© 2020 Greenberg Traurig, LLP www.gtlaw.com | 2
The first defense an owner may raise in response to a delay claim is lack of proper notice. If the contractor
failed to follow the contractual notice requirements regarding the timing, delivery method, format, delivery
or completeness of a claim, the owner may have a complete defense. Moreover, if the contract requires the
contractor to supplement the claim and the contractor fails to properly do so, that failure may be fatal to
the contractor’s claim.
No Damages for Delay
Looking again to the construction contract for defenses to a delay claim, an owner may benefit from
including a “no damages for delay clause” in the contract. This essentially declares that delays are all part
of the business, and any costs associated with them should be written off. This clause prohibits a contractor
from recovering money damages for a delay. Many no damages for delay clauses limit relief to extensions
of time for the contractor to complete its work.
However, owners may not benefit from a no damages for delay clause if the owner actively interfered with
the performance of the work. In this scenario, the contractor must show that the owner engaged in a direct,
active, and willful act in bad faith that unreasonably interfered with the contractor’s performance of the
work.
Also, an owner may not be able to rely on a no damage for delay clause if the delay was not contemplated
by the parties at the time they entered into the contract. An example is where a delay is caused by the
discovery of asbestos on a project site, or the non-party city’s failure to timely provide a permit. In such a
case, the contractor may be awarded delay damages from the owner despite the existence of a no damages
for delay clause.
Time of the Essence
A “time is of the essence” clause may also provide a beneficial defense to a delay claim. A time of the essence
clause will hold everyone responsible for completing the work by an agreed upon time. This means that the
owner may claim that any delay is a material breach of the contract and hold the contractor liable.
Challenges to Causation
In bringing a delay claim, the contractor is required to prove causation for the delay, If the contractor is
unable to show that the delays were caused by the owner or the designer and not itself, the contractor may
prevail. On the other hand, if in response to the claim, the owner can prove that the contractor caused the
delay, the owner may escape liability for the damage resulting from the delay.
Even if the contractor can show that it was delayed through no fault of its own, the owner may still be able
to remain unscathed if the owner can show that the delay was not on the critical path of the project’s
schedule. The critical path is the sequence of longest project activities that add up to the longest overall
duration of a project. Thus, a delay that is not on the critical path is deemed not to impact the overall project
duration and therefore may not be compensable.
Concurrent Delay
Concurrent delays occur when there are two or more delays at the same time that are caused by different
events but overlap. They must be unrelated to each other and caused by different parties, or by one party
and a third party or outside cause. To identify a concurrent delay, the relevant question is to whom the delay
is attributable. If the delay is attributable to both the owner and the contractor, neither can recover delay