
customers, 29.3% of small commercial customers, 56.3% of mid-sized commercial and
industrial customers and 91.7% of large commercial and industrial customers were served
by retail electricity suppliers. In terms of total electricity supply, almost half of IOU load
(47.3%) was served by retail electricity suppliers as of September 30, 2011.
In 2011, residential switching continued to increase as the number of Residential
Choice customers increased by 42% statewide. The increase in switching may be due to
the availability of savings over the Standard Offer Service rates. Certain residential
electricity offers have been observed to be on the order of 10% below the cost of
Standard Offer Service, saving an average customer about $150 per year. The
implementation of utility purchase of retail supplier receivables in 2010 for those
suppliers that use utility billing probably also played a significant role in the increase in
the number of residential customers served by retail electricity suppliers.
The following table illustrates the increase in residential customer switching during 2011:
Table VIII.A.1: Residential Customers Enrolled in Retail Supply
2010 2011
Annual %
Increase
BGE
179,801 250,856 40%
DPL
12,759 17,481 37%
PE
11,763 16,101 37%
Pepco
64,335 98,310 53%
Md. Total 268,658 382,748 42%
Source: Electric Choice Enrollment Monthly Reports.
Note:
2011 data is as of September 30, 2011.
Between December 2005 and September 2011, the total number of customers
statewide served by electricity suppliers increased from 39,527 to 553,438 customers.
During the same time, the number of customers served by electricity suppliers in BGE’s
service territory increased from 3,347 to 339,932.
64
Table VIII.A.2: Electric Choice Enrollment in Maryland as of September 30, 2011
Number of Customers Served by Competitive Electricity Suppliers
Utilities Residential Small C&I Mid C&I Large C&I All C&I Total
BGE
250,856 28,822 15,037 679 44,538 339,932
DPL
17,481 6,828 2,841 70 9,739 36,959
PE
16,101 6,760 3,211 113 10,084 36,269
Pepco
98,310 11,283 9,196 505 20,984 140,278
Total 382,748 53,693 30,285 1,367 85,345 553,438
Percentage of Peak Load Obligation Served by Competitive Electricity Suppliers
Utilities Residential Small C&I Mid C&I Large C&I All C&I Total
BGE
23.9% 34.5% 71.0% 95.5% 78.5% 48.7%
DPL
11.8% 38.2% 69.9% 91.8% 70.2% 37.4%
PE
8.1% 34.2% 64.0% 62.4% 61.1% 34.2%
Pepco
21.9% 42.4% 72.1% 94.5% 80.1% 52.7%
Total 20.9% 36.4% 70.5% 91.1% 76.5% 47.3%
Source: Electric Choice Enrollment Monthly Report, Month Ending September 2011.
Notes: Small commercial and industrial (“C&I”) customers are commercial or industrial customers with demands
less than or equal to 25 kW. These customers are eligible for “Type I” fixed-price utility SOS if they do not switch
to a supplier. Mid-sized C&I customers are commercial or industrial customers with demands greater than 25kW,
the level for small C&I service (Type I SOS) but less than 600 kW. These customers are eligible for “Type II” fixed
price utility SOS if they do not switch to a supplier. See Case Nos. 9037 and 9056 for more information on the Type
II customer class. Large C&I customers are commercial or industrial customers with demands equal to or greater
than 600 kW. These customers are no longer eligible for “Type III” SOS and receive hourly-priced service (based
on PJM hourly LMP) if they do not switch to a supplier.
B. Standard Offer Service
Standard Offer Service (“SOS”) is electricity supply service sold by electric
utility companies to any customer who does not choose a competitive supplier. The
statute requires that SOS should be “designed to obtain the best price for residential and
small commercial customers in light of prevailing market conditions at the time of the
procurement and the need to protect these customers against excessive price
increases.”
116
Except for Potomac Edison,
117
the investor owned electric companies provide
SOS by purchasing wholesale power contracts with two-year terms twice a year, for
116
MD. CODE ANN., PUB. UTIL. § 7-510(c)(4)(ii) (2011).
117
PE procures its residential and small commercial SOS full service requirement through the sealed
bid process similar to the other IOUs, but they procure a portion of the SOS load four times a year
and the length of the contract varies.
65
residential and small commercial service of two-year terms, through sealed bid
procurements. These procurements take place in the Spring and Fall for service starting
the following Fall and Summer; each procurement covers roughly 25% of the total SOS
load. Consequently, the SOS price for residential and small commercial customers at any
one time reflects an average of market conditions on those four bid days.
SOS for mid-sized non-residential customers is not intended to stabilize prices
over an extended period of time. Mid-sized non-residential SOS is procured through
sealed bids for three-month contracts procured four times a year. The price of the service
at any one time reflects market conditions on the most recent bid day.
SOS for SMECO is procured by the cooperative through an actively managed
portfolio approach. Choptank provides SOS through procurement of full-requirements
wholesale service through the Old Dominion Electric Cooperative.
IX. REGIONAL ENERGY ISSUES AND EVENTS
A. Overview of PJM, OPSI, and Reliability First
The flow of electricity and the electricity markets are undeniably regional
concepts. Maryland is not an energy island—the transmission lines located within
Maryland do not terminate at our borders, but rather are connected to the transmission
lines in adjoining states.
The entire State of Maryland resides within PJM, the RTO that coordinates the
movement of wholesale electricity in all or parts of Delaware, Illinois, Indiana, Kentucky,
Maryland, Michigan, New Jersey, North Carolina, Ohio, Pennsylvania, Tennessee,
Virginia, West Virginia, and the District of Columbia. The FERC is responsible for
approving tariff changes proposed by PJM, which wholesale market entities operating in
Maryland must abide by as a member of PJM.
The Organization of PJM States, Inc. (“OPSI”) is
an organization of statutory
regulatory agencies in the 13 states and the District of Columbia that form PJM. The
Commission is a member of OPSI.
In addition, Maryland falls within the boundaries of Reliability First, one of eight
regional entities approved by North America Electric Reliability Council (“NERC”) as of
January 1, 2006 to develop and enforce regional reliability standards.
66
1. PJM Interconnection, LLC
PJM, as an RTO, keeps the electricity supply and demand in balance by providing
power producers price signals to generate sufficient power to match supply with demand
and by adjusting import and export transactions. In managing the grid, the company
dispatches about 180,400 MW of generating capacity over 61,200 miles of transmission
lines.
118
PJM exercises a broader reliability role than that of a local electric utility. PJM
system operators conduct dispatch operations and monitor the status of the grid over a
wide area, using an enormous amount of telemetered data from nearly 74,000 points on
the grid.
119
This gives PJM a big-picture view of regional conditions and reliability
issues, including those in neighboring systems.
PJM also manages a sophisticated regional planning process for generation and
transmission expansion to ensure the continued reliability of the electric system. PJM is
responsible for maintaining the integrity of the regional power grid and for managing
changes and additions to the grid to accommodate new generating plants, substations and
transmission lines.
PJM’s members (totaling more than 750) include: power generators, transmission
owners, electricity distributors (including Maryland utilities), power marketers and large
consumers.
120
The Commission is not a member of PJM (meaning it is unable to cast a
vote); however, it does monitor and actively participates in stakeholder and committee
processes at PJM.
2. Organization of PJM States, Inc.
OPSI was established in 2005. OPSI, among other things, coordinates activities
such as data collection, issue analyses, and policy formulation related to PJM, its
operations, its market monitor, and related FERC matters.
121
OPSI provides a means for
the PJM states to act in concert with one another when it is deemed to be in their common
interest. Actions of OPSI, however, do not bind individual commissions or the states
they represent.
Each state commission has a member on the OPSI Board of Directors. Chairman
Nazarian of the Commission served as OPSI President during 2009. Commissioner
Brenner currently serves as the Commission’s member on the OPSI Board of Directors.
During 2011, OPSI was particularly active in facilitating the development of the
Independent State Agency Committee (“ISAC”). The purpose of ISAC is to provide PJM
with modeling input for potential transmission planning studies. However, no ISAC
118
PJM’s Role as an RTO, PJM (June 1, 2011), http://www.pjm.com/~/media/about-
pjm/newsroom/fact-sheets/pjms-role-as-an-rto-fact-sheet.ashx.
119
Company Overview, PJM, http://www.pjm.com/about-pjm/who-we-are/company-overview.aspx
(last visited December 1, 2011).
120
Company Overview, PJM, http://www.pjm.com/about-pjm/who-we-are/company-overview.aspx
(last visited December 1, 2011).
121
Organization of PJM States, Inc., available at: http://www.opsi.us.
67
member will be bound by the results of any PJM transmission planning study.
Furthermore, the participation of any state in ISAC proceedings will not be considered an
assessment of the merits of any particular transmission expansion project. As an OPSI
Board member, the Commission will serve as the lead agency on ISAC for the State. The
Commission continues to be a very active participant in OPSI.
3. Reliability First Corporation
ReliabilityFirst is a not-for-profit company which began operations on January 1,
2006. ReliabilityFirst's mission is to preserve and enhance electric service reliability and
security for the interconnected electric systems within the ReliabilityFirst geographic
area. The Boundaries of ReliabilityFirst are defined by the service territories of Load
Serving Entities and include all of New Jersey, Delaware, Pennsylvania, Maryland,
District of Columbia, West Virginia, Ohio, Indiana, Lower Michigan and portions of
Upper Michigan, Wisconsin, Illinois, Kentucky, Tennessee and Virginia.
ReliabilityFirst's primary responsibilities include developing reliability standards and
monitoring compliance to those reliability standards for all owners, operators and users of
the bulk electric system and providing seasonal and long-term assessments of bulk
electric system reliability within its Region. The Commission monitors ReliabilityFirst
activities and comments if necessary.
B. PJM Summer Peak Events of 2010 and 2011
Peak load is maximum load usage during a specified period of time. Table IX.B.1
provides the coincident peaks as measured by PJM to illustrate the maximum amount of
MW usage in PJM at a particular time during a 12-month period. PJM is a summer
peaking region, meaning that it has historically experienced its peak loads during hot
summer days when air-conditioning usage increases to meet cooling demand. PJM
measures energy usage over an hour; accordingly, the data in the table below means the
peak occurred sometime in the 59 minutes preceding the hour listed. The table also shows
the average LMP for each Maryland utility zone and for all of PJM at the peak hours.
68
Table IX.B.1: Summer 2010 and 2011 Coincident Peaks and Zone LMP
Summer 2010 Coincident Peaks Zone LMP During the Peak
Day Date Hour MW PE BGE DPL PEPCO PJM
Tuesday 7/6/2010 17:00 136,950 $146.60 $331.01 $332.23 $250.24 $194.70
Wednesday 7/7/2010 17:00 137,788 $139.44 $183.75 $196.80 178.59 $135.93
Friday 7/23/2010 17:00 134,917 $164.76 $271.36 $213.22 $231.33 $169.13
Tuesday 8/10/2010 17:00 132,570 $145.08 $152.42 $137.34 $141.86 $137.93
Wednesday 8/11/2010 17:00 131,949 $129.64 $126.25 $122.75 $153.04 $114.67
Summer 2011 Coincident Peaks Zone LMP During the Peak
Day Date Hour MW PE BGE DPL PEPCO PJM
Wednesday 6/8/2011 17:00 144,394 $267.88 $422.85 $352.54 $417.40 $279.82
Tuesday 7/19/2011 17:00 145,253 $96.18 $101.78 $104.43 $99.20 $99.25
Wednesday 7/20/2011 17:00 150,121 $179.70 $195.48 $207.51 $186.14 $187.70
Friday 7/21/2011 17:00 158,121 $165.32 $199.17 $196.36 $162.03 $162.36
Thursday 7/22/2011 15:00 152,921 $182.94 $361.51 $407.29 $209.20 $229.54
Source: Daily Real-Time LMP Files, PJM MARKETS & OPERATIONS, http://www.pjm.com/markets-and-
operations/energy/real-time/lmp.aspx (last visited Nov. 30, 2011).
The 2011 summer peak events in PJM were higher than the summer peak events
that occurred in 2010. Table IX.B.1 above shows the summer 2011 and 2010 coincident
peaks in PJM and the average real-time LMP by zones located in Maryland during that
time period. The summer 2011 peak was 158,121 MW and occurred on July 21, 2011
during the hour ending 5:00 PM Eastern Daylight Time.
122
The summer 2010 peak was
137,788 MW and occurred on July 7, 2010 during the hour ending 5:00 PM Eastern
Daylight Time.
123
C. PJM’s Reliability Pricing Model
As a means of ensuring reliability of the electric system in the RTO, PJM
annually conducts a long-term planning process that compares the potential available
generation located within the RTO and the import capability of the RTO against the
estimated demand of customers within the RTO and establishes the amount of generation
and transmission required to maintain the reliability of the electric grid within PJM. The
amount of capacity procured in PJM’s Reliability Pricing Model (“RPM”) is roughly
based upon a forecast of the peak load projected by PJM for a particular year, plus a
reserve margin. RPM works in conjunction with PJM’s RTEP to ensure reliability in the
PJM region for future years.
122
Summer 2011 Coincident Peaks, PJM PLANNING, http://www.pjm.com/planning/resource-
adequacy-planning/~/media/planning/res-adeq/load-forecast/pjm-5cps-and-w-n-zonal-peaks.ashx
(last updated Nov. 21, 2011).
123
Summer 2010 Coincident Peaks, PJM PLANNING, http://www.pjm.com/planning/resource-
adequacy-planning/~/media/planning/res-adeq/load-forecast/summer-2010-peaks-and-5cps.ashx
(last updated Nov. 11, 2010).
69
Using this information, PJM evaluates offers from generators and other resources
three years in advance to be available for a one year delivery period running from June
through May (up to three years for new generation) through the Base Residual Auction
(“BRA”).
124
Once PJM completes its RTEP and conducts the RPM BRA, PJM is in a
position to evaluate the reliability of its system. PJM must operate the transmission
system to meet reliability criteria established by the FERC and administered by the
NERC.
PJM held the BRA for the 2014/2015 delivery period in May 2011. PJM
calculated the RTO reliability requirement to be 148,323.1 MW, which includes a 15.3%
reserve margin. However, as a result of the administratively determined downward
sloping demand curve - the Variable Resource Requirement - more resources than needed
cleared the market. In 2011, 149,974.7 MW cleared the BRA, which essentially
increased the reserve margin to 20.6%. This means 1,651.6 MW in excess of the
reliability requirement were procured in the BRA. Approximately 10,511.6 MW of
excess capacity was offered into the 2014/2015 BRA (i.e., this capacity did not clear);
accordingly, for the 2014/2015 delivery year, approximately 12,163.2 MW of capacity in
excess of the RTO reliability requirement was offered into the BRA.
125
The “Net Load” capacity prices for the IOUs in Maryland for each of the eight
completed BRAs are presented in Table IX.C.1. The estimated total capacity cost to
Maryland of each BRA is also presented. The Net Load capacity price reflects the BRA
clearing price and credits from any transmission capacity transfer rights. Maryland has
experienced significant volatility in Net Load prices from the past eight BRAs. The Net
Load cost to Maryland from the first BRA for the 2007/2008 delivery year was
approximately $693 million. By the 2009/2010 BRA, capacity cost had increased to
approximately $1.131 billion before declining to $580 million for 2011/2012 and then
again increasing to approximately $1.1 billion for 2013/2014. The 2014/2015 BRA
experienced another decline in capacity cost, totaling over $700 million. The observed
historical pattern of results suggests that future BRA results could vary significantly from
year to year and must be closely monitored.
124
Reliability Pricing Model, PJM MARKETS & OPERATIONS, available at:
http://www.pjm.org/markets-and-operations/rpm.aspx.
125
2014/2015 Base Residual Auction Report, PJM MARKETS & OPERATIONS, available at:
http://www.pjm.com/markets-and-operations/rpm/~/media/markets-ops/rpm/rpm-auction-
info/20110513-2014-15-base-residual-auction-report.ashx.
70
126
Table IX.C.1: RPM “Net Load” Price and Cost
Potomac
Edison
BGE DPL Pepco TOTAL
Delivery
Year
($/MW-
day)
($/MW-
day)
($/MW-
day)
Maryland
($/MW-day) ($)
693,678,286
2007/2008 40.69 139.67 177.00 139.67
2008/2009 113.22 183.03 145.24 183.03 901,994,343
2009/2010 193.80 224.93 193.71 224.78 1,130,545,999
2010/2011 174.29 174.29 178.27 174.29 920,141,784
2011/2012 110.04 110.04 110.04 110.04 579,821,643
2012/2013 16.46 129.63 162.99 129.63 636,535,392
1,100,652,116
2013/2014 27.73 223.85 240.41 236.93
2014/2015 125.94 135.25 142.99 135.25 711,062,492
Source: RPM Auction User Information, PJM MARKETS & OPERATIONS, available at:
http://www.pjm.com/markets-and-operations/rpm/rpm-auction-user-info.aspx#Item01.
D. Region-Wide Demand Response in PJM Markets
Demand Response continues to be actively promoted within the wholesale
electricity markets. PJM provides the opportunity for DR to be bid into the Energy,
Capacity, Synchronized Reserve, Day-Ahead Scheduling Reserve, and Regulation
markets. 15,545 MW of demand resources were offered into the 2014/2015 BRA, which
represents an increase of 20% over the amount offered into the 2013/2014 BRA.
127
Of
that amount, 14,118 MW cleared, which is 4,836.5 MW greater than that which cleared
in the 2013/2014 BRA.
128
PJM has two basic energy and capacity market demand response programs: the
Economic Load Response Program and the Emergency Load Program. The goal of these
programs is to provide economic incentives for end-use customers to curtail their
electricity usage in the circumstances of either peak periods or unexpected outages.
126
The “Net Load” price for each company is the RPM auction price adjusted for any capacity
transfer credits and load variations from forecast. The total Maryland cost assumes a constant
demand for the periods shown based on the summer peak load contribution for each company’s
transmission zone. The PE zone includes PE, the municipal electric companies of Hagerstown,
Thurmont, Williamsport, and Somerset Rural Electric Cooperative electric loads. The DPL zone
includes DPL Maryland, Choptank, the municipal electric companies of Easton, Berlin, and A&N
Electric Cooperative loads. The Pepco zone includes Pepco Maryland and SMECO loads.
127
2014/2015 RPM Base Residual Auction Results, PJM MARKETS & OPERATIONS (Nov. 18, 2010),
http://pjm.com/markets-and-operations/rpm/~/media/markets-ops/rpm/rpm-auction-
info/20110513-2014-15-base-residual-auction-report.ashx. The newly integrated American
Transmission Systems, Inc. (“ATSI”) transmission zone accounted for 1,384 MW of the total
increase, while the other transmission zones accounted for the remaining 1,720 MW. Id. at 2.
128
Id.
71
1. Economic Load Response Program
The PJM Economic Load Response Program (“ELRP”) is a PJM-managed
accounting mechanism that provides for payment of the real savings that result from load
reductions to the load reducing customer. This is a voluntary program that allows
customers the opportunity to reduce their load and receive payments in either the energy
market or the ancillary services market, which includes reserve and regulation. Payments
in the energy market generally are based upon the difference between retail rates and day
ahead or real-time LMP. Customers who elect to have their load reductions dispatched
by PJM are guaranteed to receive a payment equal to their offer into the market.
Payments in the ancillary services markets generally are based upon the market clearing
price.
2. Emergency Load Program
The PJM Emergency Load Program is designed to provide a method by which end-
use customers may be compensated by PJM for reducing load during an emergency event.
The Emergency-Capacity Only program provides RPM payments for reducing capacity and
reduction is mandatory. The Emergency-Full program provides both RPM payments and
energy payments for reducing capacity, and reduction is mandatory. The Emergency-Energy
Only program provides energy payments to end-use customers for voluntarily reducing load
during an emergency event. The energy payment is the zonal LMP, but customers who elect
to have their load reductions dispatched by PJM are guaranteed to receive a payment equal to
their offer into the market, including shutdown costs. The 2014/2015 BRA is the first under
which two additional demand resource products were offered: Annual DR which is available
throughout the year, and Extended Summer DR, which is available for an extended summer
period. These new products have fewer limitations than the current DR product.
X. PROCEEDINGS BEFORE THE FEDERAL ENERGY REGULATORY
COMMISSION
The Commission is actively engaged in wholesale energy market policy
development at PJM. While the Commission is not a formal stakeholder in the
stakeholder process, the Commission does actively engage on issues and voice its
concerns regularly, both independently and as part of OPSI. The Commission
participates in the policy development process because decisions made at PJM directly
affect the price of electricity and related services to Maryland customers.
PJM holds more than 300 stakeholder meetings each year for more than two
dozen committees, subcommittees, task forces, and working groups. The Commission
assigns one or more Commission Advisors to represent the Commission at the major
policy-setting groups. These groups include the Members Committee, the Markets &
Reliability Committee, the Markets Implementation Committee, the Planning Committee,
and the Regional Planning Process Task Force. Other Commission Staff cover technical
and engineering-related meetings, such as the Transmission Expansion Advisory
72
Committee, Resource Adequacy Analysis Subcommittee, Demand Response
Subcommittee, and the Load Analysis Subcommittee.
Some of the issues in which the Commission is regularly engaged include load
forecasting, demand response, price responsive demand, the capacity market, shortage
pricing, governance, transmission planning and reliability planning criteria. While many of
these issues are ultimately litigated at FERC, where the Office of General Counsel represents
the Commission, being involved in PJM’s stakeholder process gives the Commission early
input into the important issues as they emerge.
APPENDIX
The Appendix contains a compilation of data provided by Maryland’s electric
companies, including the number of customers, sales by customer class, and typical
utility bills, as well as forecasted peak demand and electricity sales over the next fifteen
years, by utility. It also includes a list of licensed electricity and natural gas suppliers and
brokers in Maryland, renewable energy projects, planned transmission enhancements, and
potential new power plants in Maryland.
73
74
Table A-1: Utilities Providing Retail Electric Service in Maryland
Utility Service Territory
A&N Electric Cooperative Smith Island in Somerset County
Baltimore Gas & Electric Company Anne Arundel County, Baltimore City, Baltimore
County and portions of the following counties:
Calvert, Carroll, Howard, Harford, Montgomery, and
Prince George's.
Town of Berlin Town of Berlin.
Choptank Electric Cooperative Portions of the Eastern Shore.
Delmarva Power & Light Company Major portions of ten counties primarily on the
Eastern Shore.
Easton Utilities Commission City of Easton.
Hagerstown Municipal Electric Light
Plant
City of Hagerstown.
Potomac Edison Company Parts of Western Maryland.
Potomac Electric Power Company Major portions of Montgomery and Prince George's
Counties.
Somerset Rural Electric Cooperative Northwestern corner of Garrett County.
Southern Maryland Electric Cooperative Charles and St. Mary's Counties; portions of Calvert
and Prince George's Counties.
Thurmont Municipal Light Company Town of Thurmont
Town of Williamsport Town of Williamsport
Source: Table 1 in Company data responses to the Commission’s 2011 data request for the Ten-Year Plan.
Table A-2: Number of Customers by Customer Class as of December 31, 2010
Utility/Co. Residential Commercial Industrial Other
Sales for
Resale
Total Residential Commercial Industrial Other
Sales for
Resale
Total
A&N N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A
Berlin 1,968 293 112 18 0 2,391 1,968 293 112 18 0 2,391
BGE
1,114,712 118,575 5,536 0 0 1,238,823 1,114,712 118,575 5,536 0 0 1,238,823
Choptank 47,179 4,787 22 255 0 52,243 47,179 4,787 22 255 0 52,243
DPL 287,398 58,688 451 648 0 347,185 94,414 25,577 241 274 0 120,506
Easton
96,779 23,388 0 0 0 120,167 96,779 23,388 0 0 0 120,167
Hagerstown 14,798 2,471 123 0 0 17,392 14,798 2,471 123 0 0 17,392
PE
334,650 42,838 4,841 665 3 382,997 220,576 27,186 2,861 345 3 250,971
PEPCO 713,148 73,782 0 1,368 0 788,298 483,906 47,349 0 1,336 0 532,591
SMECO 136,191 13,641 6 314 0 150,152 136,191 13,641 6 314 0 150,152
Somerset
12,212 1,157 6 0 0 13,375 754 37 3 0 0 794
Thurmont 2,441 332 10 43 0 2,826 2,441 332 10 43 0 2,826
Williamsport
857 72 32 44 0 1,005 857 72 32 44 0 1,005
Total 2,762,333 340,024 11,139 3,355 0 3,116,854 2,214,575 263,708 8,946 2,629 3 2,489,861
System Wide Maryland
Source
: Company data responses to Table A-2 in the Commission's 2011 data request for the Ten-Year Plan.
Note: A&N did not provide the requested information.
75
Table A-3: Typical Monthly Electric Bills in Maryland (Winter 2010)
Utility/Co. Residential Commercial Industrial Other Residential Commercial Industrial Other Residential Commercial Industrial Other
A&N N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A
Berlin 1,661 1,227 8,969 1,663 249.44 238.28 1503.62 395.73 0.1502 0.1942 0.1676 0.2380
BGE
1,251 11,886 47,477 N/A 182.71 559.00 961.39 N/A 0.1461 0.0470 0.0202 N/A
Choptank 1,406 3,506 308,531 272 184.72 443.72 29175.09 71.07 0.1314 0.1266 0.0946 0.2622
DPL
1,327 5,547 130,086 3,868 181.05 290.35 2102.04 854.09 0.1365 0.0523 0.0162 0.2208
Easton 1,527 6,243 N/A N/A 155.56 670.72 N/A N/A 0.1019 0.1074 N/A N/A
Hagerstown 1,110 2,720 71,329 N/A 111.35 284.09 6576.78 N/A 0.1003 0.1045 0.0922 N/A
PE
1,540 7,687 51,412 N/A 157.36 922.68 4842.91 N/A 0.1022 0.1200 0.0942 N/A
PEPCO 1,227 15,030 3,298,402 82,154 165.23 675.11 49027.70 3249.22 0.1347 0.0449 0.0149 0.0396
SMECO 750 12,500 200,000 N/A 108.11 1533.73 21324.05 N/A 0.1442 0.1227 0.1066 N/A
Somerset
N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A
Thurmont 1,896 4,606 252,541 1,608 197.70 451.74 22478.08 180.27 0.1043 0.0981 0.0890 0.1121
Williamsport 974 1,872 16,512 1,641 95.23 189.34 1657.44 154.06 0.0977 0.1011 0.1004 0.0939
Total
14,669 72,824 4,385,259 91,205 1788.46 6258.76 139649.10 4904.45 1.3494 1.1189 0.7959 0.9666
Typical Bill ($) Revenue ($/kWh)Energy Use (kWh)
Source: Table A-3 in Company data responses to the Commission's 2011 data request for the Ten-Year Plan.
Note:
For those utilities that have retail competition available, bills and revenues reflect SOS, distribution service and any non-bypassable charges.
Note: Winter is defined as Dec. 1 through Feb. 29--as defined by PJM.
Note: A&N did not provide the requested information.
76
Table A-4(a): System Wide Peak Demand Forecast as of December 31, 2010 (MW) (Net of DSM Programs)
Year Berlin BGE Choptank DPL Easton Hagerstown PE Pepco SMECO Thurmont Williamsport
Total
2011
4 6,699 232
3,979
68 68
2,691
6,593 838 20 5
21,196
2012
4 6,710 236
3,892
69 63
2,712
6,538 836 20 5
21,084
2013
4 6,880 248
3,871
71 63
2,728
6,535 851 20 5
21,274
2014
4 6,840 257
3,878
72 63
2,750
6,562 867 20 5
21,317
2015
4 6,802 266
3,887
73 64
2,773
6,586 882 20 5
21,361
2016
4 6,728 276
3,920
74 64
2,809
6,623 897 20 5
21,420
2017
5 6,822 287
3,960
75 64
2,844
6,682 913 20 5
21,676
2018
5 6,917 297
4,007
77 65
2,883
6,743 928 20 5
21,945
2019
5 7,014 307
4,059
78 65
2,925
6,825 943 20 5
22,245
2020
5 7,112 318
4,120
79 65
2,969
6,901 958 20 5
22,552
2021
5 7,213 329
4,167
80 66
3,012
6,957 973 20 5
22,827
2022
5 7,314 341
4,217
82 66
3,061
7,018 987 20 5
23,115
2023
6 7,407 354
4,267
83 66
3,113
7,077 1,002 20 5
23,398
2024
6 7,497 367
4,318
84 67
3,168
7,144 1,017 20 5
23,692
2025
6 7,586 381
4,367
85 67
3,217
7,207 1,031 20 5
23,971
Chan
g
e (MW)
(2011-2025)
2 887 149 388 17 (1) 526 614 193 - - 2,775
Percent
Change
47.50% 13.24% 64.42% 9.75% 25.38% -1.91% 19.54% 9.31% 23.05% 0.00% 0.00% 13.09%
Annual
Growth Rate
2.82% 0.89% 3.62% 0.67% 1.63% -0.14% 1.28% 0.64% 1.49% 0.00% 0.00% 0.88%
Source: Table A-4 in Company data responses to the Commission's 2011 data request for the Ten-Year Plan.
77
Table A-4(b): Maryland Peak Demand Forecast as of December 31, 2010 (MW) (Net of DSM Programs)
Year Berlin BGE Choptank DPL Easton Hagerstown PE Pepco SMECO Thurmont Williamsport
Total
2011 4 6,699 232 1,118 68 68
1,412
3,322 838 20 5
13,786
2012 4 6,710 236 1,117 69 63
1,415
3,237 836 20 5
13,711
2013 4 6,880 248 1,117 71 63
1,414
3,246 851 20 5
13,918
2014 4 6,840 257 1,116 72 63
1,420
3,256 867 20 5
13,919
2015 4 6,802 266 1,111 73 64
1,426
3,261 882 20 5
13,913
2016 4 6,728 276 1,121 74 64
1,445
3,281 897 20 5
13,914
2017 5 6,822 287 1,133 75 64
1,463
3,312 913 20 5
14,098
2018 5 6,917 297 1,147 77 65
1,483
3,344 928 20 5
14,287
2019 5 7,014 307 1,163 78 65
1,506
3,388 943 20 5
14,493
2020 5 7,112 318 1,181 79 65
1,531
3,428 958 20 5
14,702
2021 5 7,213 329 1,195 80 66
1,556
3,458 973 20 5
14,900
2022 5 7,314 341 1,210 82 66
1,585
3,490 987 20 5
15,105
2023 6 7,407 354 1,225 83 66
1,617
3,522 1,002 20 5
15,305
2024 6 7,497 367 1,241 84 67
1,651
3,557 1,017 20 5
15,511
2025 6 7,586 381 1,255 85 67
1,680
3,591 1,031 20 5
15,707
Chan
g
e (MW)
(2011-2025)
2 887 149 138 17 (1) 267 268 193 - - 1,921
Percent
Change
47.50% 13.24% 64.42% 12.33% 25.38% -1.91% 18.91% 8.08% 23.05% 0.00% 0.00% 13.93%
Annual
Growth Rate
2.82% 0.89% 3.62% 0.83% 1.63% -0.14% 1.24% 0.56% 1.49% 0.00% 0.00% 0.94%
Source: Table A-4 in Company data responses to the Commission's 2011 data request for the Ten-Year Plan.
78
Table A-4(c): System Wide Peak Demand Forecast as of December 31, 2010 (MW) (Gross of DSM Programs)
Year Berlin BGE Choptank DPL Easton Hagerstown PE Pepco SMECO Thurmont Williamsport Total
2011 11 7,374 242 4,148 68 68
2,720
6,986 871 20 5
22,512
2012 11 7,471 246 4,173 69 63
2,757
7,095 878 20 5
22,787
2013 11 7,596 258 4,226 71 63
2,787
7,192 897 20 5
23,124
2014 11 7,717 267 4,278 72 63
2,825
7,271 915 20 5
23,443
2015 11 7,833 276 4,328 73 64
2,864
7,339 931 20 5
23,742
2016 11 7,931 286 4,361 74 64
2,903
7,376 946 20 5
23,977
2017 11 8,025 297 4,401 75 64
2,935
7,435 962 20 5
24,229
2018 12 8,120 307 4,448 77 65
2,971
7,496 977 20 5
24,496
2019 12 8,217 317 4,500 78 65
3,010
7,578 992 20 5
24,792
2020 12 8,315 328 4,561 79 65
3,049
7,654 1,007 20 5
25,094
2021 12 8,416 339 4,608 80 66
3,085
7,710 1,022 20 5
25,362
2022 12 8,507 351 4,658 82 66
3,124
7,771 1,036 20 5
25,631
2023 12 8,610 364 4,708 83 66
3,164
7,830 1,051 20 5
25,913
2024 13 8,700 377 4,759 84 67
3,210
7,897 1,066 20 5
26,196
2025 13 8,789 391 4,808 85 67
3,249
7,960 1,080 20 5
26,467
Chan
g
e (MW)
(2011-2025)
2 1,415 149 660 17 (1) 530 974 209 - - 3,955
Percent
Change
17.59% 19.19% 61.72% 15.91% 25.38% -1.91% 19.48% 13.94% 23.96% 0.00% 0.00% 17.57%
Annual
Growth Rate
1.16% 1.26% 3.49% 1.06% 1.63% -0.14% 1.28% 0.94% 1.55% 0.00% 0.00% 1.16%
Source: Table A-4 in Company data responses to the Commission's 2011 data request for the Ten-Year Plan.
79
Table A-4(d): Maryland Peak Demand Forecast as of December 31, 2010 (MW) (Gross of DSM Programs)
Year Berlin BGE Choptank DPL Easton Hagerstown PE Pepco SMECO Thurmont Williamsport Total
2011 11 7,374 242 1,249 68 68
1,441
3,713 871 20 5
15,061
2012 11 7,471 246 1,256 69 63
1,459
3,770 878 20 5
15,248
2013 11 7,596 258 1,272 71 63
1,474
3,822 897 20 5
15,487
2014 11 7,717 267 1,288 72 63
1,495
3,864 915 20 5
15,716
2015 11 7,833 276 1,303 73 64
1,517
3,900 931 20 5
15,932
2016 11 7,931 286 1,313 74 64
1,538
3,920 946 20 5
16,107
2017 11 8,025 297 1,325 75 64
1,554
3,951 962 20 5
16,288
2018 12 8,120 307 1,339 77 65
1,572
3,984 977 20 5
16,475
2019 12 8,217 317 1,355 78 65
1,591
4,027 992 20 5
16,677
2020 12 8,315 328 1,373 79 65
1,611
4,068 1,007 20 5
16,881
2021 12 8,416 339 1,387 80 66
1,628
4,097 1,022 20 5
17,072
2022 12 8,507 351 1,402 82 66
1,648
4,130 1,036 20 5
17,258
2023 12 8,610 364 1,417 83 66
1,669
4,161 1,051 20 5
17,457
2024 13 8,700 377 1,433 84 67
1,693
4,197 1,066 20 5
17,652
2025 13 8,789 391 1,447 85 67
1,712
4,230 1,080 20 5
17,839
Change (MW)
(2011-2025)
2 1,415 149 199 17 (1) 271 518 209 - - 2,779
Percent
Change
17.59% 19.19% 61.72% 15.91% 25.38% -1.91% 18.82% 13.94% 23.96% 0.00% 0.00% 18.45%
Annual
Growth Rate
1.16% 1.26% 3.49% 1.06% 1.63% -0.14% 1.24% 0.94% 1.55% 0.00% 0.00% 1.22%
Source: Table A-4 in Company data responses to the Commission's 2011 data request for the Ten-Year Plan.
80
Table A-5(a): System Wide Energy Sales Forecast (GWh) (Net of DSM Programs)
Year Berlin BGE Choptank DPL Easton Hagerstown PE Pepco SMECO Thurmont Williamsport Total
2011
41
31,991
953 12,579
275 337 14,135 26,574 3,534 85 20
90,525
2012
41
31,963
975 12,696
278 307 14,358 26,840 3,567 85 20 91,130
2013
41
32,002
995 12,777
281 310 14,503 27,070 3,631 85 20
91,714
2014
41
32,461
1,008 12,864
283 313 14,697 27,284 3,693 85 20
92,750
2015
42
32,938
1,029 13,007
286 316 14,885 27,590 3,755 85 20 93,952
2016
42
33,382
1,047 13,181
289 319 15,100 27,954 3,818 85 20
95,238
2017
43 33,931 1,066 13,365
291 323 15,321 28,272 3,877 85 20 96,593
2018
43 34,488 1,087 13,573
294 326 15,550 28,636 3,937 85 20
98,039
2019
44 35,054 1,106 13,835
297 336 15,787 29,057 3,992 85 20
99,613
2020
45 35,628 1,126 14,126
299 329 16,012 29,547 4,045 85 20 101,262
2021
45
36,212
1,146 14,371
302 332 16,256 29,979 4,098 85 20
102,848
2022
46
36,805
1,168 14,892
305 336 16,510 29,432 4,147 85 20 103,746
2023
47
37,408
1,191 15,130
307 339 16,775 29,779 4,200 85 20
105,281
2024
48
38,020
1,215 15,356
310 342 17,047 30,147 4,250 85 20
106,840
2025
48
38,642
1,241 15,633
313 346 17,315 30,570 4,299 85 20 108,512
Change (GWh)
(2011-2025)
7 6,651 288 3,054 37 9 3,180 3,996 765 - - 17,987
Percent
Change
18.39% 20.79% 30.22% 24.27% 13.55% 2.77% 22.49% 15.04% 21.64% 0.00% 0.00% 19.87%
Annual Growth
Rate
1.21% 1.36% 1.90% 1.56% 0.91% 0.20% 1.46% 1.01% 1.41% 0.00% 0.00% 1.30%
Source: Table A-5 in Company data responses to the Commission's 2011 data request for the Ten-Year Plan.
81
82
Table A-5(b): Maryland Energy Sales Forecast (GWh) (Net of DSM Programs)
Year Berlin BGE Choptank DPL Easton Hagerstown PE Pepco SMECO Thurmont Williamsport
Total
2011
41
31,991
953 4,279
275 337 7,392 15,105 3,534 85 20
64,012
2012
41
31,963
975 4,311
278 307 7,497 15,065 3,567 85 20
64,109
2013
41
32,002
995 4,348
281 310 7,542 15,186 3,631 85 20
64,440
2014
41
32,461
1,008 4,379
283 313 7,632 15,255 3,693 85 20
65,170
2015
42
32,938
1,029 4,433
286 316 7,722 15,407 3,755 85 20
66,032
2016
42
33,382
1,047 4,478
289 319 7,835 15,571 3,818 85 20
66,887
2017
43 33,931 1,066 4,515
291 323 7,956 15,732 3,877 85 20
67,839
2018
43 34,488 1,087 4,557
294 326 8,080 15,915 3,937 85 20
68,831
2019
44 35,054 1,106 4,606
297 336 8,208 16,112 3,992 85 20
69,860
2020
45 35,628 1,126 4,675
299 329 8,329 16,358 4,045 85 20
70,938
2021
45
36,212
1,146 4,734
302 332 8,464 16,616 4,098 85 20
72,056
2022
46
36,805
1,168 4,808
305 336 8,609 16,315 4,147 85 20
72,643
2023
47
37,408
1,191 4,867
307 339 8,763 16,540 4,200 85 20
73,768
2024
48
38,020
1,215 4,920
310 342 8,922 16,733 4,250 85 20
74,865
2025
48
38,642
1,241 4,993
313 346 9,076 16,978 4,299 85 20
76,041
Chan
g
e (GWh)
(2011-2025)
7 6,651 288 714 37 9 1,684 1,873 765 - - 12,029
Percent
Change
18.39% 20.79% 30.22% 16.69% 13.55% 2.77% 22.78% 12.40% 21.64% 0.00% 0.00% 18.79%
Annual
Growth Rate
1.21% 1.36% 1.90% 1.11% 0.91% 0.20% 1.48% 0.84% 1.41% 0.00% 0.00% 1.24%
Source: Table A-5 in Company data responses to the Commission's 2011 data request for the Ten-Year Plan.
Table A-6: Maryland Licensed Electric/Natural Gas Suppliers and Brokers
as of December 1, 2011
Company
Electricity
Supplier
License No.
Electricity
Broker
License No.
Natural Gas
Supplier
License No.
Natural Gas
Broker
License No.
5Linx Enterprises, Inc.
IR-2167 IR-2166
A Better Choice Energy Services
IR-1697 IR-1698
Acclaim Energy, Ltd.
IR-1726 IR-1728
Advantage IQ, Inc.
IR-2240 IR-2242
Affiliated Power Purchasers International, LLC
IR-279 IR-2127
Affinity Energy Management, LLC
IR-2016 IR-2104
Allegheny Energy Supply
IR-229 IR-229
Alphabuyer, Inc.
IR-2214 IR-2217
Ambit Northeast, LLC
IR-1992 IR-1993
Ameresco, Inc.
IR-2145 IR-2144
Amerex Brokers, LLC
IR-1513 IR-1512
America Approved Commercial, LLC
IR-2174
America Approved Energy Services Direct, LLC
IR-1841
American Power Partners LLC
IR-2142
American PowerNet Management, L.P.
IR-604
AOBA Alliance, Inc.
IR-267 IR-375
AP Gas & Electric (MD), LLC d/b/a APG&E
IR-2231
API Ink, LLC
IR-1399
ARS International, Inc.
IR-1181
Avalon Energy Services, LLC
IR-1693 IR-1743
Better Cost Control, LLC d/b/a Ardor Power
IR-2082
BGE Home Products and Services, Inc. also d/b/a
BGE Commercial Building Systems
IR-311
BGE Home Products and Services, Inc. also d/b/a
BGE Commercial Building Systems d/b/a
Constellation Electric
IR-228
BidURenergy, Inc.
IR-1847 IR-1846
BlueStar Energy Services
IR-757
Bmark Energy, Inc.
IR-2018
Bollinger Energy Corporation
IR-265 IR-322
BP Energy Company
IR-676
BTU Energy, LLC
IR-864
C & D Commercial Brokerage, Inc. t/a Capital
Energy Solutions
IR-1823
Castlebridge Energy Group
IR-1735
Castlebridge Energy Group, LLC
IR-2331
CCES, LLC
IR-2161
Champion Energy Services, LLC
IR-2196
Chesapeake Energy Services, Inc.
IR-1638
Choice! Energy Services
IR-682
Clean Currents, LLC
IR-980 IR-1782
Clearview Electric, Inc.
IR-2009
Coastal Energy Company, LLC
IR-1900
Co-eXprise, Inc.
IR-879 IR-879
Coleman Hines, Inc.
IR-1389
Colonial Energy, Inc.
IR-606
Commerce Energy, Inc.
IR-639 IR-737
83
Company
Electricity
Supplier
License No.
Electricity
Broker
License No.
Natural Gas
Supplier
License No.
Natural Gas
Broker
License No.
Commercial and Industrial Energy Solutions, LLC
IR-2062
Commercial Utility Consultants, Inc.
IR-2361
Compass Energy Services
IR-652
Competitive Energy Services-Maryland, LLC
IR-895 IR-895
ConocoPhillips Company
IR-1359
ConocoPhillips, Inc.
IR-378
Consolidated Edison Solutions, Inc.
IR-603
Constellation Energy Projects and Services
Group, Inc.
IR-239
Constellation NewEnergy, Inc.
IR-500 IR-522
Constellation NewEnergy-Gas Division, LLC
IR-655
Consumer Energy Solutions, Inc.
IR-1210
Coral Energy Gas Sales, Inc.
IR-360
CQI Associates, LLC
IR-575 IR-1753
Creativ Energy Options
IR-1528
Current Choice, Inc.
IR-2153
Cybermark Systems, Inc. d/b/a Proenergy
Consultants
IR-1785
Cypress Natural Gas, L.L.C.
IR-674
DD&J LLC
IR-1560
Delta Energy, LLC
IR-645
Direct Energy Business f/k/a Strategic Energy
IR-437
Direct Energy Services, LLC
IR-719 IR-791
Dominion Retail, Inc. t/a Dominion Energy
Solutions
IR-252 IR-345
Downing Place, LLC
IR-2011
DTE Energy Trading, Inc.
IR-686
E Source Companies, LLC
IR-2017 IR-2021
Early Bird Power
IR-1798
Eastern Shore of Maryland Educational
Consortium Energy Trust dba ESMEC Energy
Trust
IR-342
EDF Trading North America, LLC
IR-2019
EGP Energy Solutions, LLC d/b/a Atlantic
Energy Resources
IR-1363 IR-1430
Eisenbach Consulting, LLC
IR-1950 IR-1951
Electric Advisors, Inc.
IR-1183 IR-1523
Ellicott City Investments, LLC d/b/a Allied Power
Services
IR-1890 IR-1891
Emex, LLC
IR-2065
Eneractive Solutions, LLC
IR-1939
Energy Acceptance, Corp.
IR-2074
Energy Advisory Service, LLC
IR-1486 IR-1485
Energy Edge Consulting, LLC
IR-2022
Energy Enablement, LLC
IR-2385
Energy Management Resources of Missouri, Inc.
IR-2067 IR-2073
Energy Options, LLC
IR-568
Energy Plus Holdings, LLC
IR-1805
Energy Plus Natural Gas, LP
IR-2216
Energy Professionals, LLC
IR-1791
Energy Services Management, LLC d/b/a
Maryland Energy Consortium
IR-236 IR-312
84
Company
Electricity
Supplier
License No.
Electricity
Broker
License No.
Natural Gas
Supplier
License No.
Natural Gas
Broker
License No.
Energy Services Providers, Inc. d/b/a Maryland
Gas and Electric
IR-2110
Energy Shopper, LLC
IR-2048
Energy Trust, LLC
IR-1682 IR-1681
Etheredge Partners, LLC
IR-2054
Field Personnel Services d/b/a Vanguard
Engineering Services
IR-1789
FirstEnergy Solutions Corp
IR-225
Gateway Energy Services Corporation
IR-340 IR-334
GDF Suez Energy Resources
IR-605
GDF Suez Retail Energy Solutions, LLC
IR-2404
Genesis Energy International, LLC
IR-1986
Glacial Energy of Maryland, Inc.
IR-888
Glacial Natural Gas, Inc.
IR-1855
Global Energy Market Services, LLC
IR-2170
Global Montello Group Corp.
IR-2225
Goldstar Energy Group, Inc.
IR-1370 IR-1381
Good Energy, LP
IR-1592
Green Power Management Solutions, LLC
IR-1835 IR-1834
Hess Corporation
IR-219 IR-323
Horizon Power & Light, LLC
IR-704
Houston Energy Services Company, L.L.C
IR-403
Hudson Energy Services, LLC
IR-1114 IR-1120
I.C. Thomasson Associates, Inc.
IR-1445 IR-1446
IDT Energy, Inc.
IR-1747 IR-1745
Integrity Energy, LTD
IR-1985
Integrys Energy Services
IR-951
IntelliGEN Resources LP
IR-2113
Interstate Gas Supply, Inc. d/b/a IGS Energy
IR-2182
Interstate Gas Supply, Inc. d/b/a IGS Energy d/b/a
Columbia Retail Energy
IR-1836
Invado International, LLC
IR-2026 IR-2025
Liberty Power Corp, LLC
IR-607
Liberty Power Delaware, LLC
IR-962
Liberty Power Holdings, LLC
IR-957
Liberty Power, MD, LLC
IR-793
Linde Energy Services
IR-753
Long Distance Consultants, L.L.C.
IR-1455
MABLock Consulting d/b/a The Lock Group
IR-1683
Maglor Marketing Group
IR-2088 IR-2089
Major Energy Electric Services, LLC
IR-2098
Major Energy Services, LLC
IR-1749
Marathon Oil Company
IR-364
Market Direct LLC d/b/a mdenergy
IR-614
Maryland Energy Advisors, LLC
IR-1954
Maryland Energy Trust, LLC
IR-1994
MCENERGY, INC.
IR-2354
Metromedia Energy, Inc.
IR-355
Metromedia Power, Inc.
IR-867
Mid Atlantic Renewables, LLC
IR-856
MidAmerican Energy Company
IR-798
85
Company
Electricity
Supplier
License No.
Electricity
Broker
License No.
Natural Gas
Supplier
License No.
Natural Gas
Broker
License No.
Mid-Atlantic Aggregation Group Independent
Consortium, L.L.C. d/b/a MAAGIC
IR-234 IR-234
Mid-Atlantic Cooperative Solutions, Inc. d/b/a
Aero Energy
IR-2030
Mitchell Energy Management Services, Inc.
IR-1371
Mondre Energy, Inc.
IR-2334
MRDB Holdings, LP d/b/a LPB Energy
Consulting
IR-930 IR-1000
Mxenergy Electric Inc.
IR-1853
Mxenergy, Inc.
IR-327
Nania Energy, Inc.
IR-1857
National Power Source, LLC
IR-2084
National Utility Service, Inc.
IR-1400 IR-1401
Natures Current, LLC
IR-1352
Netpique, LLC
IR-2432
NextEra Energy Services, LLC
IR-966
Noble Americas Energy Solutions, LLC
IR-464 IR-464
North American Power and Gas LLC
IR-1983
North Shore Energy Consulting, LLC
IR-2160
Northeast Energy Partners
IR-1649
NOVEC Energy Solutions, Inc.
IR-338
NRGing, LLC d/b/a NetGain Energy Advisors
IR-2038 IR-2037
Oasis Power, LLC d/b/a Oasis Energy
IR-1848 IR-1929
On-Demand Energy, Inc.
IR-1442
Open Market Energy, LLC
IR-1981 IR-2013
Palmco Energy MD, LLC
IR-1803
Palmco Power MD, LLC
IR-1804
Patch Energy Services, LLC
IR-1943
Patriot Energy Group, Inc.
IR-2187
Peninsula Energy Services Company, Inc.
IR-2003
Pepco Energy Services, Inc.
IR-222
Pepco Energy Services, Inc. also d.b.a. Conectiv
Energy Services
IR-316
Planet Energy (Maryland) Corp.
IR-2133 IR-2121
Platinum Advertising II, LLC
IR-1673 IR-1668
Positive Energy Electricity Supply, LLC
IR-2164
Power Brokers, LLC
IR-2066
Power Brokers, LP
IR-1610
Power Management
IR-1670 IR-1669
PPL EnergyPlus, LLC
IR-230 IR-335
Premier Energy Group
IR-942 IR-943
Premier Power Solutions, LLC
IR-894 IR-894
Prospect Resources, Inc.
IR-2042 IR-2041
Public Power & Utility of Maryland, LLC
IR-1781
QVINTA Energy Services
IR-557 IR-530
Reflective Energy Solutions, LLC
IR-2352 IR-2253
Reliable Power Alternatives Corp.
IR-1719
Reliant Energy Northeast, LLC d/b/a Reliant
Energy
IR-2058
ResCom Energy, LLC
IR-2120
Resource Energy Systems, LLC
IR-2115
86
Company
Electricity
Supplier
License No.
Electricity
Broker
License No.
Natural Gas
Supplier
License No.
Natural Gas
Broker
License No.
Richards Energy Group, Inc.
IR-818
RMI Consulting, Inc.
IR-1685
Satori Enterprises, Inc.
IR-1499
Secure Energy Soltions, LLC
IR-2117
Select Energy Partners, LLC
IR-1864
Senergy Corporate Ventures, LLC
IR-2325 IR-2326
Shell Energy North America
IR-1357 IR-1358
Silver Star Associates Corporation
IR-2194
Simply Competitive Energy, LLC
IR-2304
Smart Choice Energy Services
IR-1611 IR-1612
Smart One Energy, LLC
IR-2355
SmartEnergy.com, Inc.
IR-270
SourceOne, Inc. (DE)
IR-2111 IR-2172
South Jersey Energy Company
IR-740
South River Consulting
IR-863
SouthStar Energy Services, LLC d/b/a Maryland
Energy
IR-2106
Spark Energy Gas, LP
IR-613
Spark Energy, LP
IR-979
Sprague Energy Corp.
IR-339
Stand Energy Corporation
IR-632
Starion Energy PA, Inc.
IR-2094
Statoil Natural Gas LLC
IR-561
Stream Energy Maryland, LLC
IR-2072
Summit Energy Services
IR-1396
Suncom Energy Inc.
IR-2051
Sustainable Star LLC
IR-2306
Taylor Consulting and Contracting, LLC
IR-1790 IR-1960
Technology Resource Solutions, Inc.
IR-2105
Technology Resources Solutions, Inc.
IR-1802
TES Energy Services, LP
IR-2169
Texas Energy Options, Inc.
IR-1542
Texas Retail Energy, LLC
IR-2272
TFS Energy Solutions, LLC
IR-918
TFS Energy Solutions, LLC d/b/a Tradition
Energy
IR-982
The Energy Link, LLC
IR-2068 IR-2069
The Eric Ryan Corporation
IR-1438 IR-1437
The Legacy Energy Group
IR-1692 IR-1691
The Loyalton Group, Inc.
IR-1766 IR-1765
Tiger Natural Gas
IR-351
Tybec Energy Management Specialist, Inc.
IR-2299
Tybec Energy Management Specialists, Inc.
IR-2163
U.S. Gas & Electric d/b/a Maryland Gas &
Electric
IR-1744
U.S. Harvest Postal Protection Services
Corp.d/b/a United States Ethane Gas Corp.
IR-1824
U.S. Harvest Postal Protection Services
Corporation d/b/a U.S. Harvest Energy &
Technologies Corp.
IR-1774
U.S. Sun Energy, Inc.
IR-1952
87
88
Company
Electricity
Supplier
License No.
Electricity
Broker
License No.
Natural Gas
Supplier
License No.
Natural Gas
Broker
License No
UEC Energy, LLC
IR-1972
UGI Energy Services, Inc.
IR-237 IR-319
Unified Energy Services, LLC
IR-1751
Usource, LLC
IR-1160
UtiliTech, Inc.
IR-915 IR-915
Utility Savings Solutions
IR-2322
Veterans Energy Supply Company, LLP
IR-2397
Virginia Power Energy Marketing, Inc. d/b/a
Dominion Sales and Marketing, Inc.
IR-689
Viridian Energy PA, LLC
IR-1840
Volunteer Energy Services, Inc.
IR-2012 IR-2004
Washington Gas Energy Services, Inc.
IR-227 IR-324
World Energy Solutions, Inc.
IR-619 IR-953
IR-2165
Xencom Green Energy, LLC
Source: PSC database and Table A-6 in Company data responses to the Commission's 2011 data request for the
Ten-Year Plan.
The Table below lists the electricity and natural gas suppliers by license type. The license
type indicates what services a supplier may offer in Maryland. The Table below only
indicates the license type and does not imply that all suppliers are offering services.
Electric Supplier
Electric Broker
Gas Supplier
Gas Broker
Total Suppliers (Incl. Brokers)*
* Certain suppliers have both natural gas and electric
licenses.
65
146
57
62
244
.
Table A-7: Transmission Enhancements by Service Area
Transmission
Owner
Voltage
(kV)
Length
(miles)
No. of
Circuits
Start
Date
Comp.
Date
In-Service
Date Purpose County Terminal County Terminal
BGE 115 0.4 2 2007 2013 2013 BTR Harford Perryman Harford Harford
BGE 115 3 2 2008 2014 2014 DA Baltimore
City
Westport Baltimore
City
Wilkens
BGE 500 1 2 2009 2019 2019 BTR Calvert MAPP
Project
Calvert MAPP Project
BGE 230 8.6 1 2011 2014 2014 BTR Harford Conastone Harford Graceton
BGE 115 3.3 1 2010 2014 2014 BTR Baltimore
County
Deer Park Baltimore
County
Northwest
BGE 115 1 2 2009 2014 2014 BTR Baltimore
City
Orchard St Baltimore
City
Front St
BGE 115 0.6 2 2012 2014 2014 DA Baltimore
City
Coldspring Baltimore
City
Melvale
BGE 230 13.7 1 2009 2014 2014 BTR Harford Graceton Harford Bagley
BGE 115 5.2 2 2012 2015 2015 DA Baltimore
City
Erdman Baltimore
City
Argon
BGE 115 5 1 2012 2015 2015 BTR Baltimore
City
Melvale Baltimore
City
Argon
BGE 230 6.1 2 2007 2015 2015 BTR Harford Raphael Rd Harford Bagley
BGE 230 4 2 2010 2015 2015 BTR Baltimore
County
Northwest Baltimore
County
Emory Grove
BGE 230 11.7 2 2007 2019 2019 BTR Harford Raphael Rd Harford Perryman
DPL 138 24 1 2014 2015 2015 BTR Queen
Annes
Wye Mills Queen
Annes
Church
Start location End Location
89
Transmission
Owner
Voltage
(kV)
Length
(miles)
No. of
Circuits
Start
Date
Comp.
Date
In-Service
Date Purpose County Terminal County Terminal
DPL 69 11.7 1 2014 2016 2016 STR Queen
Annes
Wye Mills Queen
Annes
Stevensville
DPL 69 4.42 1 2015 2017 2017 STR Wicomico Sharptown Dorchester Vienna
DPL 69 2.61 1 2011 2012 2012 BTR Worcester Ocean Bay Worcester Maridel
DPL 69 18.41 1 2011 2012 2012 BTR Dorchester Todd Talbot Trappe
DPL 138 12.33 1 2011 2012 2012 BTR Worcester Bishop Sussex Indian River
DPL 139 12.33 1 2013 2014 2014 BTR New Castle Townsend Queen
Annes
Church
DPL 230 28.28 1 2016 2017 2017 BTR Caroline Steele Dorchester Vienna
DPL 230 18.7 1 2016 2018 2018 BTR Somerset Loretto Dorchester Vienna
DPL 230 9.51 1 2016 2019 2019 BTR Wicomico Piney Grove Somerset Loretto
DPL 69 5.99 1 2016 2020 2020 DA Queen
Annes
Grasonville Queen
Annes
Queenstown
DPL 69 5.99 1 2016 2021 2021 DA Queen
Annes
Wye Mills Queen
Annes
Queenstown
DPL 69 12 1 2013 2014 2014 DA Kent Lynch Kent McCleans
DPL 69 12 1 2013 2014 2014 DA Kent Chestertown Kent McCleans
DPL 69 6.52 1 2012 2013 2013 DA Kent Massey Queen
Annes
Church
DPL 69 2.25 1 2015 2016 2016 DA Talbot Trappe Talbot Lakeside
DPL 69 2.25 1 2015 2016 2016 DA Talbot Talbot Talbot Lakeside
DPL 138 3.96 1 2011 2011 2011 BTR Accomack Wattsville Accomack Oak Hall
DPL 138 5.22 1 2014 2015 2015 BTR Cecil Cecil New Castle Glasgow
DPL 138 N/A N/A 2012 2013 2013 BTR Worcester 138th Street Worcester SVC site @ 138th
Street Sub.
DPL 69 19.13 1 2014 2016 2016 BTR Accomack Wattsville Worcester Kenney
DPL 69 15.04 1 2015 2014 2014 BTR Somerset Cristfield Somerset Kings Creek
Start location End Location
90
Transmission
Owner
Voltage
(kV)
Length
(miles)
No. of
Circuits
Start
Date
Comp.
Date
In-Service
Date Purpose County Terminal County Terminal
DPL 69 8.74 1 2016 2014 2014 BTR Worcester Ocean City Worcester Worcester
DPL 69 15.04 1 2017 2014 2014 BTR Somerset Cristfield Somerset Kings Creek
DPL 69 8.74 1 2018 2014 2014 BTR Worcester Ocean City Worcester Worcester
PE 138 16.7 1 2011 2012 2012 BTR Preston,
WV
Albright Garrett Mt. Zion
PE 230 3.2 1 Canc. -- -- BTR Frederick Doubs Frederick Eastalco (Section
205)
PE 230 3.7 1 Canc. -- -- BTR Frederick Doubs Frederick Eastalco (Section
206)
PE 138 3.2 1 2011 2012 2012 BTR Garrett Mt. Zion Mineral,
WV
Beryl
PE 230 9.8 1 2011 2012 2012 BTR Washington Ringgold Frederick Catoctin
PE 230 10.7 1 2011 2012 2012 BTR Frederick Walkersville Frederick Catoctin
PE 230 12.7 1 2010 2013 2013 BTR Frederick Catoctin Carroll Carroll
PE 230 5.4 1 2010 2013 2013 BTR Frederick Monocacy Frederick Walkersville
PE 138 6.1 1 2012 2013 2013 BTR Mineral,
WV
Beryl Allegany Black Oak
PE 230 6.7 1 2012 2013 2013 BTR Frederick Doubs Frederick Lime Kiln (Section
207)
PE 230 6.7 1 2012 2013 2013 BTR Frederick Doubs Frederick Lime Kiln (Section
231)
PE 138 4.8 1 2012 2013 2013 BTR Berkeley,
WV
Marlowe Washington Halfway
PE 138 0.1 2 2014 2015 2014 DA Garrett Altamont
(new)
Garrett Albright – Mt. Zion
Start location End Location
91
Transmission
Owner
Voltage
(kV)
Length
(miles)
No. of
Circuits
Start
Date
Comp.
Date
In-Service
Date Purpose County Terminal County Terminal
PE 138 4 1 2014 2015 2014 BTR Washington Ringgold Franklin,
PA
East Waynesboro
PE 765 19.6 1 2012 2015 SUSP BTR Hardy, WV Welton
Spring (new)
Frederick Kemptown (new)
PE 230 24.9 1 2016 2017 2017 BTR Doubs Frederick Frederick Monocacy
PE 138 0.1 2 2016 2017 2017 DA Washington McDade
(new)
Washington Halfway
Paramount No. 1
PE 230 2.1 2 2018 2019 2019 DA Frederick Urbana1 Frederick Lime Kiln -
Montgomery
PE 230 0.1 2 2019 2020 2019 DA Frederick Jefferson No.
1 (new)
Frederick Doubs - Monocacy
PE 230 0.1 2 2019 2019 2019 DA Frederick South
Frederick
No. 1 (new)
Frederick Monocacy – Lime
Kiln
PE 138 0.1 2 2019 2020 2020 DA Washington Fairplay
(new)
Washington Marlowe -
Boonsboro
PE 230 0.6 2 2019 2020 2020 DA Frederick Ridgeville 1 Frederick Mt. Airy -
Damascus
Pepco 230 10.7 2 2009 2011 2011 BTR Dickerson Existing Quince
Orchard
Existing
Pepco 230 7.5 1 2010 2011 2011 BTR Dickerson Existing Pleasant
View
Existing
Pepco 230 Unknow
n
2 2011 2012 2012 BTR Quince
Orchard
Existing Bells Mill
Rd.
Existing
Pepco 230 5.34 2 2012 2012 2012 BTR Benning Existing Ritchie Existing
Pepco 230 6.42 4 2013 2012 2012 BTR Burches Hill Existing Palmers
Corner
Existing
Start location End Location
92
Transmission
Owner
Voltage
(kV)
Length
(miles)
No. of
Circuits
Start
Date
Comp.
Date
In-Service
Date Purpose County Terminal County Terminal
Pepco 230 5.01 4 2011 2013 2013 BTR Oak Grove Existing Ritchie Existing
Pepco 230 10.98 1 2012 2014 2014 BTR Ritchie Existing Buzzard
Point
Existing
Pepco 230 10.83 1 2012 2014 2014 BTR Ritchie Existing Buzzard
Point
Existing
Pepco 500 33 1 2010 2017 2017 BTR Possum
Point
Existing Burches
Hill
Existing
Pepco 500 19 1 2010 2017 2017 BTR Burches Hill Existing Chalk Point Existing
Pepco 500 20 1 2010 2017 2017 BTR Chalk Point Existing Calvert
Cliffs
Existing
SMECO 230 20 2 2012 2013 2013 Capacity Calvert Holland Clif
f
Sw. St.
Calvert Sollers Wharf Sw.
St.
SMECO 230 10 2 2014 2015 2015
R
eliabilit
y
Calvert Sollers
Wharf Sw.
St.
St. Mary's Hewitt Rd. Sw. St.
Start location End Location
Purpose Codes:
BTR ¾ Baseline Transmission Reliability
C ¾ Capacity
DA ¾ Distribution Adequacy
STR ¾ Supplemental Transmission
Reliability
R ¾ Reliability
Source: Company data responses to Question 7 in the Commission's 2011 data request for the Ten-Year Plan.
93
94
Table A-8: Renewable Projects Providing Capacity and Energy to Maryland Customers as of December 31, 2010
Utility
Service
Area
Operator/Owner Plant Name County Energy Source
Name
Plate
Summer
PE BP Piney & Deep Creek LLC Deep Creek Garrett 20 18 Water
BGE Constellation Solar Maryland, LLC McCormick & Co. Inc. at Belcamp Hartford 1.4 1.4 Solar
Pepco Covanta Montgomery, Inc. Montgomery County Resource Recover
y
Montgomery 67.8 54 Municipal Solid Waste
PE Criterion Power Partners LLC Criterion Wind Project Garrett 70 70 Wind
BGE Eastern Landfill Gas LLC Eastern Landfill Gas LLC Baltimore 3 3 Landfill Gas
BGE Energy Recovery Operations, Inc Harford Waste to Energy Facility Harford 1.2 1.1 Municipal Solid Waste
BGE Exelon Power Conowingo Harford 506.8 572 Water
DPL Industrial Power Generating Company L
L
Wicomico Wicomico 5.4 5.4 Landfill Gas
DPL Maryland Environmental Service Eastern Correctional Institute Somerset 3.8 2.6 Wood/Wood Waste Solids
Pepco Prince George's County Brown Station Road Plant II Prince Georges 6.7 5.6 Landfill Gas
Pepco SCE Engineers Montgomery County Oaks LFGE Plant Montgomery 2.4 2.3 Landfill Gas
BGE Wheelabrator Environmental Systems Wheelabrator Baltimore Refuse Baltimore City 64.5 61.3 Municipal Solid Waste
Choptank Worcester County Renewable Energy L
L
Worcester County Renewable Energy Worcester 2 2 Landfill Gas
TOTAL 755 798.7
Capacity
Statistics (MW)
Source: Report EIA-860: "GenY10" Excel, U.S. ENERGY INFORMATION ADMINISTRATION, (Nov. 30, 2011), available at:
http://38.96.246.204/cneaf/electricity/page/eia860.html.
Table A-9: Power Plants in the PJM Process for New Electric Generating Stations
in Maryland as of December 31, 2010
Electric
Company
Service
Territory
PJM
Queue # Project Name
Status of
Application
(12/31/10)
Plant
Capacity
(MW) Fuel Type
Projected
In-Service
Date
BGE S32 Perryman Suspended 256 natural gas 2014 Q2
BGE V1-033 Pumphrey 115kV Under Construction 132 other 2015 Q1
BGE V3-037 Naval Academy Junction 13kV Under Construction 3 natural gas 2013 Q2
BGE V4-038 Friendship Manor 34.5kV Under Construction 1 methane 2013 Q1
BGE W1-033 Pumphrey 115kV Under Construction 157
b
iomass 2015 Q1
BGE W4-030 Jessup Under Construction 0 solar 2012 Q1
DPL T144 Pocomoke Under Study 20
b
iomass 2010 Q1
DPL U3-003 Mt. Olive 69kV Under Construction 2 methane 2012 Q2
DPL U3-004 Cecil Under Study 2 methane 2009 Q3
DPL V2-028 Vienna Under Study 6 solar 2010 Q4
DPL W1-070 Laurel 69kV Under Study 20 solar 2011 Q2
DPL W3-071 Worcester 25kV Under Study 13 solar 2012 Q2
DPL W3-160 Worcester 25kV Under Study 10 solar 2011 Q1
DPL W4-017 Kings Creek-Crisfield 69kV Under Study 100 wind 2013 Q4
DPL X1-032 Costen 25kV Under Construction 4 solar 2012 Q2
DPL X1-096 Loretto-Kings Creek 138kV Under Study 150 wind 2014 Q4
DPL X2-045 Kenney-Mt. Olive 69kV Under Study 20 solar 2013 Q2
DPL X2-084 East New Market 69kV Under Study 20 solar 2012 Q4
DPL X3-008 Todd 69kV Under Study 20 solar 2017 Q2
DPL X3-009 New Market 69kV Under Study 20 solar 2017 Q2
DPL X3-015 West Cambridge-Vienna 69kV Under Study 20 solar 2012 Q4
DPL X3-066 Church Hill 69kV Under Study 7 solar 2012 Q3
DPL X3-067 Church Hill 12kV Under Study 2 solar 2012 Q3
DPL X3-073 Massey 69kV Under Study 10 solar 2013 Q1
DPL X3-074 Chestertown 69kV Under Study 12 solar 2013 Q1
DPL X4-017 Fruitland 69kV Under Study 20 solar 2017 Q2
PE S14 Dans Mountain Under Study 70 wind 2009 Q4
PE T16 Gorman-Snowy Creek 69kV Under Study 30 wind 2011 Q4
PE U2-030 Four Mile Ridge Wind 138kV Under Study 60 wind 2010 Q4
PE U4-007 Jennings Randolph Dam Under Study 14 hydro 2013 Q3
PE W1-116 Emmitsburg 34kV Under Construction 14 solar 2012 Q2
PE W3-070 Metropolitan Court 34.5kV Under Study 52
b
iomass 2013 Q4
PE W4-102 Lappans 34.5kV Under Study 17 solar 2012 Q4
PE X2-038 Halfway 12.5kV Under Study 2 methane 2012 Q3
PEPCO S17 Talbert 230kV Suspended 225 natural gas 2017 Q4
PEPCO T133 Chalk Point-Bowie 230kV Suspended 225 natural gas 2016 Q4
PEPCO T134 Chalk Point-Bowie 230kV Suspended 325 natural gas 2017 Q4
PEPCO V3-017 Morgantown-Oak Grove Under Study 725 natural gas 2012 Q2
PEPCO W3-105 Dickerson 230kV Under Construction 18 oil 2011 Q4
PEPCO W4-010 White Oak Under Study 53 natural gas 2014 Q1
PEPCO W4-020 Mt. Zion 13.8kV Under Study 10 solar 2011 Q3
PEPCO W4-044 Kelson Ridge 230kV Under Study 1450 natural gas 2014 Q2
PEPCO X2-030 Morgantown-Oak Grove 230kV Under Study 830 natural gas 2016 Q1
PEPCO X3-087 Burches Hill-Brandywine 230kV Under Study 914 natural gas 2016 Q2
95
Electric
Company
Service
Territory
PJM
Queue # Project Name
Status of
Application
(12/31/10)
Plant
Capacity
(MW)
Fuel Type
Projected
In-Service
Date
PEPCO X3-088 Dickerson 230kV Under Study 440 natural gas 2016 Q4
PEPCO X3-102 Burches Hill-Possum Point 500kV Under Study 971 natural gas 2016 Q2
PEPCO X4-006 Kelson Ridge 230kV Under Study 785 natural gas 2015 Q2
PEPCO X4-007 Kelson Ridge 230kV Under Study 785 natural gas 2015 Q2
PEPCO X4-026 Aquasco 230kV Under Study 792 natural gas 2015 Q2
SMECO V2-042 Calvert Cliffs 500kV Under Study 1640 nuclear 2017 Q2
Total (MW): 11,474
Source: Generation Queues: Active, PJM, http://www.pjm.com/planning/generation-
interconnection/generation-queue-active.aspx (last visited December 18, 2011).
96