CPUC California Solar Initiative Annual Program Assessment
June 2019 i
CPUC California Solar Initiative Annual Program Assessment
June 2021 ii
California Solar Initiative
Annual Program Assessment
June 2021
Prepared by the
California Public Utilities Commission
Authors
Asal Esfahani
Cherie Chan
Christopher Westling
Erica Petrofsky
Joshua Litwin
Narissa Jimenez-Petchumrus
Tory Francisco
Special Thanks
Bruce Kaneshiro
Edward Randolph
Jill Walker
Simon Baker
Terrie Prosper
CPUC California Solar Initiative Annual Program Assessment
June 2021 iii
Table of Contents
1 Executive Summary ........................................................................................................... 6
1.1 Key Report Contents ............................................................................................................. 7
1.1.1. Installed Solar Highlights ..................................................................................................................... 7
1.1.2. CSI General Market Program Highlights .......................................................................................... 9
1.1.3. Other Program Highlights ................................................................................................................. 10
1.1.4. Net Energy Metering (NEM) ............................................................................................................ 14
2 Introduction ..................................................................................................................... 15
2.1 CSI Program Components ................................................................................................... 15
2.2 CSI Program Budget ............................................................................................................ 17
2.3 CSI Program Regulatory Process ......................................................................................... 18
3 Solar Projects Installed in California Through 2020 ........................................................ 19
3.1 Investor-Owned Utility Territory Solar Installations ........................................................... 19
3.2 Net Energy Metering ........................................................................................................... 21
3.2.1. NEM 1.0 Program Cap ...................................................................................................................... 21
3.2.2. NEM Successor Tariff ....................................................................................................................... 22
3.2.3. Revisiting the NEM Successor Tariff .............................................................................................. 23
3.3 Consumer Protections ......................................................................................................... 23
4 CSI Program Components ............................................................................................... 25
4.1 General Market Solar Program ............................................................................................ 25
4.1.1. General Market Program Background ............................................................................................ 25
4.1.2. General Market Program Progress ................................................................................................... 26
4.2 CSI Low-Income PV Solar Programs.................................................................................. 28
4.2.1. Single-Family Affordable Solar Homes (SASH) Program ........................................................... 28
4.2.2. Multifamily Affordable Solar Housing (MASH) Program ........................................................... 33
4.2.3. Summary of CSI Low-Income Program Participation ................................................................. 37
4.3 Virtual Net Energy Metering (VNEM) .............................................................................. 38
4.4 Other PV Solar Programs .................................................................................................... 38
4.4.1. Solar on Multifamily Affordable Housing (SOMAH) Program .................................................. 38
4.4.2. Disadvantaged Communities Single-family Solar Homes (DAC-SASH) Program .............. 40
4.4.3. Disadvantaged Communities Green Tariff (DAC-GT) Program ........................................... 42
4.4.4. Community Solar Green Tariff (CSGT) Program ......................................................................... 42
4.5 CSI Thermal Program ......................................................................................................... 43
4.5.1. CSI Thermal Program Background and Overview ....................................................................... 43
4.5.2. CSI Thermal Budget ........................................................................................................................... 45
4.5.3. CSI Thermal Program Participation ................................................................................................ 48
4.5.4. CSI Thermal Measurement and Evaluation (M&E) ..................................................................... 50
4.6 Research, Development, Demonstration, & Deployment .................................................. 50
CPUC California Solar Initiative Annual Program Assessment
June 2021 iv
4.6.1. RD&D Program Background ........................................................................................................... 50
4.6.2. RD&D Program Evaluation ............................................................................................................. 51
5 Program Reporting and Evaluation ................................................................................ 53
5.1 Program Reporting ............................................................................................................. 53
5.1.1. CSI General Market Reporting ......................................................................................................... 53
5.1.2. CSI Thermal Reporting ...................................................................................................................... 54
5.1.3. Periodic CSI and CSI Thermal Reports .......................................................................................... 55
5.2 Program Evaluations ........................................................................................................... 55
6 CSI Program Links and Contact Information ................................................................. 58
CPUC California Solar Initiative Annual Program Assessment
June 2021 v
List of Tables
Table i: CSI Budget by Program Component .............................................................................................. 10
Table ii: Summary of CSI Low-Income Program Participation ................................................................ 12
Table iii: CSI Thermal Installed Projects by Sector and Displaced Fuel through 2020 ........................ 13
Table 1: CSI Budget by Program Component ............................................................................................ 17
Table 2: CSI General Market MW Targets by Utility and Customer Class ............................................. 26
Table 3: Incentive MW Available by Step, Program Administrator, and Customer Class ................... 27
Table 4: SASH 1.0 Budget Allocations by IOU Service Territory ........................................................... 29
Table 5: SASH 1.0 Budget Allocations by Functions ................................................................................. 29
Table 6: SASH 2.0 Budget Allocations by IOU Service Territory ........................................................... 29
Table 7: SASH 2.0 Budget Allocations by Functions ................................................................................. 30
Table 8: MASH 1.0 Budget Allocations by IOU Service Territory .......................................................... 34
Table 9: MASH 1.0 Budget Allocations by Function ................................................................................. 34
Table 10: MASH 2.0 Budget Allocations by IOU Service Territory ........................................................ 34
Table 11: MASH 2.0 Budget Allocations by Function ............................................................................... 34
Table 12: MASH 2.0 Incentive Tracks ......................................................................................................... 35
Table 13: MASH Program Progress .............................................................................................................. 37
Table 14: Summary of CSI Low-Income Program Participation ............................................................. 37
Table 15: VNEM Projects Outside of the MASH Program by Utility Territory through 2020 .......... 38
Table 16: SOMAH Program Incentive Rate by Tax Credit Funding and Tenant/Common Area
Allocation .......................................................................................................................................................... 39
Table 17: DAC-SASH Budget Allocations by IOU Service Territory ..................................................... 41
Table 18: DAC-SASH Budget Allocations by Functions .......................................................................... 41
Table 19: CSI Thermal Gas-Displacing Budget Allocation ....................................................................... 45
Table 20: CSI Thermal Gas-Displacing 2018-2020 Incentive Budget Allocation .................................. 45
Table 21: CSI Thermal Gas-Displacing Overall Program Budget, 2018-2020 ....................................... 46
Table 22: Natural Gas-Displacing CSI Thermal General Market Incentive Steps, 2018-2020 ............ 47
Table 23: Natural Gas-Displacing Industrial CSI Thermal Incentive Rate ............................................. 47
Table 24: CSI Thermal Low-income Program 2018-2020 Budget Allocation ....................................... 48
Table 25: CSI Thermal Low-income/DAC Incentive Rate ...................................................................... 48
Table 26: CSI Thermal Installed Projects by Sector and Displaced Fuel through 2020 ....................... 49
Table 27: CSI Thermal Applications by Program Administrator through 2020 .................................... 49
Table 28: CSI RD&D Final Budget Allocations ......................................................................................... 51
CPUC California Solar Initiative Annual Program Assessment
June 2021 6
1 Executive Summary
In January 2007, California launched the Go Solar California campaign, a multi-entity $3.3
billion ratepayer-funded effort to install 3,000 megawatts (MW) of new distributed solar over the
next decade and transform the market for solar energy by reducing the cost of solar generating
equipment. The portion of the solar effort overseen by the California Public Utilities
Commission (CPUC) is known as the California Solar Initiative (CSI) program. The CSI
program components are the General Market program, Single-family Affordable Solar Homes
program (SASH); Multifamily Affordable Solar Housing program (MASH); CSI Thermal
program; CSI Thermal Low-income program; and Research, Development and Demonstration
(RD&D) program. All components except for SASH and MASH closed by the end of 2020.
The CSI program goal was to install 1,940 MW
1
of customer-sited solar capacity, and, along with
other statewide solar programs, transition the solar industry to a point where it could be self-
sustaining without subsidies. The market for solar generating equipment in California grew at a
rapid pace from the beginning of the CSI program and has continued to grow since the program
closed. California installed enough solar capacity to achieve the CSI General Market Program
goal of installing 1,750 MW of capacity prior to December 2016. By the end of 2020,
approximately 9,671 MW of customer-sited solar projects had been installed at over 1.1 million
locations within the service territories of the state’s three major investor-owned utilities (IOU).
This total, which is almost five times the CSI program goal, includes 29.7 MW of capacity under
the SASH program and 53.5 MW of capacity under the MASH program.
This Annual Program Assessment meets the statutory requirement for a yearly report to the
Legislature on the progress of the CSI program.
2
This Assessment also discusses the newer Solar
on Multifamily Affordable Housing (SOMAH) and Disadvantaged Communities Single-family
Solar Homes (DAC-SASH) programs which are separate from the CSI program but similarly
provide incentives for the installation of behind-the-meter solar. New front-of-meter alternatives
including the Disadvantaged Communities Green Tariff (DAC-GT) and the Community Solar
Green Tariff (CSGT) programs are also described. With the general market for customer-sited
solar in California thriving and the upcoming sunset of the SASH and MASH programs, the
CPUC is placing its emphasis on promoting equity of access to solar power through the
SOMAH, DAC-SASH, DAC-GT, and CSGT programs.
1
This goal includes the CSI General Market Program goal of installing 1,750 MW of capacity by the end of 2016.
2
Public Utilities Code Section 913.7 states, “On or before June 30, 2009, and by June 30
th
of every year thereafter,
the CPUC shall submit to the Legislature an assessment of the success of the California Solar Initiative Program.”
All CSI Annual Program Assessments, beginning with the 2009 report, are available at
cpuc.ca.gov/General.aspx?id=3747.
CPUC California Solar Initiative Annual Program Assessment
June 2021 7
Other state authorized programs, including the New Solar Homes Partnership (NSHP) and
publicly owned utilities’ solar offerings, are not discussed in this Assessment, although the solar
capacity installed under the NSHP is included in the totals reported here.
3
1.1 Key Report Contents
This report contains current information on distributed solar energy systems in the large IOU
4
service territories in California. It includes detailed information on program participation,
installed capacity, equipment costs, and program impacts for all the CSI program components,
including the General Market program, SASH program; the MASH program; the CSI Thermal
program; the CSI Thermal Low-income program; and the RD&D program. This report also
includes information on net energy metering (NEM) and other relevant policy updates. Unless
stated otherwise, all data is accurate as of December 31, 2020.
5
1.1.1. Installed Solar Highlights
Through the end of 2020, approximately 9,671 MW of solar capacity was installed at
1,103,288 customer sites in the large IOU territories.
6
This exceeds the state’s goal Go Solar
California of 3,000 MW by roughly 322 percent.
In 2020, 1,345 MW was installed in the IOU territories, a 13 percent increase in annual
installed capacity compared to 2019.
3
Information on non-CPUC jurisdictional solar programs is available at gosolarcalifornia.ca.gov.
4
The large IOUs under the CPUC’s regulatory jurisdiction are Pacific Gas and Electric Company (PG&E).
Southern California Edison Company (SCE), San Diego Gas & Electric Company (SDG&E), and Southern
California Gas Company (SoCalGas).
5
Please note that some subtotals in this report do not add up to their respective totals due to rounding.
6
California DG Statistics at californiadgstats.ca.gov
CPUC California Solar Initiative Annual Program Assessment
June 2021 8
Figure i: Customer-Sited Solar MW Installed Capacity in CA’s IOU Territories, 1993-
2020 (MW)
Source: California DG Statistics Interconnected Project Sites Data Set (californiadgstats.ca.gov), updated February 28, 2021. Year
defined by date of interconnection application approval. Notes: Data includes all solar PV systems interconnected under Rule 21
within PG&E, SCE, and SDG&E service territories. Data does not include systems within POU territories.
CPUC California Solar Initiative Annual Program Assessment
June 2021 9
Figure ii: Number of Installed Customer-Sited Solar Projects in CA's IOU Territories,
1993-2020 (thousands)
Source: California DG Statistics Interconnected Project Sites Data Set (californiadgstats.ca.gov), updated February 28, 2021. Year
defined by date of interconnection application approval. Notes: Data includes all solar PV systems interconnected under Rule 21
within PG&E, SCE, and SDG&E service territories. Data does not include systems within POU territories.
1.1.2. CSI General Market Program Highlights
The CSI General Market program, which closed to new applications on December 31, 2016,
exceeded its goal of installing 1,750 MW by the end of 2016. As of December 31, 2018, the
CSI General Market Program had installed 1,935 MW.
7
,
8
Pacific Gas and Electric Company (PG&E), Southern California Edison Company (SCE),
and San Diego Gas & Electric Company (SDG&E)
9
installed enough solar capacity for both
their residential and non-residential (commercial, industrial, government, non-profit, and
agricultural properties) CSI customer classes to exceed their installation goals.
As the CSI General Market Program is now closed, NEM and the Federal Investment Tax
Credit are the primary financial drivers of customer-sited solar generation.
7
CSI Working Dataset, (californiadgstats.ca.gov/downloads). Data accessed April 29, 2020.
8
The overall MW totals exceed the 1,750 MW CSI goal due to additional CSI incentive funding that was authorized
in SB 585. This funding was authorized as a result of different rebates being offered to taxable and non-taxable
entities, which caused CSI budgeting uncertainty. See CPUC Decision (D.)11-12-019 for more details.
9
The Center for Sustainable Energy (CSE) administered the CSI Program in SDG&E’s service territory.
CPUC California Solar Initiative Annual Program Assessment
June 2021 10
1.1.3. Other Program Highlights
Table i: CSI Budget by Program Component
Program Component
Budget
10
($ millions)
General Market Solar Program (includes PV and
electric-displacing solar thermal technologies)
$2,098
Single-family Affordable Solar Homes (SASH)
$108
Multifamily Affordable Solar Housing (MASH)
$108
Research, Development, Demonstration, and
Deployment (RD&D)
$50
Solar water heating Pilot Program (SWHPP)
12
$2.6
Sub-Total: CSI Electric-Displacing Budget
$2,367
CSI Thermal Program (Gas-Displacing)
$250
Total CSI Budget
$2,617
Re-authorized SASH Program
$54
Re-authorized MASH Program
$54
Total CSI Budget including re-authorized
SASH/MASH programs
$2,724
Notes: D.06-12-033 established a 1,750 MW goal for the General Market Program and a 1,940 MW goal for the overall program.
D.10-01-022 established the CSI Thermal Program pursuant to Assembly Bill 1470. D.11-12-019 approved an extra $200 million
of funding for the General Market program. D.15-01-027 reauthorized $108 million in additional funds for the CSI low-income
programs and adopted a 50 MW low-income capacity goal separate from the CSI goals established in SB 1 (Murray, 2006).
Single-Family Affordable Solar Homes (SASH)
o Since the program was launched in 2008 through December 2020, SASH has
completed a total of 9,422 projects, representing 29.7 MW of installed capacity on
eligible homes.
14
o The original $92 million SASH incentive budget was fully expended in all IOU
territories. In 2015, the CPUC extended the SASH program, with nearly $46 million
in additional incentive funding authorized.
15
10
Total budget over life of program.
11
The CPUC decisions on MASH and SASH did not explicitly adopt a 95 MW per program goal; however, the
CPUC did adopt a total CSI program goal of 1,940 MW in D.06-12-033.
12
The SWHPP was a pilot program that preceded the CSI Thermal Program and is now closed.
13
AB 797 (Irwin, 2017).
14
These numbers include both SASH 1.0 and SASH 2.0 projects. A more detailed breakdown between the original
SASH 1.0 program and reauthorized SASH 2.0 program can be found in Section 4.2.1.
15
Decision 15-01-027.
CPUC California Solar Initiative Annual Program Assessment
June 2021 11
o Through December 2020, SASH applicants have received or reserved a total of
$42.5 million of the available $45.9 million incentive budget authorized for the
extended SASH program. There are 145 SASH projects in progress or under review,
with a total capacity of 0.53 MW. The SASH program is still accepting new
applications in SCE’s service area, while funds are fully reserved in the PG&E and
SDG&E service areas.
o Since the SASH third-party ownership (TPO) model was made available in 2015
through December 2020, about 83 percent of SASH 2.0 capacity installed use the
TPO model to finance the installation of solar photovoltaic (PV) systems for low-
income customers at no cost to the SASH participants. More information on the
SASH TPO Model is provided in Section 4.2.1.1.3.
Multifamily Affordable Solar Housing (MASH)
o Since the program was launched in 2008, 574 MASH projects have been completed,
equaling 53.5 MW of installed capacity as of December 2020. There are an
additional 97 MASH projects in progress or under review, with a total pending
capacity of 18.9 MW.
16
o MASH applicants have received or reserved 100 percent of the original $95 million
MASH incentive budget.
o Due to project cancellations and adjustments to incentive claims, SCE and PG&E
briefly reopened their MASH Programs for new applications. SDG&E’s MASH
program continued to be closed as its program budget is fully subscribed. All
MASH projects must be completed no later than October 31, 2021, as the MASH
program will close on December 31, 2021.
16
These numbers include both MASH 1.0 and MASH 2.0 projects. A more detailed breakdown between the
original MASH 1.0 program and reauthorized MASH 2.0 program can be found in Section 4.2.2.
CPUC California Solar Initiative Annual Program Assessment
June 2021 12
Table ii: Summary of CSI Low-Income Program Participation
Program
Number of
Completed
Projects
17
Total Paid
Incentives
($ millions)
Total Installed
Capacity (MW)
SASH 1.0
5,266
92.08
16.0
SASH 2.0
4,158
40.91
13.6
MASH 1.0
379
86.82
27.4
MASH 2.0
195
33.30
26.1
Total
9,998
253.11
83.1
Sources: MASH: CSI Low-Income Solar PV working data set as of December 31, 2020. SASH: Single-family Affordable
Solar Homes (SASH) Program Semi-Annual Progress Report, GRID Alternatives, January 2021. Available at
gridalternatives.org/sites/default/files/SASH%20semiannual%20report_Q3-4%2C%202020%20FINAL%201.30.21.pdf.
All system capacity measured in CEC-AC PTC MW.
Newer non-CSI programs that incentivize behind-the-meter solar
o SOMAH The Solar on Multifamily Affordable Housing (SOMAH) program
provides financial incentives for installing solar PV systems on multifamily
affordable housing. SOMAH has an overall target to install 300 MW by 2030.
Eligible properties include multifamily affordable housing in the PG&E, SCE,
SDG&E, Liberty Utilities, and PacifiCorp utility territories. Funded through utility
greenhouse gas (GHG) allowance auction proceeds from California’s cap-and-trade
program, SOMAH has a program budget of up to $100 million annually through
June 30, 2026.
The SOMAH program began accepting applications on July 1, 2019. With much
anticipation, the SOMAH program received more than 200 applications on the first
day it opened, and waitlists were started in the PG&E, SCE, and SDG&E
territories. By the end of 2020, 406 applications with 71.4 MW of capacity had been
submitted into the program, with participation in all five SOMAH-eligible IOU
territories. Because each IOU territory’s annual incentive budget varies based on
their specific GHG allowance auction proceeds, the SOMAH Program
Administrator (PA) maintains five individual reservation queues and up to five
waitlist queues. In April 2020, the Commission directed the utilities to continue
funding the SOMAH program through 2026.
o DAC-SASH The Disadvantaged Communities Single-Family Solar Homes
(DAC-SASH) program was created in June 2018 through CPUC Decision (D.)18-
06-027, and it launched in fall 2019. DAC-SASH provides $3.00/watt incentives for
solar installations on owner-occupied, single-family homes located in disadvantaged
17
Figures represent only completed projects and do not include pending applications.
CPUC California Solar Initiative Annual Program Assessment
June 2021 13
communities. All participants in DAC-SASH must be income-eligible for either the
California Alternate Rates for Energy (CARE) program or the Family Electric Rate
Assistance (FERA) program. By the end of 2020, 705 DAC-SASH projects had
been installed, providing nearly 3.3 MW of capacity.
CSI Thermal Program
o From January 2010 to December 2020, the program approved 11,757 applications
for natural gas-displacing solar thermal systems for $162 million in incentives
dispersed or reserved out of the available $250 million CSI Thermal budget.
o In 2017, Assembly Bill (AB) 797 (Irwin) authorized the CSI Thermal program to
continue operation from January 1, 2018 to July 31, 2020. Although the overall
budget was kept at $250 million, AB 797 mandated the allocation of 50% of the CSI
Thermal budget to low-income residential housing or building in disadvantaged
communities (DAC).
18
Table iii: CSI Thermal Installed Projects by Sector and Displaced Fuel through 2020
Customer Class
Number of
Applications
Total
Incentives
($ thousands)
Total Project
Costs
($ thousands)
Total Annual
Energy Savings
(therms)
Commercial Pools (Gas)
878
$12,614
$20,802
2,094,881
Commercial/
Multifamily Residential
1,293
$55,027
$101,011
3,030,927
Industrial
1
$753
$825
37,284
Single Family Residential
3,418
$16,341
$29,113
602,873
Multifamily low-
income/DAC
1,248
$48,053
$89,975
2,170,125
Single-Family low-
income/DAC
4,919
$29,215
$25,124
680,181
Total
11,757
$162,003
$266,850
8,616,271
$ per Therm
-
$18.80
$30.97
-
Source: CSI Thermal Program Data (californiadgstats.ca.gov), accessed April 15, 2021.
Research, Development, Demonstration, and Deployment (RD&D) Program
o The CSI RD&D Program conducted five project solicitations, resulting in grant
funding for 37 projects, totaling $41.2 million. Funded projects focused on the
following areas:
Integration of solar PV into the electricity grid
18
The CSI Thermal program defines disadvantaged communities as a community identified by the California
Environmental Protection Agency pursuant to Section 39711 of the Health and Safety Code.
CPUC California Solar Initiative Annual Program Assessment
June 2021 14
Energy generation technologies and business development
Grid integration and production technologies
o The CSI RD&D Program (which focused primarily on CSI General Market) closed
on December 31, 2016. All solicitations and projects are now complete.
19
o In December 2016, Itron, Inc., the CSI RD&D Program Manager, completed the
RD&D Program Report, 2008-2016, which provides an overview of the program’s
solicitation process and briefs on the projects funded.
20
1.1.4. Net Energy Metering (NEM)
In January 2016, the CPUC approved D.16-01-044 adopting a NEM successor tariff (NEM
2.0), which continued the existing NEM structure with adjustments to align the costs of
NEM successor customers more closely with those of non-NEM customers. The NEM
successor tariff went into effect in SDG&E’s service territory on June 29, 2016, in PG&E’s
service territory on December 15, 2016, and in SCE’s service territory on July 1, 2017. The
program provides customer-generators full retail rate credits for energy exported to the grid
and requires them to pay an interconnection fee and non-bypassable charges to align NEM
customer costs more closely with non-NEM customer costs.
The Decision on NEM consumer protections (D.18-09-044) authorized ratepayer funding
for a consultant to conduct a formal and independent evaluation of the NEM successor
tariff to analyze the costs and benefits of customer-sited renewable resources taking service
on the tariff and its variants. The evaluation was issued on January 21, 2021. It examined the
effects of the tariff and it will also assist the CPUC in its review of NEM 2.0.
The CPUC opened a new rulemaking, R.20-08-020, in August 2020 in order to develop a
successor to existing NEM 2.0 tariffs pursuant to the requirements of California Assembly
Bill 327 (2013, Perea). The R.20-08-020 proceeding is expected to conclude by early 2022.
21
19
Final reports and individual research briefs for all projects funded under the CSI RD&D Program can be found at
calsolarresearch.ca.gov/final-project-reports.
20
See:
calsolarresearch.ca.gov/images/stories/documents/Prog_Report/CSI_RDD_ProgramReport_ResearchBriefs_201
70131.pdf
21
Information on this rulemaking is available at cpuc.ca.gov/nemrevisit.
CPUC California Solar Initiative Annual Program Assessment
June 2021 15
2 Introduction
The CSI Program is the solar incentive program for the large California IOUs: PG&E, SCE, and
SDG&E, plus SoCalGas exclusively for the CSI Thermal program. Over the years, the CSI
program has promoted customer adoption of solar PV and solar thermal technologies through
financial incentives. Through various components of the program, existing residential homes, as
well as commercial, industrial, government, non-profit, and agricultural properties within the
service territories of the large electric and gas IOUs have been eligible for CSI program
participation.
22
All components for non-residential customers were closed by August 2020. The
goals of the CSI program are to:
Install 1,940 MW of distributed solar generation capacity in the large electric IOU service
territories, and displace 585 million therms of natural gas usage, or the equivalent output
of 200,000 solar thermal systems; and
Transform the market for solar energy systems to be price competitive and self-
sustaining.
The CSI program focuses exclusively on customer-sited solar energy systems used to offset
some or all onsite energy consumption. Solar PV systems funded by the program reduce the
customer's electricity consumption from the grid, while solar thermal systems reduce the
customer's natural gas consumption. The CSI program does not fund wholesale solar power
plants, which are designed to serve the electric grid and contribute to the state’s Renewables
Portfolio Standard (RPS) requirement.
23
The electricity generated by CSI systems, however,
indirectly contributes to California’s RPS by reducing demand when serving customer load. In
addition, the owner of the CSI system owns the renewable energy credits associated with the
system’s generation and may sell the credits to retail sellers to contribute to the RPS targets.
2.1 CSI Program Components
The CSI program has several components, with a Program Administrator (PA) for each large
IOU territory. The CSI budget is overseen by the CPUC. The CSI program components are:
The CSI General Market Solar Program, which closed on December 31, 2016,
provided incentives for residential and non-residential PV systems from one kilowatt
22
The electric-displacing portion of the CSI Program, which covers solar PV and some solar thermal systems, was
authorized by the CPUC in a series of regulatory decisions between 2006 and 2011. In addition, the Legislature
expressly authorized the CPUC to create the CSI Program in 2006 in SB 1 (Murray, 2006). The gas-displacing solar
thermal portion of the CSI was authorized by the Legislature in AB 1470 (Huffman, 2007) and implemented by the
CPUC in early 2010 after the required evaluation of a pilot program in the San Diego area.
23
See SB 2 (2011).
CPUC California Solar Initiative Annual Program Assessment
June 2021 16
(kW) to one megawatt (MW) in capacity. The General Market PAs were PG&E, SCE,
and the Center for Sustainable Energy (CSE) in SDG&E’s territory. The goal of the
program was to incentivize 1,750 MW of customer-side solar capacity using a 10-year
budget of $2.1 billion for incentives and program administration.
The CSI Single-Family Affordable Solar Homes (SASH) Program provides solar
incentives to qualifying single-family, low-income households. The SASH program is
administered through a statewide Program Manager, GRID Alternatives. The original
SASH program had a budget of $108 million and the reauthorized SASH program has a
budget of $54 million. The SASH program offers job training to volunteers and
workforce development participants and offers competitive opportunities for solar
installers through a subcontractor program.
The CSI Multifamily Affordable Solar Housing (MASH) Program provides solar
incentives to multifamily low-income housing facilities. The original MASH program had
a budget of $108 million and the reauthorized MASH program has a budget of $54
million. The MASH program is administered by PG&E, SCE, and CSE (in SDG&E’s
service territory). By the end of 2018, PG&E, SCE and CSE’s MASH Programs were
fully subscribed within each respective service territory, and their waitlists were closed to
new applications. In 2019-2020, project cancellations and adjustments to incentive claims
in SCE’s and PG&E’s MASH programs made funds available for new projects, which
have since been reserved. SDG&E’s MASH program did not reopen as its program
budget was fully subscribed. All MASH projects must be completed no later than
October 31, 2021, as the MASH program will close on December 31, 2021.
The CSI Research, Development, Demonstration and Deployment (RD&D)
Program, which closed on December 31, 2016, had a budget of $50 million and
provided grants to develop and deploy solar technologies with the ability to advance the
overall goals of the CSI program, including achieving targets for capacity, cost, and a
self-sustaining solar industry in California. Itron Inc. served as the Program Manager.
The CSI Thermal Program, which closed on July 31, 2020, provided incentives to
eligible solar thermal technologies including solar water heating (SWH) systems. PG&E,
SoCalGas, and CSE administered the $250 million CSI Thermal Program for gas-
displacing solar thermal systems. The CSI Thermal program consisted of three customer
classes: single-family residential, multifamily/commercial, and solar pool heating.
Additionally, there were separate low-income programs for the single-family residential
and multifamily/commercial customer classes. The CSI Thermal program provided up
to $100.8 million to electric-displacing solar thermal systems through a carve-out
component of the CSI General Market budget, which closed on December 31, 2016.
CPUC California Solar Initiative Annual Program Assessment
June 2021 17
2.2 CSI Program Budget
The CSI program has two funding streams to incentivize solar technology used for electricity
generation and for displacing natural gas consumption. The electric portion of the CSI program
originally had a 10-year budget of $2.4 billion, collected from electric ratepayers as authorized by
SB 1 (Murray, 2006). AB 217 (Bradford, 2013) extended the CSI low-income programs with
$108 million in new funding, to continue until the incentives are exhausted or until the end of
2021, whichever is earlier. CSI Thermal, the natural gas-displacing portion of the CSI program,
was funded by AB 1470 (Huffman, 2007), which authorized $250 million in incentives for solar
thermal technologies to be collected from gas ratepayers through 2017.
Table 1: CSI Budget by Program Component
Program Component
Budget
24
($ millions)
Goal
General Market Solar Program (includes PV and
electric-displacing solar thermal technologies)
$2,098
1,750 MW
Single-family Affordable Solar Homes (SASH)
$108
95 MW
25
Multifamily Affordable Solar Housing (MASH)
$108
95 MW
25
Research, Development, Demonstration, and
Deployment (RD&D)
$50
N/A
Solar water heating Pilot Program (SWHPP)
26
$2.6
750 systems
Sub-Total: CSI Electric-Displacing Budget
$2,367
1,940 MW
CSI Thermal Program (Gas-Displacing)
$250
Cost effective deployment of solar
thermal systems to reduce natural
gas consumption in California.
27
Total CSI Budget
$2,617
-
Re-authorized SASH Program
$54
15 MW
Re-authorized MASH Program
$54
35 MW
Total CSI Budget including re-authorized
SASH/MASH programs
$2,724
-
Notes: CPUC D.06-12-033 established a 1,750 MW goal for the General Market Program and a 1,940 MW goal for the overall
program. D.10-01-022 established the CSI Thermal Program pursuant to AB 1470. D.11-12-019 approved an extra $200 million
of funding for the General Market program. D.15-01-027 reauthorized $108 million in additional funds for the CSI low-income
programs and adopted a 50 MW low-income capacity goal separate from the CSI goals established in SB 1 (Murray, 2006).
24
Total budget over life of program.
25
The CPUC decisions on MASH and SASH did not explicitly adopt a 95 MW per program goal; however, the
CPUC did adopt a total CSI program goal of 1,940 MW in D.06-12-033.
26
The SWHPP was a pilot program that preceded the CSI Thermal Program and is now closed.
27
AB 797 (Irwin, 2017).
CPUC California Solar Initiative Annual Program Assessment
June 2021 18
In most cases, the budgets are allocated across the IOUs in proportion to their annual electric
sales: PG&E at 43.7 percent, SCE at 46 percent, and SDG&E at 10.3 percent.
Budget updates for the CSI Thermal incentive buckets are available online at csithermalstats.org.
The online reports provide each program’s capacity goals, original dollar allocations, and
capacity and dollars confirmed, under review, and remaining. The sites also break down the CSI
dollars confirmed, under review, and paid, according to the type of project and customer class.
In 2015, the CPUC and PAs transitioned solar project data collection from CSI to the NEM
interconnection process per CPUC Decision (D.)14-11-001, which mandated a more
comprehensive database of solar installations given that the CSI General Market incentives were
exhausted. The solar data collected through the NEM interconnection process is now
downloadable from the California DG Statistics website at californiadgstats.ca.gov.
2.3 CSI Program Regulatory Process
Between 2006 and 2019, the CPUC adopted a number of regulatory decisions to implement the
CSI program, as well as various CSI program components.
28
Previous versions of this report
contain lists of the most significant CSI program decisions. Rules and procedures for the CSI
program have been developed and modified within the now closed Rulemaking (R.)12-11-005.
Any future policy determinations for the SASH and MASH programs will be addressed in R.20-
05-012.
In addition to formal regulatory decisions, the CPUC and CSI PAs have made numerous CSI
program changes based on regular informal feedback from program stakeholders and in
response to issues that arise during program implementation. To gather feedback on the
program, the CSI PAs have hosted quarterly public CSI program forums to discuss potential
program changes with stakeholders.
The PAs periodically file requests with the CPUC to change program rules. These requests are
referred to as advice letters and are consistent with the CPUC-established CSI Program
Handbook process. The advice letters are processed by CPUC staff in accordance with General
Order 96-B.
29
As a result, the CPUC has revised and reissued the CSI Program Handbook
30
numerous times since the program first began.
28
The CPUC has developed the CSI Program in a series of Rulemakings (R.) since 2006, including R.08-03-008 and
R.06-03-004, with precedents from earlier proceedings such as R.04-03-017. Each of the decisions noted herein
occurs in one of those dockets, unless otherwise noted.
29
See General Order 96-B here: cpuc.ca.gov/generalorders
30
See CSI Program Handbook here: cpuc.ca.gov/General.aspx?id=5367
CPUC California Solar Initiative Annual Program Assessment
June 2021 19
3 Solar Projects Installed in California Through 2020
This section of the report summarizes data on the cumulative installed capacity
31
and number of
customer-sited solar projects installed in California IOU territories. The data includes solar
projects interconnected under any of the IOU non-wholesale solar programs, including CSI,
New Solar Homes Partnership (NSHP), Emerging Renewables Program (ERP), and the Self-
Generation Incentive Program (SGIP). IOU data does not include solar projects installed in
publicly owned utility (POU) areas, such as Los Angeles Department of Water and Power or
Sacramento Municipal Utility District, nor does it include data from multi-jurisdictional utilities,
such as Pacific Power’s former California Solar Incentive Program (CSIP).
32
3.1 Investor-Owned Utility Territory Solar Installations
Through the end of 2020, approximately 9,671 MW of solar capacity were installed at 1,103,288
sites in the large IOU territories.
33
The solar installations included in Figures 1 and 2 are
interconnected on customer sites under Rule 21, the CPUC-jurisdictional interconnection tariff,
and do not include solar power plants installed under FERC-jurisdictional interconnection tariffs
that participate in CAISO markets. They do not include data on installations in POU territories.
This data set excludes systems that were decommissioned after being interconnected.
Figure 1 shows the amount of solar capacity installed by customers by year in IOU territories. In
2020, customers installed 1,345 MW of solar, a 13 percent increase in annual installed capacity
compared to 2019.
31
All data in this assessment are for grid-tied solar PV (i.e. interconnected to the utility grid), unless otherwise
noted. All solar in this report is customer-side of the meter self-generation designed to serve onsite load. All
references to capacity are reported in “CEC-AC” units, which is the industry standard for net electricity output in
MW based on the California Energy Commission’s Alternating Current rating of solar panels. The “CEC-AC”
rating tends to be slightly less than the nameplate capacity.
32
Previous CSI Annual Program Assessments included data from POUs in order to provide a statewide overview of
solar project installations. This year’s Annual Program Assessment excludes such data because the California Energy
Commission stopped collecting POU data at the end of 2018.
33
Source: California DG Statistics Interconnected Project Sites Data Set (californiadgstats.ca.gov), accessed
February 28, 2021.
CPUC California Solar Initiative Annual Program Assessment
June 2021 20
Figure 1: Customer-Sited Solar MW Installed Capacity in CA’s IOU Territories, 1993-
2020 (MW)
Source: California DG Statistics Interconnected Project Sites Data Set (californiadgstats.ca.gov), updated February 28, 2021. Year
defined by date of interconnection application approval. Notes: Data includes all solar PV systems interconnected under Rule 21
within PG&E, SCE, and SDG&E service territories. Data does not include systems within POU territories.
Figure 2 shows the number of installations by year. There were 145,608 solar projects installed in
the IOU territories in 2020, approximately the same number as in 2019.
CPUC California Solar Initiative Annual Program Assessment
June 2021 21
Figure 2: Number of Installed Customer-Sited Solar Projects in CA's IOU Territories,
1993-2020 (thousands)
Source: California DG Statistics Interconnected Project Sites Data Set (californiadgstats.ca.gov), updated February 28, 2021. Year
defined by date of interconnection application approval. Notes: Data includes all solar PV systems interconnected under Rule 21
within PG&E, SCE, and SDG&E service territories. Data does not include systems within POU territories.
3.2 Net Energy Metering
The vast majority of solar customers are enrolled in NEM (NEM 1.0) or NEM Successor (NEM
2.0) tariffs, established under Public Utilities Code Sections 2827 and 2827.1, respectively. The
NEM program supports onsite renewable energy (mostly solar, in practice) installations designed
to offset a portion, or all, of the customer’s electrical energy usage. Under NEM, customers
receive a bill credit (in dollars) based on the retail rate (including generation, transmission, and
distribution rate components) for any excess generation (in kWh) that is exported back to the
grid. In periods when a customer’s bill is negative (because the amount of energy the solar
system exported to the grid exceeded the amount of energy consumed by the customer), the bill
credits are carried forward up to one year, at which point customers may elect to receive net
surplus compensation for any electricity produced in excess of on-site energy usage.
3.2.1. NEM 1.0 Program Cap
Pursuant to AB 327 (Perea, 2013), every large electrical corporation was required to make a
NEM tariff available to eligible customer-generators until July 1, 2017, or the date when a utility
CPUC California Solar Initiative Annual Program Assessment
June 2021 22
reached its 5 percent NEM program cap.
34
The three large IOUs hit their respective caps in
2016 and 2017.
AB 327 also directed the CPUC to establish a transition period for customers enrolled in the
NEM 1.0 program, and to adopt a successor tariff or contract to NEM by December 31, 2015.
In March 2014, the CPUC adopted Decision (D.)14-03-041, establishing a 20-year transition
period for customers to remain on NEM 1.0 tariffs.
35
Specifically, the Decision established a
transition period of 20 years, beginning the year the system was interconnected, during which
participating systems may continue to take service under NEM 1.0.
3.2.2. NEM Successor Tariff
In January 2016, the CPUC approved D.16-01-044 adopting a NEM successor tariff (NEM 2.0)
that continues the existing NEM structure while making adjustments to align the costs of NEM
2.0 customers more closely with those of non-NEM customers. The Decision added a number
of new elements to the NEM tariff, including the following:
NEM 2.0 customers with systems under 1 MW
36
pay a pre-approved one-time
interconnection fee, based on each IOU’s historic interconnection costs. The fee is $75
to $132 depending upon the IOU. NEM 2.0 customers with systems 1 MW and larger
must pay all interconnection costs.
NEM 2.0 customers must pay non-bypassable charges on each kWh of electricity they
consume from the grid in each metered interval.
All residential NEM 2.0 customers must take service on an available time-of-use rate.
Customers were eligible to continue enrolling in the NEM 1.0 tariff until July 2017 or the date, if
earlier, when their utility reached its NEM 1.0 program cap. The NEM 2.0 tariff went into effect
in SDG&E’s service territory on June 29, 2016, in PG&E’s service territory on December 15,
2016, and in SCE’s service territory on July 1, 2017.
A very small number of customer-generators, especially those whose systems are unlikely to
export generation to the electric grid, opt to take utility service under a non-NEM tariff. Less
34
The NEM program cap is reached when the total installed NEM capacity exceeds 5% of the total non-coincident
peak demand of every customer within an IOU’s territory.
35
See docs.cpuc.ca.gov/PublishedDocs/Published/G000/M089/K386/89386131.PDF.
36
The Decision extends eligibility for the NEM successor tariff to eligible systems larger than 1 MW in size,
however these customers are required to pay all Rule 21 interconnection study and distribution system upgrade fees
for the facility.
CPUC California Solar Initiative Annual Program Assessment
June 2021 23
than one percent (0.11 percent) of customer-sited solar installations in the IOU territories do not
take service under a NEM tariff.
3.2.3. Revisiting the NEM Successor Tariff
On August 27, 2020, the Commission initiated Rulemaking (R.) 20-08-020 to develop a
successor to the NEM 2.0 tariff, as part of its commitment in D.16-01-044 to review the current
tariff. The Order Instituting Rulemaking (OIR) stated that “[p]ursuant to the requirements of
Assembly Bill (AB) 327, this successor will be a mechanism for providing customer-generators
with credit or compensation for electricity generated by the renewable facilities that a) balances
the costs and benefits of the renewable electrical generation facility and b) allows customer-sited
renewable generation to grow sustainably among different types of customers and throughout
California’s diverse communities.
In this proceeding, the CPUC will determine what program elements and features to include in a
successor to the current NEM tariff, as well as a timeline for implementation of the new tariff,
using proposals and information provided by parties to the proceeding as input. The CPUC may
also address issues related to current NEM tariffs and subtariffs, which include but are not
limited to the virtual NEM tariffs, NEM aggregation tariff, Renewable Energy Self-Generation
Bill Credit Transfer program, and NEM fuel cell tariff. Finally, the CPUC will consider
additional or enhanced consumer protections for customers taking service under NEM and/or
the successor to NEM 2.0 tariff.
In late 2020, the CPUC issued a scoping memo and ruling directing comments on proposed
guiding principles for the new rulemaking. Party comments and reply comments were accepted
on proposed guiding principles for the proceeding in December 2020. The proceeding is
scheduled to conclude by early 2022.
37
3.3 Consumer Protections
The CSI General Market Program had a number of built-in consumer protections. In the CSI
Program, incentives were based on actual or expected performance, which were determined
through standardized calculators. This approach incentivized systems to be designed for optimal
production and required that this information be disclosed to consumers, providing
transparency on the performance of the system. Additionally, all equipment was required to have
a 10-year manufacturer performance warranty, and system performance monitoring was required
for most systems. Contractors were also required to have a valid CSLB license and were required
37
Information on this rulemaking is available at cpuc.ca.gov/nemrevisit.
CPUC California Solar Initiative Annual Program Assessment
June 2021 24
to submit a “high cost justification and acknowledgement form” to consumers if costs were
unusually high.
With the sunset of the CSI General Market Program, the CPUC acknowledged the need to
consider what consumer protection elements should be carried forward for NEM customers.
The NEM Successor Tariff Decision, D.16-01-044, continued some of the CSI General Market
Program consumer protections for NEM 2.0. Under NEM 2.0, a solar provider must provide a
minimum 10-year warranty, or service agreement on all equipment or installation, and all major
solar system components must be on the verified equipment list maintained by the CEC. The
Decision also directed Energy Division staff, in collaboration with stakeholders, to consider
further NEM consumer protection measures including a solar information packet for
consumers.
In 2018, the CPUC adopted D.18-09-044, which established a process for creating a solar
information packet for consumers. The packet has been created and is called the Solar
Consumer Protection Guide.
38
The Decision also requires that solar providers upload three new
documents before interconnecting a residential NEM customer to the grid in the large IOU
territories: the solar installation contract, a signed copy of a CPUC Solar Consumer Protection
Guide, and a signed copy of the CSLB Solar Disclosure Document. In February 2020, the
CPUC adopted D.20-02-011, which further strengthened the provisions of D.18-09-044 by
mandating an audit trail when customers sign the Solar Consumer Protection Guide
electronically and authorized the creation of a citation program to address non-compliant solar
providers. In August 2020, the CPUC adopted D.20-08-001, which adopted standardized inputs
and assumptions for calculating estimated electric utility bill savings from residential solar energy
systems.
38
The Solar Consumer Protection Guide may be accessed at cpuc.ca.gov/solarguide.
CPUC California Solar Initiative Annual Program Assessment
June 2021 25
4 CSI Program Components
The overarching CSI program contains multiple program components, or sub-programs. These
include incentive programs targeting solar electric technologies: CSI General Market, SASH, and
MASH. The CSI Thermal program provided incentives for solar thermal technologies that
displace natural gas usage. These programs are discussed in more detail below.
4.1 General Market Solar Program
4.1.1. General Market Program Background
The CSI General Market solar program, the largest CSI program component, closed to new
applications on December 31, 2016. The program’s incentive budgets for each IOU territory
were exhausted by 2015. The program offered incentives to all eligible customer-sited solar
electric generating (typically PV) systems in the large IOU service territories.
39
The CSI General
Market program achieved a total of 1,935 MW of installed capacity.
40
Pursuant to D.16-12-055,
the CSI General Market program closed in all service territories on December 31, 2019.
41
Table 2 presents the capacity target by utility territory and customer class, showing how all the
incentives were originally allocated over the expected 10-step life of the program. Actual
allocations by step varied due to dropouts and other factors.
39
The “loading order” was introduced in the Energy Action Plan, which was jointly adopted in 2003 by the CPUC,
the CEC and the California Power Authority. The loading order is a list of preferred energy resources - the first of
which is energy efficiency.
40
CSI Working Dataset (californiadgstats.ca.gov/downloads/#_li). Data accessed April 29, 2020.
41
See the 2020 CSI Annual Program Assessment for information on the general market incentive types, incentive
levels, targets by program administrator and customer type, and applications received per year. Previous reports are
available at cpuc.ca.gov/General.aspx?id=6043.
CPUC California Solar Initiative Annual Program Assessment
June 2021 26
Table 2: CSI General Market MW Targets by Utility and Customer Class
Step
MW in Step
PG&E (MW)
SCE (MW)
SDG&E (MW)
Res
Non-Res
Res
Non-Res
Res
Non-Res
1
50
--
--
--
--
--
--
2
70
10.1
20.5
10.6
21.6
2.4
4.8
3
100
14.4
29.3
15.2
30.8
3.4
6.9
4
130
18.7
38.1
19.7
40.1
4.4
9.0
5
160
23.1
46.8
24.3
49.3
5.4
11.0
6
190
27.4
55.6
28.8
58.6
6.5
13.1
7
215
31.0
62.9
32.6
66.3
7.3
14.8
8
250
36.1
73.2
38.0
77.1
8.5
17.3
9
285
41.1
83.4
43.3
87.8
9.7
19.7
10
350
50.5
102.5
53.1
107.9
11.9
24.2
Subtotals
(Res and Non-Res)
252.4
512.3
265.6
539.5
59.5
120.8
Totals
764.7
805.1
180.3
Percent
43.7%
46.0%
10.3%
Source: D.06-12-033, Appendix B, Table 11. Notes: The MWs for Incentive Step 1 were reserved under the Self-Generation
Incentive program in 2006. Non-Residential (Non-Res) includes commercial, government, and non-profit facilities.
Once the incentives reserved for each customer class within a utility territory reached the
capacity target for a given step, the incentive level offered dropped to the next lower step.
4.1.2. General Market Program Progress
All six General Market customer classes exceeded their capacity targets. Table 3 denotes the
amount of MW that were completed in each step, compared to the original number of MW
allocated to the step by D.06-12-033. The "Actual" MW numbers are equal to the "Original"
MW numbers minus dropouts from previous steps.
CPUC California Solar Initiative Annual Program Assessment
June 2021 27
Table 3: Incentive MW Available by Step, Program Administrator, and Customer Class
Source: CSI General Market Program Administrators, April 2019. Note: Incentive Step 1 MWs were reserved under the Self-
Generation Incentive Program in 2006.
4.1.2.1 CSI Program Impact on Solar PV Market Transformation
One of the goals of the CSI program was to create a self-sustaining solar PV market in
California. In 2013, the CPUC hired Navigant Consulting, Inc. to evaluate the extent of the
transformation of California’s customer-side solar PV market since the adoption of the CSI
program, and to assess the degree to which the customer-side solar PV market would be
sustainable after the CSI General Market sunset.
42
The study, released in April 2014, found:
The customer-side solar PV market had shown significant progress toward market
transformation since the initiation of the CSI program;
While other regulatory and global market factors played an important role, the CSI
program had an indispensable role in transforming the solar PV market in California,
especially in creating a long-term policy signal to in-state suppliers of customer-sited
solar PV products and services; and
The long-term sustainability of the solar PV market in California would depend on NEM
2.0 regulation and the retail rate reform process that was under consideration before the
CPUC in 2014 and 2015.
The final CSI Impact Evaluation of program years 2011-2016 was released in January 2021.
43
42
See cpuc.ca.gov/WorkArea/DownloadAsset.aspx?id=7699.
43
See the 2020 CSI Annual Program Assessment for additional information on installed system costs, the numbers
of installations using CSI and not using CSI, and the size of CSI incentives, versus other incentives, in the later years
of the program.
Original Actual Original Actual Original Actual Original Actual Original Actual Original Actual
1 50 - - - - - - - - - - - -
2 70 10.1 11.8 20.5 12.3 10.6 9.2 21.6 15.3 2.4 2.2 4.8 7
3 100 14.4 12.9 29.3 22.6 15.2 14.1 30.8 23.9 3.4 3.2 6.9 4.3
4 130 18.7 18 38.1 29.6 19.7 19.3 40.1 19.5 4.4 4.2 9.0 5.2
5 160 23.1 22.7 46.8 56.8 24.3 22.1 49.3 68.6 5.4 5.1 11.0 14.6
6 190 27.4 26 55.6 71.9 28.8 23.7 58.6 36.7 6.5 5.7 13.1 9
7 215 31.0 27.2 62.9 55.5 32.6 30.9 66.3 58.6 7.3 6.6 14.8 14
8 250 36.1 35.8 73.2 60.3 38.0 40.6 77.1 96.7 8.5 9.2 17.3 24.8
9 285 41.1 41.2 83.4 69.3 43.3 42.0 87.8 80.2 9.7 10 18.9 18.6
10 350 50.5 61.3 102.5 123.1 53.1 105.4 107.9 174.6 36.9 46.3 8.2 9.1
Step
MW
in
Step
PG&E
(MW)
SCE
(MW)
CSE in SDG&E Territory
(MW)
Residential
Non-Residential
Non-Residential
Residential
Residential
Non-Residential
CPUC California Solar Initiative Annual Program Assessment
June 2021 28
The CPUC adopted a NEM 2.0 policy in January 2016. The new policy retained most of the
elements of the original NEM policy, with adjustments to require customers to pay a small
interconnection fee, non-bypassable charges assessed on all energy consumed from the grid, and
a requirement that residential customers go on a time-of-use rate. The CPUC found that
continuing NEM with these changes was likely to allow customer-sited renewable distributed
generation to continue to grow sustainably. NEM 2.0 is currently in effect in all three major IOU
service territories.
4.2 CSI Low-Income PV Solar Programs
4.2.1. Single-Family Affordable Solar Homes (SASH) Program
4.2.1.1 SASH Program Background
The SASH program, one of the two low-income components of the CSI program, provides
incentives for solar PV systems for eligible low-income owners of existing homes. The CPUC
approved the SASH program in November 2007 in D.07-11-047 as part of the CSI program.
GRID Alternatives (GRID) was selected as the statewide Program Manager for the SASH
program.
44
GRID is a non-profit organization providing renewable energy services, equipment,
and training in low-income communities throughout California since 2001. As Program Manager
for the SASH program, GRID identifies eligible low-income households, markets the SASH
program, and installs PV systems for eligible SASH participants.
45
In January 2015, pursuant to AB 217 (Bradford, 2013), the CPUC reauthorized the SASH
program in D.15-01-027. In this Decision, the CPUC authorized the extension of SASH with an
additional $54 million in funding and an installed capacity goal for the program of 15 MW. The
SASH program is reauthorized through 2021, or until all available incentives are encumbered,
whichever occurs first. The reauthorized SASH program opened in May 2015.
The SASH program is designed to be a comprehensive low-income solar program. In addition
to providing incentives to install PV systems, SASH is structured to promote or provide energy
efficiency services, opportunities for workforce development and green jobs training, and broad
community engagement with low-income communities. To achieve this, the SASH program
provides consumer education on solar and energy efficiency technologies to the diverse
volunteer base that contributes to SASH installations. This outreach helps further the broader
44
D.07-11-045 ordered the SASH Program to be administered by a single statewide program manager to “ensure
consistency and equity in program delivery statewide while working with a diverse group of stakeholders and service
providers.” (p. 45, Conclusion of Law 10). GRID was selected through a competitive solicitation process.
45
For more information about the SASH Program, including GRID’s latest quarterly program status report, see:
cpuc.ca.gov/general.aspx?id=3043. For more details on the SASH program’s rules and requirements, see Appendix
D to the CSI Handbook, available at: cpuc.ca.gov/workarea/downloadasset.aspx?id=4585.
CPUC California Solar Initiative Annual Program Assessment
June 2021 29
goals of promoting the use of PV-solar technology statewide and helping build broad-based
community support for solar electric technologies and energy efficiency. In addition, GRID sub-
contracts with qualified solar contractors to install SASH projects through the SASH Sub-
Contractor Partnership Program (SPP).
For clarity in this report, the original SASH program is referred to as SASH 1.0 and the 2015
reauthorization of the SASH program is referred to as SASH 2.0. At the time of this report,
SASH 1.0 incentive funding is fully encumbered in all three IOU service territories and SASH
2.0 incentive reservations are winding down. PG&E and SDG&E transitioned to SASH 2.0 in
January 2015 and SCE transitioned in October 2015.
4.2.1.1.1
SASH Program Budget
The SASH 1.0 budget was $108.3 million, allocated according to the information in Table 4 and
Table 5.
Table 4: SASH 1.0 Budget Allocations by IOU Service Territory
Utility
PG&E
SCE
SDG&E
Total
Percentage
43.7%
46.0%
10.3%
100%
Total Budget ($ millions)
$47.3
$49.8
$11.2
$108.3
Source: D.07-11-045
Table 5: SASH 1.0 Budget Allocations by Functions
Function
Allocation
Administration
10%
Marketing and Outreach
4%
Measurement and Evaluation
1%
Incentives
85%
Source: D.07-11-045
The SASH 2.0 budget is $54 million, allocated as described in Table 6 and Table 7.
Table 6: SASH 2.0 Budget Allocations by IOU Service Territory
Utility
PG&E
SCE
SDG&E
Total
Percentage
43.7%
46.0%
10.3%
100%
Total Budget ($ millions)
$23.60
$24.84
$5.56
$54
Source: D.15-01-027
CPUC California Solar Initiative Annual Program Assessment
June 2021 30
Table 7: SASH 2.0 Budget Allocations by Functions
Function
Allocation
Administration
10%
Marketing and Outreach
4%
Measurement and Evaluation
1%
Incentives
85%
Source: D.15-01-027
4.2.1.1.2
SASH Program Eligibility
The SASH program is open to low-income customers of the large electric IOUs who live in
owner-occupied single-family homes that meet the definition of low-income housing established
in Public Utilities Code Section 2852. This code section allows owner-occupied residences that
are part of a larger multifamily complex to qualify under certain conditions. GRID has created a
statewide database of eligible homes in collaboration with the California Housing Partnership
Corporation (CHPC). This database is instrumental in the effort to establish relationships and
identify resources within targeted local jurisdictions.
4.2.1.1.3
SASH Program Incentives
The SASH incentives are higher than the CSI General Market program on a dollar per watt
basis. The SASH 1.0 incentives varied depending on the household’s income level and eligibility
for the California Alternate Rates for Energy (CARE)
46
program. The SASH 2.0 incentives are
set at the same level for all SASH customers. The SASH 1.0 and 2.0 incentive rates do not
decline over time like the incentive rate in the market-transforming CSI General Market
program.
Under SASH 1.0, eligible participating households were provided a one-time payment under the
CSI EPBB structure to help reduce the up-front cost of installation. The SASH 1.0 program had
one fully-subsidized (i.e. covers the full installed cost of the system) and six highly-subsidized
incentive payment levels based on the applicant’s income relative to the area median income
(AMI), tax liability, and eligibility for the CARE program.
SASH 2.0 provides incentives at $3.00/watt to all customers whose total household income is
below 80 percent of the AMI. Eligible participating households are provided a one-time
payment under the CSI EPBB structure to help reduce the up-front cost of installations.
However, due to the significant reduction in funding for SASH 2.0 compared to SASH 1.0, and
in acknowledgement of the maturation of the market for third-party financed products, the
CPUC authorized GRID to develop and utilize a Third-Party Ownership (TPO) Model for
46
CARE provides a minimum 20 percent discount on the energy bills of qualifying low-income customers.
CPUC California Solar Initiative Annual Program Assessment
June 2021 31
SASH to help finance the installation of solar PV projects for low-income customers at no cost
to SASH participants. The SASH TPO model has been deliberately designed to maximize
household savings and include ironclad consumer protection measures as required in D.15-01-
027.
47
Through this unique “families-first” TPO model, GRID is able to leverage the Federal
Investment Tax Credit to help finance SASH 2.0 projects, while providing additional benefits to
participating families, including a performance guarantee, system monitoring, and 20-year
warranty coverage.
The SASH TPO model is playing a significant role in funding SASH 2.0 projects. Of the 4,158
SASH 2.0 projects completed through the end of 2020, 3,128 are third-party owned, or roughly
80 percent of all projects installed under SASH 2.0.
48
4.2.1.2 SASH Program Progress
Since the SASH program launched in 2008, it has experienced substantial growth in program
applications and made significant progress in key areas, including: expanding the SPP; increasing
marketing and outreach efficiency; building partnerships with volunteers and job-
training/workforce programs; and broadening the affordable housing client database.
Under SASH 1.0, a total of 5,266 projects and over 16 MW have been installed on eligible
homes, and 100 percent of the available $92 million SASH 1.0 incentive budget has been
encumbered.
49
As of December 31, 2020, SASH 2.0 has completed a total of 4,158 projects,
resulting in 13.6 MW of installed capacity, with another 0.53 MW currently in progress. These
applicants have received or reserved $42.5 million of the available $46 million SASH 2.0
incentive budget for their residential solar systems.
50
Nearly all the completed SASH installations were made at no cost to homeowners. In addition
to ratepayer funding, GRID leveraged funding from local jurisdictions, project sponsorships,
and GRID’s non-profit fundraising. Since the SASH incentive does not cover 100 percent of
installation costs and homeowners are largely unable to fund the additional incremental costs,
identifying gap financing from third-party sources has been critical to achieving the long-term
47
Resolution E-4719, June 15, 2015, and D.15-01-027, Minimum Consumer Protection standards for SASH TPO
model, at pgs. 52-53. D.15-01-027 online at
docs.cpuc.ca.gov/PublishedDocs/Published/G000/M145/K938/145938475.PDF.
48
Single-family Affordable Solar Homes (SASH) Program Semi-Annual Progress Report, GRID Alternatives,
January 2021. Available at gridalternatives.org/sites/default/files/SASH%20semiannual%20report_Q3-
4%2C%202020%20FINAL%201.30.21.pdf.
49
SASH Program data as of December 31, 2020 available at: californiadgstats.ca.gov/downloads/#_li.
50
Single-family Affordable Solar Homes (SASH) Program Semi-Annual Progress Report, GRID Alternatives,
January 2021. Available at gridalternatives.org/sites/default/files/SASH%20semiannual%20report_Q3-
4%2C%202020%20FINAL%201.30.21.pdf.
CPUC California Solar Initiative Annual Program Assessment
June 2021 32
goals of SASH. The approved TPO model will continue to play a key role in funding SASH 2.0
projects.
4.2.1.2.1
SASH Workforce Development Efforts
The SASH program is uniquely structured to provide workforce development and job-training
opportunities at every installation. In implementing the SASH program, GRID provides
opportunities for job trainees and local volunteers to assist with installations, engage their
communities, and participate in solar and energy efficiency programs. These volunteer and job-
training opportunities help strengthen California’s solar industry by imparting broad consumer
education and providing a means for individuals from diverse backgrounds to learn about PV-
solar design and installation through hands-on experience.
51
GRID partners with more than 80 California job-training programs to incorporate GRID’s
volunteer-based installation projects into their construction training curricula. GRID dedicates
approximately 20 percent of its installations for these trainees to gain hands-on experience with
real-world solar installations that have conditions and requirements comparable to what they
would encounter in private industry. This provides a double benefit to the low-income
community since many solar job trainees reside in the same neighborhoods that the SASH
Program aims to serve. GRID has created over 84,500 installation workday positions for
volunteers in California since the inception of the SASH program through 2020, and over
19,000 of these positions have been filled by students from California job training programs.
52
SASH continues its workforce development efforts under SASH 2.0, with additional data
collection and reporting requirements associated with the SASH 2.0 program.
Under both SASH 1.0 and SASH 2.0, the SASH Sub-contractor Partnership Program (SPP)
provides opportunities for licensed California contractors to participate in SASH installations.
Qualified contracting companies agree to a reduced cost model and commit to hiring at least one
eligible job trainee for each SASH installation. Though the SASH program requires contractors
to hire a minimum of one eligible job trainee per installation, over 15 percent of SASH SPP
projects have exceeded this expectation by having more two or even three trainees work on the
SASH installations. Through 2020, over 54 California contractors have installed projects under
51
Promotion of economic and workforce development opportunities as is done in the SASH program aligns with
California policies such as the CPUC Environmental and
Social Justice Action Plan and directives in Executive Orders N-79-20 and N-19-19. See
cpuc.ca.gov/uploadedFiles/CPUCWebsite/Content/News_Room/NewsUpdates/2020/MOU%20with%20CWD
B%20on%20ESJ%2010-29-2020.pdf.
52
An installation workday is a standard 8-hour workday. GRID’s installations typically span 2 days and consist of
teams of approximately 8-10 individual volunteers or job trainees each day.
CPUC California Solar Initiative Annual Program Assessment
June 2021 33
the SASH SPP model, and the SPP program has created 2,350 paid workday opportunities for
266 recent graduates of job-training programs.
4.2.2. Multifamily Affordable Solar Housing (MASH) Program
4.2.2.1 MASH Program Background
The second low-income CSI program targets affordable multifamily housing. In October 2008,
the CPUC adopted D.08-10-036, which established the $108.3 million MASH program for solar
installations on existing multifamily affordable housing that meet the definition of low-income
residential housing established in Public Utilities Code Section 2852.
53
The MASH program was
designed to operate until January 1, 2016, or until all funds available from the program’s
incentive budget were allocated, whichever occurred first.
In January 2015, pursuant to AB 217 (Bradford, 2013), the CPUC reauthorized the MASH
program through D.15-01-027. In this Decision, the CPUC authorized the extension of MASH
with an additional $54 million in funding and a 35 MW installed capacity goal for the program.
The MASH program is reauthorized through 2021, or until all available incentives are
encumbered, whichever occurs first.
The goals of the MASH program are to:
a) stimulate adoption of solar power in the affordable housing sector;
b) improve energy utilization and overall quality of affordable housing through application
of solar and energy efficiency technologies;
c) decrease electricity use and costs without increasing monthly household expenses for
affordable housing building occupants;
d) increase awareness and appreciation of the benefits of solar among affordable housing
occupants and developers.
For clarity in this report, the original MASH program is referred to as MASH 1.0 and the
reauthorization of the MASH program is referred to as MASH 2.0. By the end of 2013, MASH
1.0 incentive funding was fully encumbered in all three IOU service territories. The CPUC
authorized the MASH Program Administrators to implement MASH 2.0 in each service territory
upon complete subscription of the incentive funding in that service territory, and CPUC
approval of an advice letter implementing the new program rules. The MASH program
Administrators began implementation of MASH 2.0 in all three IOU service territories in August
2015, when the CPUC approved the MASH 2.0 rules.
53
D.08-10-036, Appendix A, mimeo., p. 1.
CPUC California Solar Initiative Annual Program Assessment
June 2021 34
By the end of 2018, PG&E, SCE and CSE’s MASH Programs were fully subscribed within each
respective service territory, and their waitlists were closed to new applications. In 2020, SCE
and PG&E briefly reopened their MASH programs for new applications to account for earlier
project cancellations and adjustments to incentive claims. The MASH 1.0 budget was $108.3
million, allocated as described in Table 8 and Table 9.
Table 8: MASH 1.0 Budget Allocations by IOU Service Territory
Utility
PG&E
SCE
SDG&E
Total
Percentage
44%
46%
10%
100%
Total Budget ($ millions)
$47.3
$49.8
$11.2
$108.3
Source: D.08-10-036.
Table 9: MASH 1.0 Budget Allocations by Function
Function
Allocation
Administration and Marketing and Outreach
10%
Measurement and Evaluation
2%
Incentives
88%
Source: D.08-10-036.
The MASH 2.0 budget is $54 million, allocated according to the information in Table 10 and
Table 11.
Table 10: MASH 2.0 Budget Allocations by IOU Service Territory
Utility
PG&E
SCE
SDG&E
Total
Percentage
43.7%
46.0%
10.3%
100%
Total Budget ($ millions)
$23.60
$24.84
$5.56
$54
Source: D.15-01-027
Table 11: MASH 2.0 Budget Allocations by Function
Function
Allocation
Administration and Marketing and Outreach
6%
Measurement and Evaluation
1%
Incentives
93%
Source: D.15-01-027
4.2.2.1.1
MASH Program Eligibility
The MASH program is open to multifamily affordable housing properties that meet the
definition of “low-income residential housing” per Public Utilities Code Section 2852, which
requires that at least 20 percent of the onsite tenants are low-income. The MASH program also
CPUC California Solar Initiative Annual Program Assessment
June 2021 35
provides eligibility for certain pre-identified tenant units to enroll with their utility’s VNEM
tariffs, as described in the VNEM section below.
In implementing the new energy efficiency and job training policy requirements of AB 217
(Bradford, 2013), the CPUC required that, to be eligible for MASH 2.0, MASH properties must
conduct an energy efficiency walkthrough audit, and must provide a job training opportunity for
up to five trainees per MASH system installation.
4.2.2.1.2
MASH Program Incentives
Due to reduced funding levels for the MASH 2.0 program compared to the MASH 1.0 program,
the CPUC reduced the incentive levels for both the common area and tenant load incentive
tracks. The CPUC renamed the new incentive levels Track 1C and 1D. The CPUC also created
an additional requirement that, in order to receive the higher incentive level for tenant load, a
MASH project would have to allocate generation to MASH property tenants by utilizing VNEM
to share bill credits and guarantee that the tenants would retain at least 50 percent of the
economic benefits of the generation allocated to them. Table 12 below displays the MASH 2.0
incentive tracks, 1C and 1D, and the eligibility requirements for MASH 2.0.
Table 12: MASH 2.0 Incentive Tracks
Track
Incentive
Amount
Eligibility Requirements
1C: PV System
Offsetting
Common Area
Load, Non-
VNEM Tenant
Load, or VNEM
Tenant Load with
<50 percent
Tenant Benefit
$1.10/watt
Provide job training opportunity to more than one
trainee, with one additional trainee for each 10 kW up
to 50 kW
Conduct onsite walkthrough energy audit at American
Society of Heating, Refrigerating, Air-Conditioning
Engineers (ASHRAE) Level I or higher, or enroll in a
utility, Regional Energy Network (REN), Community
Choice Aggregator (CCA) or federally-provided
whole-building multifamily energy efficiency program
Portion of system allocated to offsetting one of the
following:
o Common Area Load
o Non-VNEM Tenant Load
o VNEM Tenant Load where tenant receives
less than 50 percent of economic benefit of
allocated generation
CPUC California Solar Initiative Annual Program Assessment
June 2021 36
Track
Incentive
Amount
Eligibility Requirements
1D: PV System
Offsetting
VNEM Tenant
Load with ≥50
percent Tenant
Benefit
$1.80/watt
Provide job training opportunity to more than one
trainee, with one additional trainee for each 10 kW up
to 50 kW
Conduct onsite walkthrough energy audit at ASHRAE
Level I or higher, or enroll in a utility, REN, CCA, or
federally provided whole-building multifamily energy
efficiency program
Portion of PV system allocated to offsetting:
o VNEM Tenant Load where tenant receives at
least 50 percent of economic benefit of
allocated generation
4.2.2.2 MASH Program Progress and Project Attributes
As the MASH program nears its sunset, the progress of the program has been measured in
terms of reserved projects reaching completion and waitlisted projects being brought into the
incentive reservation queue when additional funds are made available via system resizing and
project dropouts. By the end of 2018, PG&E, SCE and CSE’s MASH Programs were fully
subscribed within each respective service territory, and their waitlists were closed to new
applications. In 2019-2020, project cancellations and adjustments to incentive claims in SCE and
PG&E’s MASH programs made funds available for new projects. On March 2, 2020, SCE
reopened its MASH Program for new applications with a remaining budget of roughly $6.6M.
Shortly thereafter, on April 24, 2020, SCE closed its program as those remaining funds were
fully subscribed. In PG&E service territory, the program reopened on August 10 with roughly
$12.4M available for potential projects and closed on August 21, 2020. SDG&E’s MASH
program did not reopen as its program budget has remained fully subscribed.
There were 379 projects, representing 27.4 MW of installed capacity, completed under MASH
1.0. Through the end of 2020, 195 projects representing 26.1 MW of capacity have been
completed under MASH 2.0. There are an additional 97 MASH 2.0 applications, representing
18.9 MW, currently under review.
54
54
Data as of December 31, 2020 from California DG Stats Low-Income Solar PV Data Set available at:
californiadgstats.ca.gov/downloads/#_li
CPUC California Solar Initiative Annual Program Assessment
June 2021 37
Table 13: MASH Program Progress
Status of Application
CSE
PG&E
SCE
Total
MASH 1.0
Completed
Projects
41
191
147
379
Capacity (MW)
2.6
11.3
13.5
27.4
MASH 1.0
Pending
Projects
0
0
0
0
Capacity (MW)
0.0
0.0
0.0
0
MASH 2.0
Completed
Projects
23
89
83
195
Capacity (MW)
3.7
10.6
11.9
26.1
MASH 2.0
Pending
Projects
1
65
31
97
Capacity (MW)
0.4
11.7
6.9
18.9
Source: CSI Low-Income Solar PV working data set as of December 31, 2020.
All system capacity measured in CEC-AC PTC MW.
Between 2006 and 2020, the MASH program paid an average of $2,244 in incentives per
kilowatt installed. The General Market program paid an average of $965 per kilowatt installed.
55
4.2.3. Summary of CSI Low-Income Program Participation
Table 14: Summary of CSI Low-Income Program Participation
Program
Number of
Completed
Projects
56
Total Paid
Incentives ($
millions)
Total Installed
Capacity (MW)
SASH 1.0
5,266
92.08
16.0
SASH 2.0
4,158
40.91
13.6
MASH 1.0
379
86.82
27.4
MASH 2.0
195
33.30
26.1
Total
9,998
253.11
83.10
Sources: MASH: CSI Low-Income Solar PV working data set as of December 31, 2020. SASH: Single-family Affordable Solar
Homes (SASH) Program Semi-Annual Progress Report, GRID Alternatives, January 2021. Available at
gridalternatives.org/sites/default/files/SASH%20semiannual%20report_Q3-4%2C%202020%20FINAL%201.30.21.pdf.
All system capacity measured in CEC-AC PTC MW.
55
California DG Stats Low-Income Solar PV Statistics and Charts (californiadgstats.ca.gov/charts/li) and
California Solar Initiative Statistics and Charts (californiadgstats.ca.gov/charts/csi). Installed capacity based on CEC
PTC Rating.
56
Figures represent only completed projects and do not include pending applications.
CPUC California Solar Initiative Annual Program Assessment
June 2021 38
4.3 Virtual Net Energy Metering (VNEM)
Multi-tenant buildings have been a challenging segment for solar PV adoption due to the
problem of distributing the benefits of system output among individually metered occupants. To
help address this issue, the CPUC directed the IOUs to file tariffs for VNEM in 2008.
57
Under VNEM, the utility meters the PV system’s output, then allocates energy credits for the
energy produced by the PV system to the building owners’ and/or tenants’ individual utility
accounts, based on a pre-arranged allocation agreement. The MASH program piloted the
VNEM tariffs. The original intent of VNEM was to help low-income multifamily residents
receive direct benefits of a building’s solar system.
Based on the merits of these tariffs, the CPUC expanded VNEM to all multi-tenant, multi-meter
properties in 2011 and included all NEM-eligible technologies for eligibility. As of the end of
2020, in PG&E, SCE, and SDG&E’s service territory there were 651 projects with a total of
over 54 MW of solar capacity on the VNEM tariff who are not participants in the MASH
program.
Table 15: VNEM Projects Outside of the MASH Program by Utility Territory through
2020
Utility
PG&E
SCE
SDG&E
Total
VNEM Projects outside of MASH Program
328
81
242
651
Total Capacity (kW, CEC-AC)
35,539
5,648
12,946
54,133
Source: Data request to IOUs, April 2020.
4.4 Other PV Solar Programs
4.4.1. Solar on Multifamily Affordable Housing (SOMAH) Program
AB 693 (Eggman, 2015) established the Multifamily Affordable Housing Solar Roofs Program,
with up to $100,000,000 annually in funding from shares of greenhouse gas (GHG) allowance
auction proceeds from PG&E, SDG&E, SCE, Liberty Utilities Company, and PacifiCorp
(collectively the investor-owned utilities or IOUs). The program provides incentives for the
installation of solar distributed generation projects sited on existing multifamily affordable
housing.
On December 22, 2017, the CPUC issued Decision (D.)17-12-022 establishing the Solar on
Multifamily Affordable Housing (SOMAH) Program. The SOMAH Program, while similar to
57
CPUC Decision (D.)08-10-036.
CPUC California Solar Initiative Annual Program Assessment
June 2021 39
the MASH program, is a new program, established to provide upfront incentives to install 300
MW of solar on multifamily affordable housing in the service territories of IOUs by 2030.
Pursuant to direction in the authorizing decision, a competitive solicitation for a statewide
program administrator was held and a team consisting of the Center for Sustainable Energy
(CSE), GRID Alternatives (GRID), the Association for Energy Affordability (AEA), and the
California Housing Partnership Corporation (CHPC) was selected.
SOMAH provides fixed, upfront, capacity-based incentives for qualifying solar energy systems
using the Expected Performance Based Buydown (EPBB) methodology. The EPBB incentive
payment relies on verified solar energy system characteristics such as location, system size,
shading, and orientation. The SOMAH incentive value depends on the capacity of the installed
system, the energy percentage split between tenant and common area serving load, and the other
funding resources that the project may leverage, such as the Federal Investment Tax Credit
(ITC) and Low-income Housing Tax Credits (LIHTC).
The incentive levels are reduced annually by the lesser of either five percent or an amount based
on the National Renewable Energy Lab’s cost analysis (whichever is less).
Table 16: SOMAH Program Incentive Rate by Tax Credit Funding and
Tenant/Common Area Allocation
Tax Credits
$ per AC Watt Incentive
ITC
LIHTC
Tenant
Common
2019-2020
2020-2021
2019-2020
2020-2021
Yes
No
$3.20
$3.04
$1.10
$1.04
No
Yes
$2.25
$2.14
$0.80
$0.76
Yes
Yes
$2.25
$2.14
$0.80
$0.76
Source: calsomah.org/costs-incentives
On October 1, 2018, the SOMAH Program Administrator filed two Tier 3 Advice Letters
including the SOMAH Program Handbook and Program Implementation Plan. Both Advice
Letters were approved with minor modifications on March 28, 2019 in Resolution E-4987.
58
The SOMAH program began accepting applications on July 1, 2019. With much anticipation,
the SOMAH program opened with more than 200 applications received on day one, and
waitlists were started in PG&E, SCE and SDG&E territories. By the end of 2020, 406
applications with 71.4 MW of capacity had been submitted into the program, with participation
in all five SOMAH-eligible IOU territories.
59
Because each IOU territory’s annual incentive
58
Resolution E-4987: docs.cpuc.ca.gov/SearchRes.aspx?docformat=ALL&DocID=279170414
59
SOMAH Semi-Annual Progress Report: July 1, 2020 Dec. 31, 2020. Available at
cpuc.ca.gov/General.aspx?id=6442461609.
CPUC California Solar Initiative Annual Program Assessment
June 2021 40
budget varies based on their specific GHG allowance auction proceeds, the SOMAH Program
Administrator maintains five individual reservation queues and up to five waitlist queues. On
April 23, 2020, the Commission issued D.20-04-012 that determined there is adequate
participation and interest in SOMAH program, and that revenues continue to be available for
the program. The Decision authorized continued allocation of funds to the SOMAH program
through June 30, 2026. In May 2020, the SOMAH program received its next round of incentive
funding via the approval of the IOUs’ Energy Resource Recovery Account (ERRA)/Energy
Cost Adjustment Clause (ECAC) applications. On June 5, 2020 ED issued Resolution E-5054,
which approved revisions to the SOMAH Program Handbook to limit participation of a
photovoltaic (PV) project to either the SOMAH Program or the MASH Program. On
December 22, 2020, Energy Division disposed of CSE's Advice Letter 118-E-A that updates the
SOMAH Program Handbook to implement an optional two-payment incentive structure that
may be selected in preference to the existing single incentive payment structure.
4.4.2. Disadvantaged Communities Single-family Solar Homes
(DAC-SASH) Program
Although solar adoption and investment has increased throughout the state, participation in
disadvantaged communities (DAC) has lagged. To address this gap, AB 327 (Perea, 2013)
directed the CPUC to develop “specific alternatives designed for growth among residential
customers in disadvantaged communities.”
On June 22, 2018, the CPUC issued D.18-06-027 Adopting Alternatives to Promote Solar
Distributed Generation in Disadvantaged Communities, which created three new programs to
improve access to renewable generation for residential customers in DACs, pursuant to AB 327.
D.18-06-027 defined DACs, for the purpose of the programs created, as census tracts that are
among the top 25 percent most impacted census tracts statewide using CalEnviroScreen 3.0
scoring, plus 22 additional census tracts that do not have an overall ranking but score among the
highest five percent of CalEnviroScreen’s Pollution Burden category. Of the three programs
created, one is for behind-the-meter solar: the DAC Single-family Solar Homes (DAC-SASH)
program.
The DAC-SASH program is modeled largely after the SASH program and provides participants
the same $3.00/watt incentive that was established for the SASH 2.0 program. DAC-SASH also
allows for the use of a Third-Party Ownership model as long as it complies with the minimum
Consumer Protection Standards established for SASH.
60
Unlike SASH, DAC-SASH does not
require participants to live in low-income housing as defined in Public Utilities Code Section
60
Resolution E-4719, June 15, 2015, and D.15-01-027, Minimum Consumer Protection standards for SASH TPO
model, at pgs. 52-53. D.15-01-027 online at
docs.cpuc.ca.gov/PublishedDocs/Published/G000/M145/K938/145938475.PDF.
CPUC California Solar Initiative Annual Program Assessment
June 2021 41
2852. Instead, DAC-SASH participants must be eligible for either the California Alternate Rates
for Energy (CARE) program or the Family Electric Rate Assistance (FERA) program and must
live in owner-occupied, single-family homes located in DACs as defined by D.18-06-027. As of
January 1, 2021 homeowners are also eligible if they reside in “California Indian Country,” as a
result of D.20-12-003. This Decision was in response to GRID’s 2020 petition to modify the
program that, among other things, requested the inclusion of tribes in addition to DACs as the
geographic threshold.
61
D.18-06-027 established an annual budget of $10 million for DAC-SASH beginning in 2019 and
continuing through 2030. It adopted the same budget allocations established for SASH, as
shown below.
Table 17: DAC-SASH Budget Allocations by IOU Service Territory
Utility
PG&E
SCE
SDG&E
Total
Percentage
43.7%
46.0%
10.3%
100%
Total Budget 2019-2030 ($ millions)
$52.44
$55.20
$12.36
$120
Source: D.18-06-027
Table 18: DAC-SASH Budget Allocations by Functions
Function
Allocation
Administration
10%
Marketing and Outreach
4%
Measurement and Evaluation
1%
Incentives
85%
Source: D.18-06-027
As required in D.18-06-027, the program administrator (PA) for DAC-SASH was selected
through a competitive solicitation. In February 2019, GRID was selected as the PA for DAC-
SASH. The DAC-SASH program launched after approval of the DAC-SASH Handbook and
Program Implementation Plan in September 2019. As of the end of 2020, 705 DAC-SASH
projects had been installed equaling nearly 3,300 kW and utilizing nearly $9.9 million in
incentives. Another 112 projects were confirmed under DAC-SASH for an additional 441 kW.
62
61
D. 20-12-003 and the 2021 DAC-SASH ME&O plan.
62
DAC-SASH Semi-Annual Program Status Report. GRID Alternatives (January 2021).
gridalternatives.org/sites/default/files/DAC-SASH%20Q3-
4%202020%20SA%20report_FINAL%201.30.2021.pdf at page 13, Table 3.
CPUC California Solar Initiative Annual Program Assessment
June 2021 42
4.4.3. Disadvantaged Communities Green Tariff (DAC-GT) Program
The Disadvantaged Communities - Green Tariff (DAC-GT) program is the second program
created under D.18-06-027, pursuant to AB 327. It enables income-qualified, residential
customers in DACs who may be unable to install solar on their roof to benefit from utility scale
clean energy projects and receive a 20 percent bill discount.
The DAC-GT program is modeled after the Green Tariff portion of the Green Tariff/Shared
Renewables Program. DAC-GT allows customers who are not in a position to take advantage of
SOMAH or DAC-SASH through onsite solar, to still benefit from solar energy. The program
has a total capacity allocation of 158 MW.
D.18-06-027 ordered that these programs be funded first through available GHG allowance
proceeds and that if those funds are exhausted, then the programs be funded through public
purpose program funds. PG&E, SCE, and SDG&E launched two rounds of project solicitations
in 2020. As of December 31, 2020, 10,255 customers had been enrolled using interim resources
and 4.65 MW of new solar projects were approved. The Decision also specifically authorized
Community Choice Aggregators (CCA) to launch their own DAC-GT programs as long as they
meet all the rules and requirements established in the Decision. As of the end of 2020, Clean
Power Alliance’s implementation plan for the DAC-GT program was approved.
4.4.4. Community Solar Green Tariff (CSGT) Program
The Community Solar Green Tariff (CSGT) program is the third program created under D.18-
06-027, pursuant to AB 327. This program enables residential customers in DACs who may be
unable to install solar on their roof to benefit from a local solar project and receive a 20 percent
bill discount.
The program is a variation on the Green Tariff/Shared Renewables Program. It is structured
similarly to the DAC-Green Tariff program but requires each solar project to be located in
proximity to the customers it serves. D.18-12-015 extended the CSGT program to include San
Joaquin Valley Disadvantaged Communities Pilot Projects
63
and allows CSGT projects to be
within a 40-mile radius of the pilot communities they serve, rather than within a 5-mile radius.
The CSGT program also provides participating customers a sense of ownership in locally-
generated solar power via the required participation of a community sponsor. Community
sponsors help ensure interest from the local community and community engagement in project
63
D.18-12-015 authorized pilot projects in the communities of Allensworth, Alpaugh, California City, Cantua
Creek, Ducor, Fairmead, Lanare, Le Grand, La Vina, Seville, and West Goshen.
CPUC California Solar Initiative Annual Program Assessment
June 2021 43
siting. If eligible, community sponsors can receive a 20 percent bill discount on up to 25 percent
of a CSGT project's energy output. The program has a total capacity allocation of 41 MW.
D.18-06-027 ordered that these programs be funded first through available GHG allowance
proceeds and that if those funds are exhausted, then the programs be funded through public
purpose program funds. PG&E, SCE, and SDG&E launched two rounds of project solicitations
in 2020. D.18-06-027 specifically authorized CCAs to launch their own CSGT programs as long
as they met all the rules and requirements established in the Decision. As of the end of 2020,
Clean Power Alliance’s implementation plan for the CSGT program was approved.
4.5 CSI Thermal Program
4.5.1. CSI Thermal Program Background and Overview
The CSI Thermal program was an incentive program for solar thermal technologies that displace
natural gas consumption. It was established by legislative language in SB 1 (Murray, 2006), which
contained a provision that allowed up to $100.8 million of CSI General Market program funds
to be used for incentives for solar thermal technologies that displace electricity. The electric-
displacing portion of this program expired alongside the CSI General Market program on
December 31, 2016. AB 1470 (Huffman, 2007) authorized the creation of a $250 million
program to promote the installation of 200,000 solar water heating systems in homes and
businesses that displace the use of natural gas by the end of 2017.
The CPUC established the CSI Thermal program in January 2010 through D.10-01-022. The
program began accepting applications from single-family residential customers that install solar
water heating systems on May 1, 2010 and from multifamily and commercial customers on
October 8, 2010. In March 2012, the CSI Thermal Low-income program, which provides higher
incentives for low-income residences, began accepting applications. In 2013, the CPUC issued
two decisions authorizing new incentives. D.13-02-018 allowed incentives for process heating
and cooling, and for space heating. D.13-08-004 allowed incentives for swimming pools at
multifamily and commercial sites. Subsequently, D.15-01-035 increased early-step incentive
levels for the single-family and multifamily/commercial gas-displacing customer classes, and
revised project rebate caps and customer class budgets.
On May 6, 2016, Energy Division approved temporary higher incentives for the installation of
solar water heating systems to address the need to reduce natural gas use in the region impacted
by the Aliso Canyon natural gas leak. The new rules applied only to systems in SoCalGas service
territory that are installed by the end of 2016. The modifications include increased incentive
rates for general market single family and multifamily/commercial applications, reallocated funds
from later Steps 3 and 4 to the new, higher Step 1 incentives for single family and
CPUC California Solar Initiative Annual Program Assessment
June 2021 44
multifamily/commercial general market funds, and removal of the cap limiting the swimming
pool incentive from covering more than 50 percent of a project’s cost.
64
In February 2017, due
to ongoing Aliso Canyon mitigation efforts and the program’s success in raising single family
residential participation, the CPUC extended the installation deadline for projects that had
permit applications dated on or before October 6, 2016 but were not able to finish installation
before the initial December 31, 2016 deadline. Projects with the required permitting had until
June 16, 2017 to complete installation and receive the higher incentive.
In 2017, AB 797 (Irwin) authorized the CSI Thermal program to continue operation from
January 1, 2018 through July 31, 2020. Although the overall budget will not exceed the initial
$250 million ceiling, AB 797 mandates the allocation of 50 percent of the CSI Thermal budget
to low-income residential housing or buildings in disadvantaged communities (DAC).
65
Another
10 percent of the budget is reserved for industrial applications, which are larger projects that, in
general, use process heating to produce basic commodities and materials. As of December 31,
2017, the CSI Thermal incentive budget available for the program extension through July 2020
equaled $82.7 million.
Additionally, AB 797 expanded the program to include homeowners in the San Joaquin Valley
Communities without access to natural gas as identified by the CPUC pursuant to Public
Utilities Code 783.5 (a)(1). These households rely on propane or wood burning to fulfill their
space heating, water heating, and cooking needs.
Per legislative direction, the CPUC established two primary program elements corresponding to
the type of water heating fuel being displaced by solar technologies. Incentives for natural gas-
displacing systems were provided through a statewide budget of $250 million, as described in
detail below. Incentives for electric or propane-displacing systems were drawn from the closed
CSI General Market budget in each utility territory. The CSI Thermal program consisted of:
1. incentives for natural gas-displacing systems (including swimming pools);
2. incentives for natural gas-displacing systems serving low-income customers and DACs;
66
and
3. incentives for industrial process heat natural gas-displacing systems.
64
For more information, please consult the CSI Thermal Program Incentives webpage on the CPUC website at
cpuc.ca.gov/General.aspx?id=3785.
65
The CSI Thermal program defines disadvantaged communities as a community identified by the California
Environmental Protection Agency pursuant to Section 39711 of the Health and Safety Code.
66
This category includes the exception provided for communities lacking access to natural gas in the San Joaquin
Valley, as identified by the CPUC pursuant to paragraph (1) of subdivision (a) of Public Utilities Code Section
783.5.
CPUC California Solar Initiative Annual Program Assessment
June 2021 45
The four Program Administrators (PA) of the CSI Thermal program were: PG&E, SoCalGas,
SCE,
67
and CSE (on behalf of SDG&E). The CSI Thermal program closed to new applications
on July 31, 2020.
4.5.2. CSI Thermal Budget
4.5.2.1 Natural Gas-Displacing Program
For the natural gas-displacing portion of the program, the $250 million program budget was
collected during the duration of the program by the three gas IOUs based on the percentages
presented in Table 19.
Table 19: CSI Thermal Gas-Displacing Budget Allocation
Utility
Budget Allocation
Total Program Collections
($ millions)
PG&E
39%
$97.5
SDG&E
10%
$25.0
SoCalGas
51%
$127.5
Total
100%
$250 million
Source: D.10-01-022
During the program extension years, 2018-2020, each PA had access to the remainder of their
original budget allocations as of December 31, 2017, which was then adjusted based on program
revisions mandated by AB 797. Table 20 displays each PA’s budget for natural gas-displacing
solar thermal systems as of December 31, 2017.
Table 20: CSI Thermal Gas-Displacing 2018-2020 Incentive Budget Allocation
Utility
Total Program Collections
($ millions)
PG&E
$42.33
SDG&E
$8.45
SoCalGas
$31.92
Total
$82.70
Source: SoCalGas Advice Letter (AL) 5262
A/PG&E AL 3942
G
A/CSE AL 88
A
Table 21 shows funding for program administration and market outreach activities plus the
67
Note: As an electric-only utility, SCE offered incentives for electric or propane-displacing systems in their service
territory until the program closed at the end of 2016. Similarly, as a gas-only utility, SoCalGas only offers incentives
for natural gas-displacing systems in their service territory.
CPUC California Solar Initiative Annual Program Assessment
June 2021 46
specific budget reallocations pursuant to AB 797 that shifted 50 percent of program funds to the
Low-Income program and 10 percent to the Industrial sector.
Table 21: CSI Thermal Gas-Displacing Overall Program Budget, 2018-2020
CSI Thermal
Program Elements
CSI Thermal Program
Sub-Elements
Budget ($
millions)
Incentives (82%)
General Market
$22.189
Low-income/DAC (50% of total funds)
$50.429
Industrial (10% of total funds)
$10.085
Subtotal
$82.703
Program
Administration/Market
Facilitation (18%)
General Administration
$6.051
Marketing and Outreach
$10.086
Measurement and Evaluation
$2.017
Subtotal
$18.154
Total
$100.857
Source: SoCalGas AL 5262
A/PG&E AL 3942
G
A/CSE AL 88
A
4.5.2.2 CSI Thermal Natural Gas-Displacing Program Incentives
For systems that displace natural gas, general market incentives were available for three different
market segments (or customer classes): single-family, commercial/multifamily, and commercial
and multifamily solar pool heating. Due to low program participation rates, all budget categories
had not advanced past step 1 in 2018. At that time, because there were only two years left in the
program, the CPUC approved an AL collapsing all incentive steps from four to two tiers in May
2018.
68
For the single-family market, the average system rebate started at $3,493 in Step 1 and
declined over two steps to an average of $2,968. Commercial / multifamily systems were
incentivized at a slightly lower rate, and solar pool heating systems were incentivized at
substantially lower rates due to favorable project economics (see Table 22).
Pursuant to Decision (D.)15-01-035, all customer classes were subject to maximum system
incentive caps.
69
Incentive levels declined when the total incentive budget for a step was
exhausted. Step incentive levels, customer class budgets, and individual project caps for natural
gas-displacing systems were revised in May 2018 to reflect budget revisions to the program
pursuant to mandates in AB 797 (Irwin, 2017).
70
68
SoCalGas AL 5262A/PG&E AL 3942GA/CSE AL 88A, dated April 24, 2018 and effective as of May 24,
2018; Disposition Letter issued May 30, 2018.
69
The single-family system maximum incentive level is set to 125% of the average system cost.
Multifamily/commercial projects have a maximum incentive of $800,000 per project. Solar Pool Heating systems
have a maximum incentive level of 50% of total project costs up to $500,000.
70
SoCalGas Advice Letter No. 5102
CPUC California Solar Initiative Annual Program Assessment
June 2021 47
The Low-Income/DAC budget did not follow a step-down structure, and the incentive level
remained the same through the end of the program.
Table 22: Natural Gas-Displacing CSI Thermal General Market Incentive Steps,
2018-2020
Step
Customer Class
Incentive per
Therm
Displaced
Incentive for
Average
Solar Water
Heating
System
System
Maximum
Incentive
Funding
Amount
1
Single-Family
$29.85
$3,493
$4,366
$2,840,000
Commercial/
Multifamily
$20.19
PBI - $10.10
N/A
$800,000
$10,118,000
Commercial/
Multifamily Solar
Pool Heating
$7.00
50% of total
project costs
$4,793,000
2
Single-Family
$25.37
$2,968
$3,710
$710,000
Commercial/
Multifamily
$17.16
PBI - $8.58
N/A
$800,000
$2,530,000
Commercial/
Multifamily Pool
Heating
$5.00
50% of total
project costs
$1,198,000
Total
$22,189,000
Source: CSI Thermal Program Handbook, May 2019
4.5.2.3 CSI Thermal Industrial Natural Gas-Displacing Program Incentives
AB 797 reserved 10 percent of program funds through a separate budget category for industrial
solar thermal systems, which the CSI Thermal program defined as process heating systems that
use hot water or other fluid to produce basic materials and commodities.
Table 23: Natural Gas-Displacing Industrial CSI Thermal Incentive Rate
Step
Industrial Incentive
per Therm Displaced
Incentive Cap for
Industrial Projects
1
$10.10
$800,000
Source: CSI Thermal Program Handbook, May 2018
CPUC California Solar Initiative Annual Program Assessment
June 2021 48
4.5.2.4 CSI Thermal Low-income Natural Gas-Displacing Program Incentives
During the program extension years, 2018-2020, the low-income program provided
approximately $50.4 million of CSI Thermal incentives to promote the installation of gas-
displacing solar water heating systems on single-family and multifamily low-income housing and
buildings in DACs. The program budget is broken down by PA in Table 24.
Table 24: CSI Thermal Low-income Program 2018-2020 Budget Allocation
Utility
Total Program Collections
($ millions)
PG&E
$25.81
SDG&E
$5.15
SoCalGas
$19.47
Total
$50.43
Source: SoCalGas AL 5262
A/PG&E AL 3942
G
A/CSE AL 88
A
The CSI Thermal program offered higher incentives to low-income customers and installations
at buildings located in DACs. Pursuant to AB 797’s statutory emphasis on these customers, as of
May 2018, incentives in this budget category did not decline to maximize participation rates.
Table 25: CSI Thermal Low-income/DAC Incentive Rate
Step
Single-Family
Low-income
Incentive per
therm displaced
Incentive Cap
for Single-
Family Low-
income Projects
Multifamily
Low-income
Incentive per
therm displaced
Incentive Cap
for Multifamily
Low-income
Projects
1
$36.90
$4,317.00
$20.19
$800,000.00
Source: CSI Thermal Program Handbook, May 2018
4.5.3. CSI Thermal Program Participation
4.5.3.1 CSI Thermal Program History and Application Statistics
The CSI Thermal program approved 11,757 applications for $162 million in incentives through
2020. As seen below, the low-income/DAC single-family customer class received the greatest
number of applications. However, due to their much larger average project size, the
commercial/ multifamily customer class represented a larger portion of incentive amounts,
project costs, and energy savings.
CPUC California Solar Initiative Annual Program Assessment
June 2021 49
Table 26: CSI Thermal Installed Projects by Sector and Displaced Fuel through 2020
Customer Class
Number of
Applications
Total
Incentives
($ thousands)
Total Project
Costs
($ thousands)
Total Annual
Energy Savings
(therms)
Commercial Pools (Gas)
878
$12,614
$20,802
2,094,881
Commercial/
Multifamily Residential
1,293
$55,027
$101,011
3,030,927
Industrial
1
$753
$825
37,284
Single Family Residential
3,418
$16,341
$29,113
602,873
Multifamily low-
income/DAC
1,248
$48,053
$89,975
2,170,125
Single-Family low-
income/DAC
4,919
$29,215
$25,124
680,181
Total
11,757
$162,003
$266,850
8,616,271
$ per Therm
-
$18.80
$30.97
-
Source: CSI Thermal Program Data (californiadgstats.ca.gov), accessed April 15, 2021.
4.5.3.2 CSI Thermal Incentives Received
As mentioned above, the CSI Thermal program was jointly administered by PG&E, SoCalGas,
and CSE. As shown in Table 27, SoCalGas received the most applications, followed by PG&E
and then CSE.
Table 27: CSI Thermal Applications by Program Administrator through 2020
Program Administrator
Complete
Applications
Total Incentive ($ thousands)
PG&E
3,516
$54,490
CSE
454
$10,988
SoCalGas
7,772
$96,505
Total
11,742
$161,983
Source: natural gas displacing systems, CSI Thermal Statistics csithermalstats.org/program_totals.html, may include applications
that were cancelled at a later date.
CPUC California Solar Initiative Annual Program Assessment
June 2021 50
4.5.4. CSI Thermal Measurement and Evaluation (M&E)
Unlike the CSI General Market program, where generation performance can be evaluated at the
meter, CSI Thermal technologies offset electric or gas consumption. This requires evaluation of
kilowatt-hour and therm savings to assess whether the program is meeting its goals.
Decision (D.)10-01-022 adopted a $6.3 million total budget for M&E of the CSI Thermal
program. In February 2014, when program participation had risen to a level warranting M&E
expenditures, the CPUC released a detailed M&E plan for the program. This plan, available on
the CPUC’s website, outlined both the field performance data to be collected from a sample of
CSI Thermal systems, and the program evaluation studies to be performed with this data.
71
In
accordance with the 2014 CSI Thermal M&E Plan, the CPUC retained Itron through a
competitive solicitation to complete a Performance Data, Impact, and Technology Project,
which includes the installation of performance metering on CSI participating solar thermal
systems and publishing of Technology Evaluation, Impact Evaluation. The three final reports
under the Performance Data, Impact, and Technology Project can be found on the CPUC CSI
Thermal Program Evaluation webpage.
72
In 2019, and in accordance with Public Utilities Code
2863(a)(4) the CPUC commissioned the California Solar Initiative (CSI) Thermal Cost
Effectiveness study, which was submitted to the California Legislature in February 2020.
73
4.6 Research, Development, Demonstration, & Deployment
4.6.1. RD&D Program Background
The CSI Research, Development, Demonstration, and Deployment (RD&D) program was a
CPUC-administered program that closed on December 31, 2016. The purpose of the CSI
RD&D program was to identify and support projects that would help reach the program goals
of installing 1,940 MW of distributed solar by the end of 2016 and creating a self-sustaining,
subsidy-free solar market.
The CSI RD&D program conducted five solicitations for projects over the life of the program.
The first program solicitation focused on integrating solar PV into the electricity grid. The
second program solicitation had two focus areas: energy generation technologies and business
development and deployment. The third program solicitation had a primary focus of grid
integration with a secondary focus of production technologies, business development, and
71
The CSI Thermal Measurement and Evaluation Plan is available at: cpuc.ca.gov/General.aspx?id=7623.
72
CSI Thermal Program Evaluation webpage, cpuc.ca.gov/General.aspx?id=11155.
73
California Solar Initiative (CSI) Thermal Cost Effectiveness study,
cpuc.ca.gov/uploadedFiles/CPUC_Public_Website/Content/Utilities_and_Industries/Energy/Energy_Programs/
Demand_Side_Management/Customer_Gen_and_Storage/CSI-T_CE_2020.pdf
CPUC California Solar Initiative Annual Program Assessment
June 2021 51
deployment. The fourth solicitation focused on cost-effective strategies and solutions for
integrating large amounts of PV into distribution systems. The fifth solicitation focused on
leveraging the value of past or current CSI RD&D investments or other publicly funded
research to address the goals of the CSI RD&D program.
The five CSI RD&D solicitations resulted in grant funding for 36 projects totaling $31.2 million.
With the additional award of $10 million to the Helios Solar Energy Center at UC Berkeley, the
total allocation of CSI RD&D funds to date is approximately $41.2 million. The CSI RD&D
program completed all grant making activities and will not conduct any future solicitations.
Table 28: CSI RD&D Final Budget Allocations
Source: CSI RD&D Program Report, 2006-2016, Itron, 2017
Several CSI RD&D projects made notable contributions to the grid integration of solar and the
industry in general. An example was the grant funding awarded to the Electric Power Research
Institute for a project based in Fontana, CA of 20 Zero Net Energy (ZNE) homes in a builder
community, which has become a test bed for several research questions around both ZNE and
grid integration of solar and storage. Detailed profiles of all CSI RD&D funded projects, project
documentation, and reports can be found at calsolarresearch.ca.gov.
4.6.2. RD&D Program Evaluation
Pursuant to D.07-09-042, the CPUC commissioned an independent evaluation of the CSI
RD&D program. Results of the evaluation provide the CPUC and stakeholders an independent,
Grant
Solicitation
Target Areas Available Funding
No. of Proposals
Approved for Funding
Approved CSI RD&D
Funding Ceiling
Approved
Match Funding
1 Grid Integration $15M 8 $7.0M $4.6M
2
Improved PV Production
Technologies and
Innovative Business Models
$15M 9 $12.8M $10.2M
4 Grid Integration $7M 6 $5.1M $7.9M
36 $31.2 $29.7
1 $10 -
37 $41.2M $29.7M
Solicitations Total
Solar Energy Center
CSI RD&D Total
$0.5M
Primary Area:
Grid Integration
Secondary Areas:
Production Technologies
and Business Development
and Deployment
3
$9M
$3M
6
$5.6M
$6.5M
5
Small Projects in all target
areas
$1M
7
$0.7M
CPUC California Solar Initiative Annual Program Assessment
June 2021 52
expert conclusion about the CSI RD&D program’s legacy impacts on the economics,
deployment, and integration of innovative solar technologies in California. The evaluation
concluded in March 2017 and resulted in the following findings.
74
The Program Manager, Itron, performed very well. It implemented the program in
accordance with the original program design. It also played an important and highly
effective role in facilitating communication and partnerships within and between
projects, as well as with the broader solar community, helping to engage key stakeholders
and reduce duplication of efforts.
CSI RD&D projects were mostly successful in making progress toward the long-term
policy goals established for the program. Grid Integration was the most successful
research area, with 20 completed projects. Important accomplishments for these projects
included improvement to interconnection requirements, development of software
products, improved modeling tools, and inverter system enhancements.
The program resulted in a substantial amount of knowledge benefits. The creation and
dissemination of knowledge benefits may be the most important metric of success when
evaluating a research program. By this measure, the CSI RD&D program was very
successful and took an essential step toward achieving its longer-term program goals.
74
The CSI RD&D Program Program Evaluation is available at
calsolarresearch.ca.gov/images/stories/documents/Prog_Report/CSI_RDD_Evaluation_Report_FINAL_051117.
pdf.
CPUC California Solar Initiative Annual Program Assessment
June 2021 53
5 Program Reporting and Evaluation
5.1 Program Reporting
5.1.1. CSI General Market Reporting
CSI General Market program data is available on the California Distributed Generation Statistics
(California DG Stats)
75
website, (formerly named California Solar Statistics). California Solar
Statistics, launched in 2010, was a collaborative effort between the CSI Program Administrators
and CPUC staff, and contained a wealth of program data. The website originally focused on the
CSI General Market program, but later added data on the MASH and SASH programs. As the
CSI General Market program became fully subscribed, there was a concern that this source of
solar PV market data would become outdated. For this reason, the CPUC adopted D.14-11-001,
which instructs the CPUC, CEC, and Program Administrators to continue the collection of non-
CSI solar PV installation data through the NEM interconnection process.
California DG Stats was launched in 2016 to maintain access to useful data on all (including
non-CSI) solar projects in the three large IOU service territories. It includes data for all behind-
the-meter (BTM) generation and storage systems interconnected to the large IOUs.
76
California DG Stats provides the following data:
Charts and tables that can be filtered by CSI program administrator, application status,
date ranges, customer classes, and system ownership.
Data on individual BTM installations (while maintaining customer confidentiality)
including:
o system costs,
o manufacturer, model, capacity, and other technical information, and
o geographic location.
A “Find an Active Solar Contractor” feature, which helps prospective solar buyers
search local options for solar installations.
75
See californiadgstats.ca.gov.
76
Systems interconnected under the Wholesale Distribution Access Tariff (WDAT) are not included in this dataset.
CPUC California Solar Initiative Annual Program Assessment
June 2021 54
Monthly updates to the budget status of the General Market, SASH, and MASH
programs.
A Data Annex, containing information about the efficiency of the program’s
administrative processing.
Market participants (installers, third-party owners, manufacturers, etc.) have praised the benefits
of this online data because it is current, comprehensive (covering the vast majority of
California’s distributed generation PV installations), and in-depth (including a wide array of data
fields). Outside agencies have modeled their public-facing solar energy databases after California
DG Stats.
5.1.2. CSI Thermal Reporting
The CSI Thermal “Incentive Step Tracker”
77
informs the public which incentive steps are
currently in effect for the various CSI Thermal customer classes, including those in the low-
income programs, and how much funding remains in each step.
Using the California Solar Statistics website as a model, CPUC staff and the Program
Administrators developed the CSI Thermal Statistics site as a public-facing database for the CSI
Thermal program. The CSI Thermal Statistics site launched in February 2015 and contains
extensive CSI Thermal program data. The website contains data on all customer classes and can
also be filtered by backup commodity (natural gas, electricity, or propane). The data is updated
weekly and includes the following features:
Charts and tables that display key program data and can be filtered by program
administrator, application status, date ranges, customer classes, and system ownership.
A master data set, which includes data on individual installations (while maintaining
customer confidentiality).
o System costs
o Manufacturer, model, capacity, and other technical information
o Geographic location and climate zone
A “Find an Active Solar Contractor” feature, which helps prospective solar buyers
search local options for solar thermal installations.
77
See csithermal.com/tracker.
CPUC California Solar Initiative Annual Program Assessment
June 2021 55
Bi-weekly updates to the CSI Thermal budget.
A Data Annex, containing information about the Program Administrators’ processing
times for CSI Thermal applications.
5.1.3. Periodic CSI and CSI Thermal Reports
A number of periodic reports are filed publicly and posted to the CPUC’s CSI website:
78
The CPUC’s Annual Program Assessment to the Legislature (this report), required by
statute every year no later than June 30.
The Program Administrators MASH and SASH semi-annual progress reports.
The SOMAH Program Administration budget reports, SOMAH Program IOU Semi-
Annual Administrative Expense Reports, and SOMAH Program Administrator’s Semi-
Annual Progress Reports.
The Program Administrators’ CSI Thermal quarterly reports that provide programmatic
updates and updates on the programs progress towards its energy displacement goals.
5.2 Program Evaluations
The CSI Evaluation Plan measures the CSI program’s progress towards its goals of deploying
1,940 MW of new solar capacity and helping to create a self-sufficient solar industry in which
solar energy systems are a viable mainstream option for both homes and businesses within 10
years, without ratepayer support. A summary of CSI M&E reports is as follows:
PV Market Assessment Studies: In 2014, the CPUC released three studies that address
the core questions of how much the distributed generation PV market has been
transformed, how much we expect it will be transformed after the CSI program’s market
interventions, and how we will know. The PV Market Assessment Studies included:
79
o Third-Party Ownership Market Impact Study: This study found that third-party
ownership had accounted for a significant portion of residential solar
installations and demand for this model was growing.
78
See cpuc.ca.gov/General.aspx?id=3747.
79
See cpuc.ca.gov/General.aspx?id=7623.
CPUC California Solar Initiative Annual Program Assessment
June 2021 56
o CSI Market Transformation Study: This study found that significant market
transformation had occurred, but that continued health to the industry was
dependent on the resolution of NEM policies and residential rate reforms.
o Solar PV and Residential Roof Study: This study assessed the relationship
between roofing and the distributed generation PV market.
Impact Evaluations: Four studies have been published covering CSI program
accomplishments, including energy, capacity, and environmental impacts and PV system
performance degradation.
o 2007-8 CSI Impact Evaluation
o 2009 CSI Impact Evaluation
o 2010 CSI Impact Evaluation
o 2011-2016 CSI Impact Evaluation
Impact of Distributed Generation Reports: These reports were mandated in AB 578
(Blakeslee, 2008) and Public Utilities Code 913.10. The first impact of distributed
generation report was completed in 2010. The second impact of distributed generation
report, delivered in 2013, showed that, while California’s solar distributed generation
installed capacity was large compared to other states, the impact on the distribution and
transmission infrastructures was relatively low. The third impact of distributed
generation report, delivered in 2016, focused on the effects of customer-sited solar on
CAISO’s net load curve.
80
The report’s primary findings included that:
o Customer-sited solar power was effective at reducing summer peak net load but
did not reduce winter and spring peak net load, when the “duck curve” effects
are most pronounced.
o There were tradeoffs in the effects of west-facing and south-facing customer-
sited solar, but the findings alone did not support policy to incentivize one type
of solar over the other.
o A diverse portfolio of renewables produced a smoothing benefit to CAISO’s net
load curve.
80
A competitive solicitation was issued in January 2015 to perform the third bi-annual study. The CPUC retained
DNV-GL in May 2015.
CPUC California Solar Initiative Annual Program Assessment
June 2021 57
o Large-scale deployment of energy storage, dispatchable demand-response, and
time-of-use rates for consumers would help integrate increasing amounts of
customer-sited solar.
External Financial Audit Report: In 2010, CPUC audit staff completed a PG&E
2007-08 audit, SCE 2007-08 audit, and SDG&E 2007-08 audit. The 2010-11 audit was
conducted by an outside firm, and was completed in 2013.
81
The audit did not identify
any significant issues with administration of the program. The 2012-14 audit was
completed in 2016. As before, the audit did not identify any significant issues with
administration of the program.
California Solar Initiative Cost-Effectiveness Evaluation: this study, completed in
2011, looked at cost effectiveness from several perspectives program administrators,
ratepayers, and especially program participants and society overall.
82
Based on participant
economics, the study suggested that the residential solar PV market would be self-
sustaining by 2017, with a mixed outlook for non-residential customers.
CSI Thermal Performance Data, Impact, and Technology Project: The CPUC
contracted with Itron to assess the performance of installed CSI thermal systems
through metering and collecting data from solar water heating systems. In 2016, Itron
completed metering on 120 CSI Thermal solar water heating systems to gather data for
the study. The project included the publication of a Technology Evaluation Report in
2019, which assessed the costs and benefits of various solar thermal technologies
amongst different markets. The project also assessed the CSI Thermal program’s impact
on electricity and natural gas demand, and effectiveness in reducing greenhouse gas
emissions, and compared the actual performance of solar water heating systems against
their expected performance. A 2018 CSI Thermal Impact Evaluation Report and 2019
CSI Thermal Impact Evaluation Report were completed.
California Solar Initiative (CSI) Thermal Cost Effectiveness Study: This study,
completed in February 2020, looked at cost effectiveness from several perspectives
program administrators, ratepayers, program participants, and society at large. Overall,
the study found that the CSI Thermal Program was not currently cost-effective for
natural gas-displacing systems. Relatively high installation costs combined with low
natural gas prices and low avoided costs made cost-effectiveness a challenge for many of
the solar thermal technologies from the four perspectives mentioned above.
CSI SASH and MASH Biennial Report: In 2016, the CPUC released Navigant
Consulting’s evaluation of CSI SASH and MASH, program years 2011-13, program
81
See cpuc.ca.gov/General.aspx?id=7623.
82
See cpuc.ca.gov/General.aspx?id=7623.
CPUC California Solar Initiative Annual Program Assessment
June 2021 58
design, delivery, operations, and impact. The evaluation consisted of a program
administrator assessment and an impact and cost-benefit analysis, which built upon the
previous MASH and SASH studies completed in 2011.
CSI RD&D Program Evaluation: Pursuant to requirements in Decision (D.)07-09-
042, the Commission hired Evergreen Economics for an independent evaluation of the
CSI RD&D program. The evaluation provides the CPUC and stakeholders with expert
conclusions about the CSI RD&D program’s legacy impacts on the economics,
deployment, and integration of innovative solar technologies in California. The final CSI
RD&D Evaluation Report was released in 2017.
Another relevant report, not directly tied to CSI, is an evaluation of the NEM successor tariff
that was authorized by the Decision on NEM consumer protections (D.18-09-044). Verdant
Associates, LLC conducted the evaluation to analyze the costs and benefits of customer-sited
renewable resources taking service on the tariff and its variants. The evaluation was released in
January 2021.
6 CSI Program Links and Contact Information
The CPUC Energy Division website provides information related to the CSI program at
cpuc.ca.gov/Demand_Side. Additionally, CSI Thermal program information is available at
CSIThermal.com. For CSI inquiries please contact [email protected].