!Undefined Boo kmark, I
IN THE COUNTY COURT OF VICTORIA
AT MELBOURNE
COMMERCIAL DIVISION
BUILDING CASES LIST
Revised
Not Restricted
Suitable for Publication
Case No. CI-18-01563
PHHH Investments No 2 Pty Ltd (ACN 602 191 506)
Plaintiff
v
United Commercial Projects Pty Ltd (ACN 110 860 369)
Defendant
---
JUDGE:
His Honour Judge Woodward
WHERE HELD:
Melbourne
DATE OF HEARING:
2226 February; 25 March and 9 March 2021; final oral
closing submissions 19 November 2021
DATE OF JUDGMENT:
5 April 2023
CASE MAY BE CITED AS:
PHHH Investments No 2 Pty Ltd v United Commercial
Projects Pty Ltd
MEDIUM NEUTRAL CITATION:
REASONS FOR JUDGMENT
---
Subject: CONTRACTS
Catchwords: Building and construction building contract whether regime for
determination of claims under the contract is exclusive whether
claims can be re-opened either under the contract or because of
superintendent’s lack of impartiality – assessment of variations and
extensions of time whether date for practical completion brought
forward by owner taking possession for kindergarten open days
calculation of liquidated damages assessment of defect claims -
leave to file and serve further amended defence and counterclaim
admissibility of additional documents following the close of evidence
Legislation Cited: County Court General Civil Procedure Rules 2018 (Vic) (“Rules”); Civil
Procedure Act 2010 (Vic)
Cases Cited: Allmore Constructions Pty Ltd v K7 Property Group Pty Ltd [2016]
VCAT 1770, Peninsula Balmain Pty Ltd v Abigroup Contractors Pty Ltd
[2002] NSWCA 211, Kane Constructions Pty Ltd v Sopov [2005] VSC
!Undefined Boo kmark, II
237, Bellgrove v Eldridge (1954) 90 CLR 613, Tabcorp Holdings Ltd v
Bowen Investments Pty Ltd (2009) 236 CLR 272, Metricon Homes Pty
Ltd v Softley [2016] VSCA 60, The Owners - Strata Plan No 76674 v Di
Blasio Constructions Pty Ltd [2014] NSWSC 1067, Turner Corporation
Ltd (Receiver and Manager Appointed) v Austotel Pty Ltd (1994) 13
BCL 378, Director of War Services v Harris [1968] Qd R 275, Linden
Gardens Trust Ltd v Lenesta Sludge Disposals Ltd [1993] 3 All ER 417,
De Cesare v Deluxe Motors Pty Ltd (1996) SASR 28, Westpoint
Management Ltd v Chocolate Factory Apartments Ltd [2007] NSWCA
253, Cordon Investments Pty Ltd v Lesdor Properties Pty Ltd [2012]
NSWCA 184, Aon Risk Services Australia v Australian National
University (2009) 239 CLR 175, Traffic Technique Pty Ltd v Burgmann
[2020] VSCA 319
---
APPEARANCES:
Counsel
Solicitors
For the Plaintiff
Mr J Richardson
Noble Lawyers
For the Defendant
Mr S Stuckey QC with
Mr N Andreou
Macpherson Kelley
[2023] VCC 516
1
JUDGMENT
Table of Contents
Table of Contents .................................................................................................................. 1
Summary and Outcome ......................................................................................................... 3
Factual background ............................................................................................................... 5
The proceeding ...................................................................................................................... 7
The lead up to trial ............................................................................................................. 7
Trial and closing submissions ............................................................................................ 9
Witnesses .......................................................................................................................... 9
Key terms of the Contract .................................................................................................... 11
Issues .................................................................................................................................. 15
Can UCP dispute PC 16 Rev A and the decisions of the architect pursuant to the Contract?
............................................................................................................................................. 16
Contract construction ....................................................................................................... 16
Can UCP dispute PC 16 Rev A and the decisions of the architect due to the conduct of the
architect? ............................................................................................................................. 23
Particular variations ......................................................................................................... 24
Processing variations ...................................................................................................... 27
Variations register............................................................................................................ 29
Communications in relation to variations ......................................................................... 29
Defects ............................................................................................................................ 31
Breach of clause A6.4 of the Contract ............................................................................. 33
PHHH’s submissions ....................................................................................................... 34
Analysis ........................................................................................................................... 37
Did PHHH breach clause A6.4 of the Contract? .............................................................. 46
How should the disputed variations be resolved? ................................................................ 48
Variations which the experts agreed................................................................................ 48
Variation 48 Rev A........................................................................................................... 48
Variation 55 ..................................................................................................................... 50
Variation 56 Rev A........................................................................................................... 51
Variation 58 Rev A........................................................................................................... 51
Variation 59 ..................................................................................................................... 52
Variation 62 Rev A........................................................................................................... 53
Variation 80 ..................................................................................................................... 53
Variation 84 ..................................................................................................................... 54
Variation 88 ..................................................................................................................... 55
Variation 89 ..................................................................................................................... 55
Variation 99 ..................................................................................................................... 56
Variation 94 Rev B........................................................................................................... 57
Variation 96 ..................................................................................................................... 58
Variation 26 and 30 ......................................................................................................... 59
Is PHHH entitled to liquidated damages in the amount certified or some other amount? .... 60
Is PHHH is entitled to liquidated damages? .................................................................... 60
What is the quantum of PHHH’s liquidated damages? .................................................... 63
Amounts owed by UCP to PHHH for breach of contract and restitution .............................. 76
Is PHHH entitled to damages for defective work by UCP? .................................................. 77
What defects are agreed? ............................................................................................... 78
[2023] VCC 516
2
JUDGMENT
What is UCP’s liability for the disputed defects? ............................................................. 78
Should PHHH’s damages be reduced because it denied UCP the opportunity to
undertake rectification works at lower cost? .................................................................... 85
Does PHHH’s sale of the property reduce the amount of the defects damages it can
claim? .............................................................................................................................. 94
Variation 37 Claim ............................................................................................................... 99
Utilities Claim ..................................................................................................................... 101
Incidental matters .............................................................................................................. 102
UCP’s application to file and serve further amended counterclaim ............................... 102
Admissibility of Tranche 14 ............................................................................................ 112
[2023] VCC 516
3
JUDGMENT
HIS HONOUR:
Summary and Outcome
1 By a contract dated 16 March 2016 (“Contract”), the plaintiff (“PHHH”) engaged
the defendant (“UCP”) to construct a childcare centre at 282284 Victoria Street,
Brunswick, Victoria (“Site”), for $3,833,665.00 (inc GST) (“Contract Price”). All
dollar sums referred to below include GST, unless stated otherwise.
2 During the course of the Contract:
(a) UCP claimed 99 variations. Of these, the architect, Insite Architects (the
representative of which was Mr Luciano Palma) (“the architect”), approved
variations totalling $416,841.80;
(b) UCP claimed 44 extensions of time (“EOT”) and the architect certified EOTs
totalling 4.5 working days (less than the 10-day allowance under the
Contract);
(c) PHHH paid UCP a total of $4,539,281.37;
(d) on 23 August 2017, the architect issued progress certificate “No. 016 Rev
A” certifying that $322,493.54 was payable by UCP to PHHH (“PC 16 Rev
A”); and
(e) UCP did not pay PHHH the amount certified by PC 16 Rev A.
3 The ultimate question for determination in this proceeding is: what is the final
adjusted Contract Price? PHHH claims that the adjusted Contract Price taking
account of PC 16 Rev A is $4,250,506.80 (comprising the amounts certified in
PC 16 Rev A as “Revised Contract Price” of $4,241,638.36 plus the “Total of
This Claim” of $8,864.44) and that PHHH is therefore entitled to restitution for
overpayments under the Contract in a sum totalling $288,774.57. This comprises
an amount of $40,310.37 that UCP admits was overpaid, plus $248,464.20 in
[2023] VCC 516
4
JUDGMENT
payments by PHHH to UCP in respect of unapproved variations. UCP
counterclaims that the adjusted Contract Price is $5,463,855.14 and that PHHH
owes it $923,689.42.
4 In addition to the adjusted Contract Price calculated based on PC 16 Rev A
summarised above, PHHH claims the allowances in that Progress Certificate for
liquidated damages of $324,000.00 and utilities of $7,361.98. These amounts
total $331,361.98.
5 Finally, PHHH claims that UCP breached the Contract as:
(a) UCP’s work was defective or incomplete and that PHHH is entitled to
damages for such breach; and
(b) UCP failed to pay for utilities incurred during the works and is liable to repay
amounts paid by PHHH for utilities.
6 For the reasons below, I have determined that the adjusted Contract Price is the
$4,250,506.80 as submitted by PHHH, and thus PHHH has overpaid UCP a total
of $288,774.57. UCP must give restitution in that sum. Further, UCP must pay
PHHH $331,361.98 for the certified amounts of liquidated damages, plus
damages for defects totalling $174,191.55. There will therefore be judgment for
PHHH against UCP for $794,328.10, plus interest and costs.
7 On the question of interest and costs, PHHH is entitled to interest pursuant to the
Contract at 10% per annum on the amount certified by PC 16 Rev A and unpaid
($322,493.54), from 10 March 2018, being the date this was due for payment by
PHHH. My preliminary view is that the balance of the judgment amount will incur
interest pursuant to s60 of the Supreme Court Act 1986 at the penalty interest
rate, on and from the date of the writ (12 April 2018).
8 On costs, in my view, despite having some claims found against it as set out
below, PHHH has been overwhelmingly successful in the pursuit of its claims.
[2023] VCC 516
5
JUDGMENT
Thus, unless a party can point to an offer of compromise or other sustainable
basis for a different order, I will order that UCP pay PHHH’s costs of the
proceeding (including reserved costs) on the standard basis in default of
agreement.
9 I also confirm my rulings during the hearing:
(a) refusing UCP’s application to file and serve a further amended defence and
counterclaim; and
(b) that the second Powercor invoice is inadmissible.
10 The parties will be invited to check my arithmetic on the various sums awarded
and agree on the form of orders to give effect to these reasons, including on
interests and costs. Failing agreement, they are directed to submit brief written
submissions in support of the orders they seek. Final orders will then be made on
the papers.
Factual background
11 Patrick Honeyborne is the sole director and company secretary of PHHH. In
2014, PHHH purchased the Site with the view to developing it into a childcare
centre that PHHH would continue to own after completion, but would be let out
on a long-term lease to Happy Hippo Kindergarten and Childcare Pty Ltd
(“Happy Hippo”). Mr Honeyborne’s wife, Heather Honeyborne, is the sole director
and company secretary of Happy Hippo. Tendering for the development of the
kindergarten occurred in 2015 and on 16 March 2016, UCP was contracted by
PHHH to complete the project.
12 The Contract was a build only ABIC SW-2008 Simple Works Contract. The
relevant terms of the Contract are set out in the following section of these
reasons. As noted above, Insite Architects was appointed to administer the
Contract. Mr Luciano Palma, an associate architect and contract administrator
with Insite Architects, was appointed as the architect’s representative.
[2023] VCC 516
6
JUDGMENT
13 On or about 1 June 2017, PHHH and Happy Hippo entered a lease of the site,
which commenced on 1 July 2017 for an initial 20-year term.
14 The certificate of practical completion was not issued by the architect until 21
July 2017 and there was no final certificate issued by the architect. The parties
dispute the date on which practical completion of the project was achieved.
PHHH asserts that the practical completion was achieved on or about 21 July
2017, as certified by the architect. UCP contends that it occurred when PHHH
took possession of the site in around April or May 2017.
15 On 23 August 2017, the architect issued PC 16 Rev A which certified that UCP
was to pay PHHH $322,493.54. More particularly, by PC 16 Rev A, the architect
certified that:
(a) the revised Contract price is $4,241,638.36;
(b) the progress claim for PC 16 Rev A totalled $8,868.44; but
(c) there is a deduction of $324,000 for liquidated damages;
(d) there is a deduction of $401.98 for water usage paid by PHHH;
(e) there is a deduction of $6,960 for electricity usage paid by the owner; and
(f) therefore the “Amount for Payment to PHHH Investments No. 2 Pty Ltd”
was $322,493.54.
16 The architect issued the final progress certificate (PC 17) on 20 September 2017,
but this did not make any further adjustments to the amounts stated and certified
in PC 16 Rev A.
17 On 23 February 2018, PHHH delivered PC 16 Rev A and a tax invoice to UCP by
email. PHHH claims that UCP’s failure to pay PC 16 Rev A and the associated
invoice by 9 March 2018 constitutes a breach of subclause N6.1 of the Contract.
UCP asserts that the amounts certified in PC 16 Rev A are incorrect and that it is
[2023] VCC 516
7
JUDGMENT
not liable to pay PHHH. UCP argues that PC 16 Rev A is not of contractual force
and the amounts certified in it are re-enlivened for determination in this
proceeding.
18 In March 2018, PHHH put the Site up for sale and on or about 17 April 2018, it
was sold to an unrelated entity, Duongquynh Pty Ltd, for $7,375,000 by contract
of sale. Settlement occurred on 22 June 2018. Happy Hippo (under the control of
Mrs Honeyborne) remains the tenant of the Site, running its childcare business
from the premises.
19 Around this time, PHHH and UCP were party to other proceedings related to the
project:
(a) In October 2017, PHHH commenced proceedings in the Supreme Court for
an injunction or order that UCP provide it with two unconditional bank
guarantees. This proceeding was dismissed in March 2018.
(b) In January 2018, PHHH commenced proceedings in the Supreme Court
seeking review of an adjudication determine under the Building and
Construction Industry Security of Payment Act 2002. This proceeding was
dismissed in the same month.
20 Following the sale of the Site, on 16 July 2018, the architect issued a defects
inspection report by way of “Architects Instruction” (“AI”) No. 649.
The proceeding
The lead up to trial
21 This proceeding was commenced by PHHH on 12 April 2018, for the recovery of
delay liquidated damages. While UCP filed a notice of appearance, UCP failed to
file a defence and default judgment was entered on 6 June 2018. This was set
aside on 6 July 2018. The proceeding thereafter progressed as follows:
[2023] VCC 516
8
JUDGMENT
(a) on 1 August 2018, PHHH filed an amended statement of claiming adding
various other claims and on 31 August 2018, UCP filed a defence and
counterclaim;
(b) on 2 November 2018, the proceeding was fixed for trial on 8 July 2019, on
an estimate of 8 to 10 days;
(c) on 5 November 2018, PHHH filed a further amended statement of claim
and on 5 and 6 December 2018, UCP filed an amended defence and
counterclaim respectively;
(d) on 21 December 2018, UCP made an application by summons for security
for costs and in April 2019, this application was dismissed;
1
(e) a short time later, the trial date of 8 July 2019 was vacated;
(f) the ruling dismissing UCP’s application for security for costs was later
overturned by the Court of Appeal, and PHHH was ordered to provide
security for costs of the proceeding until the completion of mediation, in the
sum of $85,000;
2
(g) in October 2019, the proceeding was re-fixed for trial on 29 June 2020;
(h) in November 2019, UCP made an application for judgment or to strike out
of certain claims made by PHHH pursuant to r23.01(1) of Rules;
(i) on 6 December 2019, this application was dismissed;
(j) on 28 May 2020, UCP made an application to join Mackey Brothers &
Company Roofing Pty Ltd (“Mackey Bros”) and Matthew Mackey (together
“the Mackey parties”) as third parties to the proceeding and for adjournment
of trial;
1
United Commercial Projects Pty Ltd v PHHH Investments No 2 Pty Ltd [2019] VCC 333.
2
United Commercial Projects Pty Ltd v PHHH Investments No 2 Pty Ltd [2019] VSCA 192.
[2023] VCC 516
9
JUDGMENT
(k) on 12 June 2020, UCP was granted to leave to file and serve a third-party
notice joining the Mackey parties, and the proceeding was re-fixed for trial
on 23 November 2020;
(l) on 25 August 2020, the trial date was once again vacated and the
proceeding was refixed for trial on 22 February 2021; and
(m) the third party proceeding against the Mackey parties was dismissed by
consent of UCP and the Mackey parties on 4 February 2022, following a
settlement agreed between those parties.
22 It was revealed during the course of the trial that the settlement between UCP
and the Mackay parties included terms for a payment of around $100,000 by the
Mackay parties to UCP, with that sum to be held by the solicitors for the Mackay
parties and released only by court order or the consent of the Mackay parties
and UCP.
Trial and closing submissions
23 Trial commenced from 22 February 2021 and the evidence concluded on 9
March 2021. On this date, I ordered that UCP file and serve written closing
submissions by 12 April 2021, PHHH do likewise by 23 April 2021 and UCP file
and serve any submissions in reply by 30 April 2021. There were some minor
delays in the filing and service of written submissions, which ultimately concluded
with the filing and service of UCP’s reply submissions on 6 May 2021. I heard
brief oral closing submissions on 19 November 2021. The entirety of the hearing
(including final oral submissions) was conducted remotely over Zoom.
Witnesses
24 The lay evidence-in-chief was given primarily by lengthy witness statements, with
some supplementation by oral evidence-in-chief. PHHH called Mr Honeyborne,
the architect Mr Palma and Mrs Honeyborne. UCP called Mark Potter, UCP’s
construction director and Tamar Soliman, a director of UCP.
[2023] VCC 516
10
JUDGMENT
25 I relation to expert witnesses, PHHH relied on:
(a) David Watson, engineer, in relation to extensions of time;
(b) Trevor Jeffrey, quantity surveyor and project manager, in relation to
variations;
(c) Phillip Naughton, building consultant, in relation to defects generally and
roofing defects;
(d) Richard Drew, structural engineer, in relation to Variation 37; and
(e) Robert Quick, licensed plumber and consultant in building matters
specialising in plumbing and roofing, in relation to roofing defects.
26 UCP relied on:
(a) Peter Quigley, architect, in relation to extensions of time, variations and
defects generally;
(b) Peter Wenning, plumbing inspector and licensed plumber, in relation to
quantum and roofing defects;
(c) Daniel Herbert, structural engineer, in relation to Variation 37;
(d) Douglas Buchanan, quantity surveyor, in relation to defects generally; and
(e) Robert Lorich, building consultant, in relation to defects generally.
27 The experts gave evidence by way of expert reports, joint reports and concurrent
oral evidence at trial, in a variety of combinations. Generally speaking, the
experts worked cooperatively and constructively during the process of the
witness conclaves and the concurrent evidence. They were able to narrow down
the issues in dispute and made helpful and appropriate concessions. I found the
evidence of some of the expert witnesses more persuasive than others, and I
give my reasons for this when discussing their evidence below.
[2023] VCC 516
11
JUDGMENT
Key terms of the Contract
28 Schedule 1 of the Contract contains the Contract information, the key items of
which are as follows:
(a) the Contract Price is $3,833,665.00 (Item 4);
(b) the interest rate on overdue amounts is 10% per annum (Item 28);
(c) the allowance for disruptive weather is 10 working days (Item 20);
(d) as agreed by the parties, the date for practical completion is 16 March 2016
(Item 22); and
(e) the rate for liquidated damages is $2,000 per calendar day (Item 24).
29 The key clauses of the Contract are as follows (emphasis in original):
A Overview
A4 Obligations of the owner
.1
The owner must:
a subject to subclause A2.1e, obtain and give to the contractor
all *official documents required to begin the *works and any
shown in item 30b of schedule 1
c give [access to] to the *site in accordance with this contract
A6 Architect to administer contract
.3
The architect is the owner's agent for giving instructions to the
contractor. However, in acting as assessor, valuer or certifier, the
architect acts independently and not as the agent of the owner.
.4 The owner must ensure that the architect, in acting as assessor,
valuer or certifier, complies with this contract and acts fairly and
impartially, having regard to the interests of both the owner and the
contractor. The owner must not compromise the architect's
independence in acting as assessor, valuer or certifier.
A8 Disputing architect’s certificate, written decision or failure to act
.1 If a *party wishes to dispute a certificate, notice, written decision or
written assessment issued by the architect, or to dispute the failure of
the architect to do something, the *party must give written notice under
this clause within 20 *working days after:
a receiving the certificate, notice, written decision or written
assessment or
b becoming aware of the failure of the architect to issue
something.
.2 If the *party fails to give a notice under subclause A8.1, the *party will
not be entitled to dispute the matter at all.
[2023] VCC 516
12
JUDGMENT
.3 The architect must assess a notice given under subclause A8.1 and
give a written decision to the *party and the other *party within 10
*working days.
.4 If a *party wishes to dispute a written decision given under subclause
A8.3, or the architect’s failure to give a decision, the requirements of
section P apply.
F The site
F1 Owner to give contractor possession of the *site
.1 The owner must give the contractor [access to] the *site within ten
working days after the owner:
c has received, or the architect as agent of the owner has
received, any *official documents required under item 30a of
schedule 1.
H Claims to adjust the contract
H1 Time for making a *claim to adjust the contract
.1 The contractor is entitled to make a *claim to adjust the contract only if
the contractor:
a *promptly notifies the architect in writing of its intention to make
a claim after receiving an instruction or, if no instruction is
issued, *promptly notifies the architect after becoming aware of
an event that will result in a claim and
b submits the detailed *claim to adjust the contract to the
architect within a time agreed in writing between the contractor
and the architect or, if no time is agreed, within 20 *working
days after receiving an instruction or, if no instruction is issued,
within 20 *working days after becoming aware of the event that
has resulted in the claim and, for these purposes, an event is
not a consequence of an instruction.
.2 If the claim results from an instruction to proceed with a *variation, the
requirements for submission of the claim are set out in clause H2.
.3 If the claim results from a delay in the progress of the *works, the
contractor is not required to give the first notification required under
subclause H1.1, but the detailed claim must be submitted within 20
*working days after the delay ends.
H2 Details required for claim
.1 A *claim to adjust the contract must contain the following details:
a identification of the architect's instruction, or a copy of the
*official document that caused the claim or, where none has
been issued, details of the event and the basis for the claim
H3 Architect to assess claim
.1 The architect must *promptly assess the *claim to adjust the contract
and in so doing the architect must consider the detailed claim
submitted by the contractor and any further information the architect
requests the contractor to supply.
.2 If the architect needs additional information to assess the claim, the
architect must issue a written request to the contractor.
.3 The contractor must *promptly give to the architect any additional
information the architect reasonably requests.
H4 Architect to give assessment
.1 The architect must, within 20 *working days after receiving the claim,
issue to the contractor and to the owner its written decision specifying
[2023] VCC 516
13
JUDGMENT
any adjustment to the *contract price or any adjustment to the date for
*practical completion, or both.
.2 The contractor may dispute the architect's decision or a failure to issue
a decision issued under this clause in accordance with clause A8 but,
in accordance with clause P1, must continue to perform its contractual
obligations.
H5 Sum recoverable for claim for *adjustment of time costs
.1 Where a sum or sums per day is shown in item 18 of schedule 1, a
claim by the contractor is limited to that sum [no sum is shown in item
18 of schedule 1]. If no sum or sums per day is shown, the contractor
is entitled to an adjustment to the *contract price equal to the loss,
expense or damage it incurs as a result of the approval of an
adjustment by the architect to the date for *practical completion.
H6 Architect may adjust contract in absence of claim
.1 If the contractor has not made a *claim to adjust the contract in
relation to any change which results from complying with any
instruction under section J for a *variation or from causes of delay
noted in clause L1 or L2, the architect may adjust the contract at any
time up to the issue of the final certificate under clause N11, or a
certificate under clauses Q9 or Q17.
J Variation to the works
J5 Adjustment to the contract after written instruction to proceed
.1 If the architect issues a written instruction to proceed that confirms
acceptance of a quotation, the architect must adjust the *contract price
and the date for *practical completion (if applicable) in accordance
with the quotation in the next certificate.
L Adjustment of time
L1 Causes of delay which entitle making a claim for adjustment of
time with costs
.1 The contractor may make a claim for an adjustment to the date for
*practical completion and *adjustment of time costs in respect of a
delay affecting *working days, caused by:
b the owner failing to give [access to] the *site in accordance with
clause F1
c an architect's instruction
.4 The requirements for making a *claim to adjust the contract and the
procedures to be followed are stated in section H.
L2 Causes of delay which entitle making claim for adjustment of time
without costs
.2 The requirements for making a *claim to adjust the contract and the
procedures to be followed are stated in section H.
L6 Overlapping delays
.1 Subject to clauses L4 and L5, when one or more *critical construction
activities are delayed by more than one cause at the same time, the
architect must assess and *claim to adjust the contract in accordance
with this clause L6.
[2023] VCC 516
14
JUDGMENT
M Completion of the works
M1 Practical completion
.1 The contractor must bring the*works to *practical completion by the
date for *practical completion shown in item 22 of schedule 1 is
adjusted in accordance with this contract. The *works are at *practical
completion when, in the reasonable opinion of the architect:
a they are substantially complete and any incomplete *necessary
work or *defects remaining in the *works are of a minor nature
and number, the completion or rectification of which is not
practicable at that time and will not unreasonably affect
occupation and use
b all commissioning tests in relation to the plant and equipment
shown in item 23 of schedule 1 have been carried out
successfully and
c any approvals required for occupation have been obtained
from the *relevant authorities and copies of the *official
documents evidencing the approvals have been provided to
the architect.
.2 Subject to clause M11, the owner takes possession of the *works at
4.00pm on the date the architect issues the notice of *practical
completion.
M8 Possession of the *works before *practical completion
.1 If the owner takes possession of the *works before the architect issues
the notice of *practical completion, the *works are to be treated as
having reached *practical completion. The architect must issue to the
contractor and to the owner a notice of *practical completion within five
*working days after being notified in writing that the owner has taken
possession, unless clause M4 applies.
.2 If the owner takes possession of the *works before the architect issues
a notice of *practical completion, the contractor may make a *claim to
adjust the contract.
.3 The requirements for making a *claim to adjust the contract and the
procedures to be followed are stated in section H.
M9 Liquidated damages may be payable
.1 If the *works have not reached *practical completion by the date for
*practical completion as adjusted, the architect must *promptly notify
the contractor and the owner in writing of the owner’s entitlement to
liquidated damages.
.2 Up to 20 *working days after the date of issue of the notice of
*practical completion, the owner may notify the architect in writing
whether it will enforce its entitlement to liquidated damages against
the contractor.
.3 The contractor is liable to pay or allow to the owner liquidated
damages at the rate shown in item 24 of schedule 1.
M10 Deduction of liquidated damages
.1 If the owner notifies the architect in writing under clause M9, then the
architect must:
a notify the contractor of the owner’s decision within one
*working day, and
b deduct liquidated damages from the next and subsequent
progress certificates as applicable.
.2 If, after the architect has issued a certificate in which an allowance for
the owner’s entitlement to liquidated damages has been made, an
adjustment is made to the date for *practical completion, with the
result that the owner’s entitlement to liquidated damages is altered, or
[2023] VCC 516
15
JUDGMENT
the owner has advised that it no longer wishes to enforce its
entitlement to liquidated damages, the architect must make an
appropriate adjustment in the next certificate.
M11 Contractor to correct *defects and finalise *necessary work
.1 The contractor must correct any *defects or finalise any incomplete
*necessary work, whether before or after the date of *practical
completion, within the agreed time as stated in an instruction or if no
time is stated, within 10 *working days after receiving a written
instruction from the architect to do so.
N Payment for the works
N4 Progress claims - procedure for architect
.4 If the architect reasonably needs additional information to assess the
claim, the architect must *promptly ask the contractor for it. If that
information is needed to assess only part of the claim, the architect
must assess the rest of the claim.
S Definitions
S1 Definitions
claim to adjust the contract a claim made to the architect to adjust the
*contract price (including *adjustment of time
costs) or the date for *practical completion or
both
Issues
30 The key issues at trial were:
(a) Can UCP dispute PC 16 Rev A and the decisions of the architect pursuant
to the Contract?
(b) Can UCP dispute PC 16 Rev A and the decisions of the architect due to the
conduct of the architect?
(c) How should the disputed variations be resolved?
(d) Is PHHH entitled to liquidated damages in the amount certified or some
other amount?
(e) Is PHHH entitled to damages for defective work by UCP?
31 These issues will be dealt with in turn below.
[2023] VCC 516
16
JUDGMENT
Can UCP dispute PC 16 Rev A and the decisions of the architect pursuant to the
Contract?
32 It is not in dispute that the form of PC 16 Rev A is valid and will bind the parties
unless it is tainted by fraud, collusion or other misconduct.
3
However, UCP seeks
in effect to re-open the decisions of the architect that are (ultimately) reflected in
PC 16 Rev A on either or both of two grounds. UCP’s primary ground is that the
architect’s certifications are tainted by misconduct. But it says that if the court
rejects its contentions on this ground, the question remains justiciable. It relies
for this purpose on a finding by Senior Member R Walker in Allmore
Constructions Pty Ltd v K7 Property Group Pty Ltd
4
(“Allmore”). The second
ground is more straightforward, so I turn to this first.
Contract construction
33 Clause H6 is set out above. It provides in effect that if UCP has not made a claim
to adjust the Contract in relation to any change which results from a variation to
the works or an EOT, the architect may adjust the Contract at any time up to the
issue of a final certificate.
34 In its written reply submissions, UCP sets out the following passage from Allmore
(emphasis added):
5
“In case I should find the claims made were not in accordance with the
requirements of the Contract, counsel for the Builder relied upon Clause
H6 of the Contract and submitted that, since a final certificate has not
been issued, it is open to me to allow an extension of time pursuant to
that clause, even though the requirements of the Contract were not
complied with. The full wording of that clause is set out in paragraph 23
above. The power is available If the Contractor has not made a claim to
adjust the Contract in relation to any change…’ of the nature described,
and if it is available, the Architect is empowered to ‘…adjust the Contract
at any time up to the issue of the final certificate…’
Since no final certificate has been issued it is submitted on behalf of the
Builder that the power conferred by this clause may still be exercised
and that it is open to me to exercise it now.
3
LexisNexis, Halsbury’s Laws of Australia (online at 7 December 2021) 65 Building and Construction,
III Performance at [65-865].
4
[2016] VCAT 1770.
5
[2016] VCAT 1770 at [150]-[151] and [162]-[163], per Senior Member R Walker.
[2023] VCC 516
17
JUDGMENT
I think the fallacy in this argument [that H6 applies] is that a claim is
either a valid claim for an extension of time or it is not. If it is valid, then
recourse need not be had to Clause H6. It is invalid, then a claim for an
extension of time has not been made because the requirements for it
have not been satisfied. If the requirements have not been satisfied it is
not a claim of the nature contemplated by the Contract.
It seems to me that I am now standing in the shoes of the Architect and,
if I consider that it would be fair and reasonable to grant any of the
extensions of time that are sought, I should do so. I should therefore look
at each of the claims on the merits rather than ignore them on the basis
that the contractual procedures were not followed. That is not to say, of
course, that the procedures set out in the Contract should be ignored by
the Builder. As was pointed out in the case cited, if a timely claim has not
been made, and the ground on which an extension of time is claimed is
now difficult to decide because of the time that has elapsed since the
time the claim should have been made, that may be a ground on which
an extension should fairly be refused. However that does not appear to
be the case here”.
35 UCT next submits as follows (references omitted):
“Palma’s evidence regarding the EOT claims is that the claims did not
comply with the contractual requirements because there had been no
service (or no service in a timely manner) of a Notice of Likely Delay…
Alternatively he contends that a claim was not made under the Contract.
On the Owner’s case, the EOTs were either not valid claims under the
Contract, or the claims were simply not made. In either case it is
submitted that the Court can, as the Tribunal did in Allmore
Constructions, assess the merits of the EOT claims. The Owner cannot
have its cake and eat it as well.
In any event, and contrary to the Owner’s Closing Submissions, PC 16
Rev A was the subject of a notice of dispute. On 1 September 2017, the
Owner issued a notice disputing the Architect’s failure to issue a
certificate In response, on 4 September 2017 the Architect issued PC 16
Rev A. On 8 September 2017, the Builder sent an email to the Architect
and the Owner disputing PC 16 Rev A. Therefore, it cannot be argued by
the Owner that the subject matter of PC 16 Rev A is not justiciable under
the Contract (leaving aside that it may be justiciable for other reasons).”
36 This argument based on the findings in Allmore was developed for the first time
in UCP’s written reply submissions, and was therefore not the subject of
submissions on behalf of PHHH until oral closing submissions. Those
submissions approached the issue as essentially one of construction of clause
H6, in the context of the Contract as whole. The effect of PHHH’s submissions
(as I understood them) was as follows:
[2023] VCC 516
18
JUDGMENT
(a) The expression “claim to adjust the contract” is defined by the Contract as:
“a claim made to the architect to adjust the *contract price (including
*adjustment of time costs) or the date for *practical completion or both”
(asterisked terms are defined terms).
(b) Thus a “claimis simply a demand to adjust one of those two things it is
not circumscribed by time, nor by whether or not it is accompanied by
particular information.
(c) Clause H1 of the Contract deals with timing and clause H2 sets out the
details that the claim must contain, but these are not pre-requisites as to
whether the claim qualifies as a “claim to adjust the contract”. Rather, these
are criteria for the architect to assess whether or not to approve the claim.
(d) Clause H3 sets out the process of that assessment and clause H4.1 obliges
the architect to issue its written decision specifying any adjustments within
20 working days after receiving the claim.
(e) Clause H4.2 expressly provides that UCP (emphasis added) “may dispute
the architect’s decision or a failure to issue a decision issued under this
clause in accordance with clause A8”.
(f) Clause A8 (set out in full above) is the exclusive regime for disputing
certifications of claims made it provides in clear terms that if a party fails
to give a notice of dispute under that clause “the party will not be entitled to
dispute the matter at all”.
(g) But a claim that fails because it is rejected by the architect or because the
contractor fails to dispute it as required by clause A8, is still a claim made. It
is analogous to a claim under a claims-made insurance policy. There may
be other conditions precedent to indemnity or other conditions or
exclusions, but an excluded claim is still a claim.
[2023] VCC 516
19
JUDGMENT
(h) The effect of UCPs submission is that a claim that (for example):
(i) is out of time under clause H1;
(ii) fails to include the necessary details under clause H2; or
(iii) the contractor fails to dispute under clause A8,
ceases to be a “claim to adjust the contract within the meaning of the
Contract, and thus becomes amenable to an adjustment under clause H6
by the architect, or by the court standing in the shoes of the architect.
(i) This defies common sense. It essentially means that, by the contractor’s
recalcitrance or delinquency, it gets a second chance to pursue its claims.
This, in turn, would mean that a court or VCAT would be routinely called on
to exercise the role of the superintendent under clause H6 (or its
equivalents) wherever a significant dispute develops between parties to a
standard building contract.
(j) Allmore is wrongly decided. First, contrary to the Senior Member’s finding, it
gets no support from the decision of the NSW Court of Appeal in Peninsula
Balmain Pty Ltd v Abigroup Contractors Pty Ltd
6
(“Peninsula Balmain”). The
clause under consideration in that case is markedly different from clause H6
of the Contract.
(k) Second, the wording of clause H6 could hardly be clearer it is only
engaged if a contractor has not made a claim. The clause does not say: “If
a contractor has not made a valid claim”.
(l) Properly construed, clause H6 operates to “sweep up” potential claims
under the Contract’s variation or EOT regime, where (for example) the
making of a claim has been overlooked. It does not apply where a claim has
6
[2002] NSWCA 211.
[2023] VCC 516
20
JUDGMENT
been made but rejected because the requirements for it have not been
satisfied.
(m) Here, the court is not entitled to adjust the contract price in the shoes of the
architect pursuant to clause H6 as the adjustments sought by UCP were all
submitted to the architect during the course of the Contract and rejected.
37 The principles of construction that are to be applied to a commercial contract like
the Contract are well established.
7
In determining the meaning of the terms of a
commercial contract, it is necessary to ask what a reasonable businessperson
would have understood those terms to mean. That inquiry will require
consideration of the language used by the parties in the contract, the
circumstances addressed by the contract and the commercial purpose or objects
to be secured by the contract. Unless a contrary intention is indicated, the court
is entitled to approach the task of giving a commercial contract a businesslike
interpretation, on the assumption that the parties intended to produce a
commercial result. Put another way, a commercial contract is to be construed so
as to avoid it making commercial nonsense or working commercial
inconvenience.
38 Applying these principles, I agree with PHHH’s submissions. In my view, the
language of clause H6 is clear. It is engaged only if the contractor has not made
a claim to adjust the contract (emphasis added). And “claim to adjust the
contract” is likewise clearly defined as “a claim made to the architect to adjust the
contract”. I can see no reason to read into that definition words to the effect that
the claim must be a valid or compliant claim. Indeed, doing so undermines an
important commercial object to be secured by the Contract. Namely, to create in
clause A8 an exclusive and self-contained regime for resolving disputes in
relation to an architect’s certificate or other decision (or lack of decision).
7
Electricity Generation Corporation v Woodside Energy Ltd (2014) 251 CLR 640; Mount Bruce Mining
Pty Ltd v Wright Prospecting Pty Ltd (2015) 256 CLR 104, per French CJ, Nettle and Gordon JJ at
[46]-[52].
[2023] VCC 516
21
JUDGMENT
39 Clause H1 specifies the time limits applicable to claims, clause H2 lists the
details that a claim must contain and clauses H3 and H4.1 govern the process
for the architect to request further information and assess the claim. Most
notably, clause H4.2 then provides that the contractor may dispute the architect’s
decision or failure to issue a decision in accordance with A8. Despite the use of
may in clause H4.1, clause A8 itself makes clear that the dispute procedure
under that clause is both mandatory and exclusive. Thus, in my view, “may” in
clause H4.2 denotes the contractor’s option to dispute or not dispute, not a
discretion as to the means of dispute.
40 Clause A8 provides that (emphasis added):
(a) if a party wishes to dispute a certificateissued by the architect, or to
dispute the failure of the architect to do something, the party must give
written notice under this clause within 20 working days; and
(b) if a party fails to give that notice, the party will not be able to dispute the
matter at all.
41 It would undermine the dispute regime provided for by these provisions if a
contractor who has made a claim within the meaning of the Contract and had
that claim rejected by the architect, can effectively sidestep clause A8 or, worse
still, reopen a dispute determined under clause A8, by resort to clause H6.
42 Further, it is not an answer to this concern to argue that clause H6 only becomes
available if the claim is invalid or non-complaint because (for example) it is to late
or incomplete. There could be any number of reasons (or combination of
reasons) why an architect may reject a claim. It makes no sense that one basis
for rejection (for example, insufficient supporting material) gives a contractor a
second chance of a claim, where another basis does not. This is particularly so
where the basis enlivening that second chance results from (in PHHH’s words)
the contractor’s recalcitrance or delinquency.
[2023] VCC 516
22
JUDGMENT
43 Turning to the decision in Allmore, I agree with PHHH that it is wrongly decided.
With respect to the Senior Member, I would make the following observations:
(a) In my view, the argument gets no support from the decision in Peninsula
Balmain. In particular, I would not describe the clause under consideration
in that case as “somewhat similar”. It provided:
“Notwithstanding that the Contractor is not entitled to an extension of time
the Superintendent may at any time and from time to time before the
issue of the Final Certificate by notice in writing to the Contractor extend
the time for Practical Completion for any reason.
(b) Thus, and in contrast to clause H6, it expressly confers on the
superintendent the power to extend the time for practical completion
notwithstanding that the contractor is not entitled to an extension of time.
Indeed, the Court of Appeal relevantly stated that (emphasis added):
“I accept that, in the absence of the superintendent’s power to extend
time even if a claim had not been made within time, Abigroup would be
precluded from the benefit of an extension of time and liable for
liquidated damages, even if delay had been caused by variations
required by Peninsula and thus within the so-called ‘prevention
principle’.”
8
(c) This aspect of the Peninsula Balmain decision was otherwise primarily
concerned with whether a superintendent was obliged to act honestly and
impartially in deciding whether to exercise this power and it was the Court
of Appeal’s approach in finding that the superintendent was so obliged that
found favour in later cases including Kane Constructions Pty Ltd v Sopov
9
(“Kane Constructions”).
(d) The Senior Member referred to submissions before him highlighting the
distinction between the clause in Peninsula Balmain and clause H6, but
does not directly address the argument. Nor does he deal with the
construction issue more broadly.
8
Peninsula Balmain at [78] per Hodgson JA, Mason P and Stein JA agreeing.
9
[2005] VSC 237.
[2023] VCC 516
23
JUDGMENT
(e) In particular, the Senior Member makes no reference to the dispute regime
under clause A8 and the implications for the operation of that regime of
reading “claim in clause H6 as applying only to a “valid” claim (that is, a
claim where the applicable pre-requisites have been satisfied).
44 UCP is seeking adjustment of the Contract price for variations and EOTs
submitted to the architect and already claimed by UCP during the course of the
Contract. UCP is not seeking to challenge the architect’s assessment of these
claims pursuant to clause A8 which in my view operates as the exclusive
dispute resolution mechanism for such disputes. It has belatedly asserted that it
did issue a notice of dispute under clause A8 in response to PC 16 Rev A, but
has not challenged PC 16 Rev A on that basis.
10
On the proper construction of
clause H6, UCP is therefore not entitled to an adjustment of the Contract price
for the variation and EOT claims subject of this proceeding pursuant to clause
H6.
Can UCP dispute PC 16 Rev A and the decisions of the architect due to the
conduct of the architect?
45 UCP submits that Mr Palma failed to act fairly and impartially in administering the
contract, resulting in the architect’s certifications being vitiated and of no effect.
In its closing submissions, UCP particularised a range of conduct on the part of
the architect. UCP begins by pointing to the longstanding relationship between
Insite Architects and PHHH. In particular, UCP relies on the following matters:
(a) Mr Honeyborne is a practicing accountant and by his various companies
had developed five separate childcare centres;
(b) three of those centres involved the sale of the site and the business, and
another two involved only the sale of the business; and
(c) three out of the five centres developed involved Insite Architects.
10
UCP’s application to amend its statement of claim to plead reliance on notices of dispute under clause
A8 was refused, as discussed below.
[2023] VCC 516
24
JUDGMENT
46 However, the bulk of UCP’s submissions on this issue concern the nature and
extent of the communications between PHHH and the architect in relation to
variation claims. These comprise:
(a) submissions focussing on particular variations;
(b) the way variation claims made by UCP to the architect were processed;
(c) the architects management and changes to the spreadsheet maintained by
the architect listing variations and their status over time (described during
the evidence as the variations register) (“variations register”); and
(d) the nature and the content of communications between PHHH and the
architect.
47 UCP also points to the architect’s handling of defects as demonstrating PHHH’s
efforts to influence the architect and the architect’s failure to act impartially.
Particular variations
48 Turning first to particular variations, UCP’s submissions about these include the
following:
CV 14
(a) On 20 July 2017, PHHH wrote to the architect raising issues with variations,
asserting that UCP is responsible for the cost of, among other things,
locating Telstra existing services, permits and fees. This is notwithstanding
the architect’s and PHHH’s own approval of the cost of locating Telstra
services a year earlier, as shown in the architect’s variation adjustment for
CV 14 dated 12 July 2106 and the variations register dated 22 July 2016.
CV 50
(b) On 2 March 2017, UCP issued CV 50, landscape drainage cell. According
to AI 419, CV 50 was to be assessed by a quantity surveyor. The Builder
performed the work.
[2023] VCC 516
25
JUDGMENT
(c) UCP submits that CV 50 remained “under review” from at least 5 April 2017
and on 25 July 2017, some four months after CV 50 had been claimed by
UCP, PHHH emailed the architect requesting “all the details of this claim”,
which the architect then proceeded to provide to PHHH.
(d) UCP notes that on 26 July 2017 PHHH emailed the architect as follows:
“Have a think about this and please discuss at length with Luc and Kim.
Before this variation gets approved
…Also if we have don’t the above as designed I would not have had the
crisis with regards to the drainage and inadequate drainage from the play
surfaces we had right at the end [sic].”
(e) UCP submits that on 22 August 2017, variation 50 was marked “additional
information” and then rejected on 23 August 2017. No quantity surveyor
assessment was arranged by the architect.
(f) I note in passing that UCP omits from its submissions the part of the email
of 26 July 2017 where Mr Honeyborne sets out in some detail the reasons
why he was concerned to ensure that the architect “have a think about” the
variation, including copies of extracts from relevant plans.
CV 64
(g) On 28 July 2016, AI 119 requested a quotation to install five additional
Braille exit signs to comply with the new standard NCC2016. This varied the
original specification. This was increased again to 18 signs as specified in
drawing A-50/2.
(h) The variations register of 5 July 2017 and 20 August 2017 showed CV 64
“ticked” as approved by the architect. However, the variations register dated
22 August 2017 bore an “x” against client approval and an “x” against
architect approval.
(i) Mr Honeyborne gave evidence that he had spoken with Mr Palma as to why
the variation had been approved. His evidence was that:
[2023] VCC 516
26
JUDGMENT
“I discussed with [Mr Palma] as to why this variation came about
when the items were in the original documents and tender
documents and then he went back and he said okay, and he
reviewed it and said well, then he must have been wrong to approve
it I didn't remonstrate with him. I discussed it and I said look, it's in
the tender documents…[The reason Mr Palma changed the
acceptance of that item was not] because I objected to it. It was
because I pointed out to him it was wrong to approve that.”
CV 66, 73 and 79
(j) Mr Honeyborne was asked in evidence about each of these variations,
which were shown as approved in earlier versions of the variations register.
But in the second version of the variations register of 22 August 2017, the
variations were changed to further information or rejected.
CV 94
(k) On 3 July 2017, PHHH wrote to the architect and UCP, agreeing to UCP
conducting overflow works at a price of $46,619 plus GST and to “pause”
liquidated damages for 4 weeks. The variations register dated 4 July 2017
shows CV 94 as under review at $7,500.00.
(l) The variations register is then updated to reflect the agreement. The
variations register dated 5 July 2017 has CV 94 under review at
$46,619.00.
(m) UPC submits that this was based on discussions Mr and Mrs Honeyborne
had with Amiens Consulting, “in which they falsely represented the works
only took 3 days to complete”. I note that these discussions (including the
alleged falsity of the representations) were not put to Mr or Mrs Honeyborne
in the course of their evidence.
(n) UCP submits that On 7 July 2017, in AI 545, the architect approved CV 94
Rev B (overflow works). However, it seems that there was some confusion
over whether an earlier requirement that the final price be subject to review
by a Quantity Surveyor still applied and there is also uncertainty over
[2023] VCC 516
27
JUDGMENT
whether PHHH’s offer to “pause” liquidated damages had lapsed. Mr
Honeyborne asserted it had.
(o) UCP then asserts that Mr Honeyborne wrote to Cherys Gatt of Insite
Architects on 26 July 2017, instructing her to “… discuss this at length with
Luc and Kim. Before this variation gets approved” and CV 94 Rev B then
became “not approved” in the variations register of 22 August 2017. UCP
submits that this was a change that “can only be explained by the architect
succumbing to pressure from PHHH”.
(p) However, as UCP itself later acknowledges (at paragraph 111 of its written
submissions) this email in fact related to CV 50, not CV 94 (see above).
Processing variations
49 UCP submits that Mr Honeyborne’s evidence establishes that:
(a) variations which were not yet carried out but were in contemplation were
often sent by Insite Architects to Mr Honeyborne;
(b) Mr Honeyborne and Insite Architects would then have a “lengthy
discussion… about what caused the variation and what ‘we’ could do about
it,” before Mr Honeyborne agreed to pay the variations;
(c) Mr Honeyborne would have variations brought to him by the architect and
Mr Honeyborne would then identify the kind of information he wanted before
he would agree to the variation;
(d) Mr Honeyborne would ask the architect for more information or ask the
architect to seek more information from UCP before he would resolve the
variation;
(e) where variations were not being assessed by the architect, it was because
Mr Honeyborne himself was seeking more information on the variation, and
would identify that further information;
[2023] VCC 516
28
JUDGMENT
(f) Mr Honeyborne would be given the variation and he would have the
opportunity to review the variation and discuss with Mr Palma whether the
architect was right or wrong in approving it;
(g) Mr Honeyborne would tell the architect what to do and it was Mr
Honeyborne that was challenging the decisions of the architect;
(h) Mr Honeyborne would get Mr Palma to “withdraw” his approval of
variations, but “not a lot”; and
(i) the normal process of assessing a variation involved the architect then
PHHH looking at it.
50 UCP argues that, for his part, Mr Palma:
(a) conceded that Mr Honeyborne purported to dictate to him how he should
assess the variations;
(b) acknowledged that his assessment was the same as what had been
directed by Mr Honeyborne a day earlier;
(c) only two variations were accepted by Mr Palma, the remaining variations
were accepted by his colleagues.
51 In relation to each of these submissions, I note that:
(a) before accepting that Mr Honeyborne purported to dictate how he should
assess the variation, Mr Palms stated: I assessed it and I was asking for
additional information. Mr Honeyborne does not dictate how I am to assess
the variations”;
(b) Mr Palma’s evidence was that he made his assessment independently of
Mr Honeyborne’s suggestions and it was in fact Mr Honeyborne who came
to the same conclusion as Mr Palma, not the other way around; and
[2023] VCC 516
29
JUDGMENT
(c) in the particular passage of transcript on which UCP relies for this
submission, I am satisfied that Mr Palma is limiting his answer to the period
during which he was on leave.
Variations register
52 In relation to the variations register more generally, UCP relied upon the
following:
(a) Mr Honeyborne was familiar with the variations register maintained by the
architect, and the iterations of the register were provided to him from time to
time.
(b) In the variations register dated 19 July 2017, some 20 variations had not
been assessed by the architect, many of these are highlighted in yellow on
the document. Two columns on the register provide for “Approved by
Architect” and “Approved by client”. CVs 58, 64, 66, 73, 79, 80, 81, 82, 83,
84, 85, 87, 89 and 90 are all approved by the architect and the column for
“Approved by client” is blank.
(c) Variations registers were produced by the architect dated 1, 9, 16, 20, 21,
22 June 2017. On 21 June 2017, many variations which were “under
review” are approved (CV 78 to 90 - CV 86 withdrawn). These approvals
are all later rejected on 22 August 2017.
Communications in relation to variations
53 UCP points to two communications by Mrs Honeyborne, which it suggests show
a willingness to subvert the proper conduct of the variations process. These are:
(a) on 19 December 2016, Mrs Honeyborne stated that she “had no choice” but
to sign CV 1, but wanted further investigations as to whether the hydraulic
engineer had been sent the landscape plans when they were completed in
2015, because she still wanted to determine where the “blame lays for this
blunder”; and
[2023] VCC 516
30
JUDGMENT
(b) on 16 February 2017, after the architect drew PHHH’s attention to the fact
that all shelving to the storerooms were nominated as “by others”, Mrs
Honeyborne directed the architect to “keep quiet” about it (although there is
no evidence that the architect acted on this suggestion);
54 UCP made similar observations about Mr Honeyborne’s antagonistic approach to
dealings with UCP. For example, upon receipt of a notice of mediation dated 24
July 2017, PHHH wrote to the architect stating: “Can you please tell Hamish
[UCP’s construction manager] to get lost. The EOT (sic) have been assessed
twice already yet he keeps coming back. Is there anything we can do to stop this
harassment”.
55 UCP is also critical of other aspects of the architect’s conduct in relation to
variations. For example, UCP submits that:
(a) while the Contract required the architect to identify what information was
required, the architect largely did not identify the information it required, and
failed to document any discussions he said he had where he asked for
further information;
(b) particular communications between Mr Honeyborne and Mr Palma showed
that Mr Honeyborne sought to dictate to Mr Palma how variations ought to
be assessed;
(c) the fact that Mr Palma’s final assessment of PC16 Rev A matched that of
PHHH showed that Mr Palma was influenced by pressure from Mr
Honeyborne; and
(d) Mr Palma’s was ignorant of various notices of dispute.
56 UCP also relies upon:
[2023] VCC 516
31
JUDGMENT
(a) meetings between the architect and PHHH’s lawyers in relation to progress
claims 15 and 16 (which it alleges showed further influence of Mr
Honeyborne in Mr Palma’s decisions);
(b) Mr Palma’s failure to meet UCP on or about 21 August 2017 to try and
assess variations being claimed; and
(c) Mr Palma’s alleged reversal of approved variations (after having discussed
those variations with PHHH).
Defects
57 Turning to the handling of defects, UCP submits that:
(a) in continuance of the pattern of behaviour exhibited by Mr Honeyborne in
relation to variations, on 16 July 2018, Mr Honeyborne directed the architect
to send notices of defects to UCP;
(b) Mr Honeyborne went on to say “I will be very cross if the builder gets away
with not having to make the repairs due to you not sending the notice out.
Don’t go blaming me as I was on leave”;
(c) that same day, the architect issued the following AIs:
(i) AI 648, requiring the Builder to rectify a water leak to the entry soffit
(CB4208-4211);
(ii) AI 649, containing a report prepared by Mr Naughton of VPCO Pty Ltd
dated 18 June 2018, referring to all defects; and
(iii) AI 650, attaching a report from Adams Consulting Engineers Pty Ltd
dated 20 June 2018, referring to drainage defects;
(d) two days later, on 18 July 2018, the architect issued AI 651, instructing
UCP to rectify the height of the balustrades, an alleged defect, by the end of
the defects liability period; and
[2023] VCC 516
32
JUDGMENT
(e) a great number of the defects identified in these AIs arose from defective
design, Insite were the designing architects and thus the architect’s and
PHHH’s interests were aligned in making design defects UCP’s
responsibility.
58 Based on the evidence summarised above, UCP asserts:
(a) requests for information were ultimately a mechanism used by PHHH (and
acquiesced to by the architect) to delay the assessment of UCP’s
variations;
(b) avoiding notices of dispute were also part of delaying the assessment of
variations (and their accompanying EOTs);
(c) ultimately the assessments of the variations could not be postponed any
longer, the parties were in dispute and had a payment claim before an
adjudicator, which was determined in favour of UCP;
(d) PHHH had no intention of paying the adjudicated amount and was
determined to have an assessment by the architect which would result in a
net payment to itself;
(e) in order to achieve this assessment, PHHH directed the architect and the
architect complied, to reverse previously approved variations, reject
variations which were long overdue for assessment, so called “under
review” and to adopt PHHH’s erroneous calculation of liquidated damages;
and
(f) PHHH could then use the certificate in its favour to offset against the
amount adjudicated by the adjudicator.
59 UCP argues that PHHH exercised “improper pressure, influence or interference”
upon Mr Palma. UCP further says that Mr Palma engaged in conduct which falls
short of the proper standard of fairness, independence and impartiality”.
[2023] VCC 516
33
JUDGMENT
Breach of clause A6.4 of the Contract
60 In its written reply submissions and oral closing submissions, UCP’s focus shifted
somewhat from that developed in some detail in its initial written closing
submissions. It describes Mr Palma’s alleged willingness to accede to PHHH’s
improper demands as a “secondary argument” and gives primacy to PHHH’s
express contractual obligation to uphold the architect’s independence. In
particular, UCP argues that:
(a) unlike most of the authorities where the court finds an implicit contractual
obligation on the part of the owner to ensure that its architect acts
impartially in carrying out certifications, in this case there is no room for
uncertainty or ambiguity;
(b) clause A6.4 of the Contract expressly imposes an obligation on the owner
to
ensure that the architect, in acting as…certifier, complies with this
contract and acts fairly and impartially, having regard to the interests of both
the owner and the contractor and not to compromise the architect's
independence in acting ascertifier”;
(c) the only basis on which any sensible builder would enter into an agreement
where the owner is engaging the certifier, is if the builder is assured that
there will not be any attempts to sway the certifier’s impartiality UCP has
accepted somebody who is in a prima facie position of conflict, but has
done so married with a promise by PHHH not to seek to place any pressure
or to do anything to rely upon that conflict;
(d) if PHHH breaches that obligation, it poisons the well of impartiality in a way
that UCP, in agreeing to that arrangement, legitimately expects will not
occur;
(e) PHHH’s own evidence establishes that it is seriously (and not merely
incidentally) in breach of clause A6.4 Mr Honeyborne acted consistently,
[2023] VCC 516
34
JUDGMENT
vigorously and repeatedly to attempt to compromise the impartiality of the
architect;
(f) PHHH had the right or the advantage of holding everyone to the process
laid down by the Contract but elected to suborn that process, and there is
no good reason to put PHHH back into the position it would have been if
this had not occurred;
(g) in those circumstances, PHHH can no longer rely upon the determinative
nature of the architect’s decisions UCP’s obligation to treat the architect’s
decisions as binding falls away, because the basis on which that obligation
was accepted by UCP has been defeated by PHHH’s conduct; and
(h) it is irrelevant that the architect manfully resisted such interference and
coincidentally came to the result being demanded. The contention is risible.
But even if it were not, [UCP] contracted for an assessment process that did
not lay itself open to question in that way”.
PHHH’s submissions
61 PHHH submits that the architect acted fairly and impartially. It distils the evidence
on which UCP relies into five broad categories:
(a) PHHH was keen to keep costs down;
(b) Mr Honeyborne and Mr Palma would discuss the variations, and Mr
Honeyborne would seek explanations for the variations;
(c) unbeknownst to UCP, Mr Palma adjusted his internal variations register;
(d) the architect arrived at the same calculation of liquidated damages as Mr
Honeyborne; and
(e) Mr Palma eventually did not admit the outstanding variations.
[2023] VCC 516
35
JUDGMENT
62 As to (a), PHHH submits it is “somewhat axiomatic” that an owner would not wish
to pay more than it has to for a project. But this does not inform whether it acted
improperly in achieving this end. Further, Mr Honeyborne’s evidence was that
PHHH’s financial position was not an issue albeit that he was keen not to pay
more than required.
63 As to (b), PHHH argues that Mr Honeyborne’s request for information does not of
itself evince the required degree of interference or influence, and does not affect
the architect’s independence.
64 As to (c), PHHH submits it is difficult to see how this evinces any relevant
conduct on the part of the architect. It argues that the registers were internal
documents, not seen by UCP at the relevant time and, at best, reflected the
architect’s view of the status of the variation claims from time to time.
65 It further contends that whatever the status of those internal documents,
variations that were approved or denied retained their status. The registers did
not alter that fact, and the Defendant had a contractual mechanism available for
it should it wish these matter to be determined. PHHH continues (references
omitted):
“Mr Palma’s evidence was clear insofar as he was awaiting further
information on these claims. Tellingly, Mr Potter gave credence to Mr
Palma’s evidence by saying the Defendant decided to stop providing the
information sought by Mr Palma in around late 2016/early 2017 (that is,
months before the impugned conduct), notwithstanding that he fully
accepted that without this the architect could not fulfil his function.
Further, it is noteworthy that event the Defendant’s own experts were
unable to assess many of the variation claims some three years plus
hence, and with the benefit of both a complete suite of documents and
(presumably) in circumstances where the defendant was not refusing to
provide further information…[O]f the variations assessed by the experts
in their joint report, thirteen were agreed as requiring more information,
which included CV 48, CV 50, CV 53, CV 55, CV 56, CV 58, CV 59 and
CV 62, which is the entirety of the variations cited by the Defendant in
paragraphs [108] and [109] of it Closing Submissions in support of its
allegations impugning the architect’s conduct.”
[2023] VCC 516
36
JUDGMENT
66 As to (d), PHHH says this is of no merit as this was a function of rudimentary
arithmetic.
67 PHHH does not address (e) directly, but submits in conclusion that:
(a) The conduct relied upon does fall foul of the indicia set out in Kane
Constructions (UCP has not attempted to characterise the conduct).
(b) UCP has failed to identify what is says the consequences are. Specifically,
and with respect to the focus on events in August 2017, what actions are
impugned and why?
(c) Even if the conduct satisfied the requisite standard, UCP’s claim would be
for breach of contract, and it has not pleaded such a claim.
(d) Even if UCP had pleaded a claim for breach of contract:
[T]he architect’s conducts was not causative of its loss and damage in
circumstances where (a) it had a contractual mechanism for challenging
variations, including failures to assess, (b) by its own evidence, it had
reached the conclusion in late 2106/early 2017 that the architect was not
independent, and (c) that, again by late 2016/early 2017, it had opted not
to provide any further information to the architect, notwithstanding that it
was aware that this was necessary for his assessment task.”
(e) Critically, in circumstances where UCP’s claims relate to claims made to
adjust the contract, clause H6 does not apply to the claims made.
68 In oral closing submissions, PHHH responded briefly to UCP’s submissions
relying on clause A6.4 of the Contract. I understood it to be submitting that,
regardless of PHHH’s obligation under that clause and its conduct, the court is
still required to make an objective assessment of whether the architect has in
fact been suborned. Further, in the case of an architect who can be assumed to
ordinarily act in a professional manner, it is going to take a reasonable amount of
effort to demonstrate that he has been suborned. PHHH also emphasised that
UCP must establish that is had suffered loss by reason of any conduct by PHHH
in breach of A6.4.
[2023] VCC 516
37
JUDGMENT
Analysis
69 The law regarding the architect’s role in the administration of a construction
contract is well established and was recently and conveniently summarised by
Digby J in V601 v Probuild,
11
The architect has two separate and distinct roles:
12
(a) to act as an agent for the principal; and
(b) to act as an independent assessor and certifier.
70 In the former role, the architect is to act in the principal’s best interests and in the
latter, the architect must ordinarily act independently and in an impartial and fair
manner so as not to advance the principal’s interests over that of the
contractor.
13
This is reflected in clause A6.2 and 3 of the Contract, which
provides:
“.2 The architect is appointed to administer this contract on behalf of the
owner and the owner warrants that the architect has authority to
administer this contract.
.3 The architect is the owner’s agent for giving instructions to the
contract. However, in acting as assessor, valuer or certifier, the
architect acts independently and not as the agent of the owner
71 The faithful performance of these two roles may give rise to tension.
14
72 As discussed above, in addition to the architect’s obligations to act
independently, under clause A6.4 pf the Contract, PHHH must ensure that the
architect discharges this obligation. If the architect does not act independently,
the architect’s certificates may be set aside.
15
A certificate which is produced by
fraud or improper collusion between the architect and a party is vitiated and has
no effect.
16
11
[2021] VSC 849.
12
V601 v Probuild [2021] VSC 849 at [238], citing Dixon v SA Railways Commissioner (1923) 34 CLR
71, 112.
13
V601 v Probuild [2021] VSC 849 at [239].
14
V601 v Probuild [2021] VSC 849 at [253], citing Peninsula Balmain.
15
V601 v Probuild [2021] VSC 849 at [253], citing Peninsula Balmain Pty Ltd v Abigroup Contractors Pty
Ltd (2002) 18 BCL 322.
16
V601 v Probuild [2021] VSC 849 at [253], citing Attorney-General v McLeod (1893) 14 LR (NSW) 246;
Perini Corporation v Commonwealth of Australia [1969] 2 NSWR 530; Redmond v Wynne (1892) 13
LR (NSW) L 39; 8 WN (NSW) 103.
[2023] VCC 516
38
JUDGMENT
73 Circumstances in which the architect’s conduct may be impugned cannot be
stated exhaustively.
17
Although, in Baulderstone Hornibrook Pty Ltd v Qantas
Airways Ltd,
18
Finkelstein J identified the following broad categories suggested in
Hudson’s Building and Engineering Contracts, 11
th
ed 1995: (1) where the
decision-maker has a special interest in the result; (2) fraud or collusive conduct;
(3) improper pressure, influence or interference by the owner; (4) conduct which
falls short of the proper standard of fairness, independence and impartiality; (5)
breach of contract or other act or omission of the owner having the effect of
preventing the builder obtaining a decision; (6) unreasonable refusal by the
decision-maker to consider the matter; and (7) taking improper considerations
into account.
74 In Kane Constructions, Warren CJ also cited with approval commentary in
Hudson’s Building and Engineering Contracts in Australia (“Hudsons”), as
follows:
“It is submitted that fraudulent motion is irrelevant in considering
[interference] which is sufficiently wide to cover any improper
interference with the certifier’s independence and function by either
party. It is, of course, both usual and proper for both parties to make
representations, however strongly worded, to the certifier upon any
matter or dispute upon which the contract requires him to certify. The
dividing line between such representations and pressure of an improper
kind is not difficult to discern in practice, and broadly speaking any
pressure or action which goes beyond representations confined to the
merits of the matter in question, or which does not expressly or impliedly
recognise the certifier’s ultimate right and duty to decide the matter
impartially on its merits, will be suspect.
19
75 However, her Honour went on to refer to a passage in Hudson’s relied on by
UCP in its reply submissions:
“No doubt where interference or pressure by an owner results in no
certificate being given, the prevention principle will apply but the cases
show that other forms of influencing or interference need only be such as
to cast doubt on the certifier’s independence...once the certifier’s
independence has become suspect, the courts will not concern
17
Baulderstone Hornibrook Pty Ltd v Qantas Airways Ltd [2003] FCA 174 at [89], quoted in V601 v
Probuild [2021] VSC 849 at [260].
18
[2003] FCA 174.
19
Kane Constructions at [620], citing Hudson’s at p822.
[2023] VCC 516
39
JUDGMENT
themselves unduly with the extent or degree of influence over the
certifier, or its precise impact on the certificate in question.”
20
76 Her Honour next provided a non-exhaustive summary of indicia for determining
whether the architect’s conduct is impugned (citations omitted):
“…when the superintendent allows judgment to be influenced; when the
superintendent is in a position whereby the certificate is deprived of
value; when the superintendent acts in the interests of one of the parties
and by their direction; when the position is misconceived and the
superintendent acts as mediator; when there is not sufficient firmness in
order to decide questions based on his or her own opinion; where
judgement and conduct are controlled by the principal; and where the
superintendent considers the assent of the principal to be necessary, has
ceased to be a free agent and does not give full disclosure of every
communication between the superintendent and the principal. Finally, the
superintendent may lose independence without actually intending to do
so or even without knowledge they have done so.
In relation to the principal, interference will arise where there is an
attempt to lead the superintendent astray in the interests of the principal;
and where there is correspondence and communication of an improper
character between the principal and the superintendent. In relation to the
contractor, interference will arise where the contractor has no knowledge
of the interfering conduct so as to prevent the builder raising the point.
21
Did the architect fail to act fairly and impartially?
77 Determining the answer to this question has not been easy. I accept that there
were aspects of the conduct of both PHHH and the architect that raise legitimate
questions about the latter’s independence. However, I have concluded on
balance that the architect did not fail to act fairly and impartially (or otherwise fail
to act independently) in carrying out his obligations as certifier under the
Contract. I am also not persuaded that that PHHH acted in breach of clause A6.4
of the Contract.
78 I accept that Mr Palma routinely passed UCP’s claims on to PHHH for comment,
and thereafter often engaged in unilateral discussions or communications about
the claims with Mr and Mrs Honeyborne (usually the former). However, this alone
20
Kane Constructions at [621], citing Hudson’s at p822.
21
Kane Constructions at [623]-[624], quoted in V601 v Probuild [2021] VSC 849 at [259].
[2023] VCC 516
40
JUDGMENT
does not constitute a lack of impartiality or independence. As observed in
Bailey’s Construction Law:
22
“The fact that the contract administrator may have communicated or met
with the owner unilaterally, to obtain the owner’s views on a matter in
respect of which the contract administrator is required to make a
decision, does not of itself suggest unfairness…A contract administrator
is not required unlike a judge to give the appearance of being
impartial. What matters is that the contract administrator is not actually
partial between the contracting parties, or at least there is not a material
probability of the contract administrator being biased.”
79 The learned authors of Building and Construction Contracts in Australia also
suggest that “the mere fact of private communications from principal to the
[architect] will not result in actionable breach.
23
80 Mr Honeyborne is an experienced property developer. As UCP submitted, he is a
practising accountant and has been involved in the development of five separate
childcare centres. He presented as someone with a detailed understanding of
construction practices and contracts, including the Contract. Mrs Honeyborne is
also generally familiar with construction projects and has considerable
experience in the regulation and operation of childcare centres. Further, I accept
PHHH’s submission that it is axiomatic that any owner would not wish to pay
more than it is obliged to for a project.
81 Against this background, the evidence that PHHH was diligent, pedantic and
persistent in ensuring that it only paid what the Contract required, is unsurprising.
And I reiterate part of the passage from Hudson’s cited in Kane Constructions
and set out above that (emphasis added): It is, of course, both usual and proper
for both parties to make representations, however strongly worded, to the
certifier upon any matter or dispute upon which the contract requires him to
certify”.
22
Julian Bailey, Construction Law (London Publishing Partnership, 3
rd
ed, 2020), 373.
23
John Dorter and John Sharkey, Building and Construction Contracts in Australia (Thomson Reuters,
online) at [7.500].
[2023] VCC 516
41
JUDGMENT
82 I accept that PHHH had a relationship with Mr Palma that went beyond this
project. It is likely that in the course of that relationship, Mr Palma came to
recognise PHHH’s expertise and concern to provide input in relation to all
aspects of the Contract, particularly any variations and EOTs that were likely to
impact the price. But I agree with PHHH’s submission that evidence of a pre-
existing or broader relationship is not proof of a lack of independence,
particularly if that relationship is primarily or solely professional.
83 Based on my observations of both Mr Honeyborne and Mr Palma, I am satisfied
that their relationship was entirely professional and not particularly close there
was no evidence of any personal dealings between them. I have no doubt that
Mr Palma respected Mr Honeyborne’s experience and opinions. However, Mr
Palma’s responses and general demeanour also suggested that he often found
Mr Honeyborne cantankerous, argumentative and difficult. Indeed, it is this factor
that has caused me the greatest difficulty in assessing this issue.
84 More particularly, I have asked myself whether Mr Palma’s frustrations in his
dealings with Mr Honeyborne might have led him to capitulate on some issues in
the face of Mr Honeyborne’s persistence, in order to avoid an argument. Had this
been the case, I would have been obliged to find that the architect had been
suborned by PHHH. Such a finding would have been mandated by Warren CJ’s
observation in Kane Constructions extracted above that the form of influence
“need only be such as to cast doubt on the certifier’s independence...once the
certifier’s independence has become suspect, the courts will not concern
themselves unduly with the extent or degree of influence over the certifier, or its
precise impact on the certificate in question”.
85 I have also considered in this context UCP’s submissions that (some citations
omitted):
Bad faithincludes circumstances where the owner has given
instructions to the contract administrator for the amount which he should
(under)certify, or as to the decision which he ought to arrive at, and the
contract administrator has acceded to the owner’s demand.
[2023] VCC 516
42
JUDGMENT
There are cases where evidence of the contract administrator’s conduct
casts sufficient doubt on the exercise of his judgment, so that the
conclusion may be drawn that he has not brought his own mind to bear
on the issue, and that his decision is invalid. It may therefore be prudent,
if not necessary in most cases, for a contract administrator to “repel
unworthy communications” made by the owner; that is, communications
made for the purpose of improperly influencing the contract
administrator.
Pullen v Gutteridge Haskins & Davey Pty Ltd [1993] 1 VR 27, at 62 the
Court of Appeal (Brooking, Tadgell and Hayne JJ) said:
‘…Architects are often submitted to pressure by proprietors in an attempt
to persuade them not to issue promptly a progress certificate to which the
contractor is entitled. Unhappily, this pressure is not always resisted.
Many architects exhibit timidity, and fail to administer the building
agreement correctly, by sending the progress certificate, not to the
builder, but to the proprietor. The objection to the sending of progress
certificates by the architect to the proprietor is not merely that the
particular provisions of the building agreement are not being observed but
also that the practice is symptomatic of an unhealthy dependence of the
architect upon his client’”
86 However, considering the evidence as a whole, I am satisfied that this is not what
occurred. My starting point in this conclusion is that I am satisfied that both Mr
Honeyborne and Mr Palma were truthful in their evidence. UCP did not submit
otherwise. There is no doubt that Mr Palma was at times frustrated and even
annoyed by Mr Honeyborne’s pedantic and nit-picking approach to compliance
with the Contract. But I am satisfied that Mr Palma was enough of a professional
to look past this and decide each of the claims on its merits, having regard to
both the content of each claim and any representations by (primarily) Mr
Honeyborne on behalf of PHHH.
87 I accept that Mr Palma frequently determined the claims consistently with the
position being advocated by PHHH. In my view this simply reflected the fact that
Mr Honeyborne had a good working knowledge of the tender process and
Contract and was often able to identify references in the plans or specifications
that supported his position. To my mind, Mr Honeyborne’s communications were
not unworthy in the sense envisaged in the extract from UCP’s submissions
above. For the most part, they comprised reference to relevant parts of the plans
and specifications and requests that the architect “have a think about” the claims
or seek further information or clarification.
[2023] VCC 516
43
JUDGMENT
88 Whether Mr Palma was persuaded by Mr Honeyborne’s representations or
independently came to the same conclusion is not to the point. (It is most likely to
have been a bit of both.) The only relevant question is whether Mr Palma’s
assessments and certifications were directed, overborne or otherwise improperly
influenced by Mr Honeyborne’s protestations. In my view, they were not. Mr
Palma forthrightly rejected the suggestion that he bowed to Mr Honeyborne’s will,
and I accept this evidence. I discuss in more detail below particular aspects of Mr
Palma’s evidence informing that conclusion.
89 Turning to UCP’s submissions identifying more specific instances of alleged lack
of independence or other impropriety, I find as follows:
Particular variations
(a) For the most part, UCP’s submissions on particular variations do little more
than recite the circumstances in which particular claims for variations were
made, the content or effect of PHHH’s response and the result. In some
cases, they highlight where the architect appears to have changed position
following receipt of PHHH’s response. However, I do not detect in them
anything overbearing, unworthy or otherwise improper.
(b) There is a sense in the submissions that the sheer number of instances
where the architect has taken a position consistent with that urged by
PHHH should be enough to establish a lack of impartiality. However, this is
not a sustainable basis for the findings urged upon me by UCP. It merely
reflects the significant number variation claims made, coupled with PHHH’s
practice of making “strongly worded” representations in response.
(c) The submissions also overlook the variation claims the architect approved
including, notably, variation 37, requiring PHHH to pay an additional
$167,608.54, discussed further below. I have referred in my summary of its
submission above to other gaps in UCP’s arguments on the particular
variations.
[2023] VCC 516
44
JUDGMENT
Processing variations
(d) These submission tend to discuss the processing of variations from PHHH’s
perspective. In that respect, they merely reflect the undeniable fact that
PHHH was routinely questioning most of the claims and making
representations as to why they should not be accepted.
(e) To the extent that they assert that PHHH was dictating when further
information was needed and what it should comprise, I accept Mr Palma’s
evidence that he ultimately satisfied himself about the need for further
information. This included his assessments after his return from leave when
he reviewed preliminary decisions made by other Insite Architect staff in his
absence.
(f) I also note and agree with PHHH’s submission extracted above to the effect
that:
(i) Mr Potter of UCP effectively conceded that it decided to stop providing
the information sought by Mr Palma in late 2016 and early 2017; and
(ii) the impediments this created for the architect’s assessment of the
claims was echoed in the expert evidence.
Variations register
(g) I agree with PHHH that it is difficult to see how this evinces any relevant
conduct on the part of Mr Palma. The variations register was an internal
working document which merely tracked the status of variations claimed by
UCP a “tick” in the “Approved by architect” column did not constitute
actual or formal approval of a variation.
(h) The variations register was not seen by UCP in the course of the project. It
at best reflected the architect’s view of variation claims from time to time,
and a record of PHHH’s position (hence the need to supply it to PHHH from
time to time). Mr Palma’s evidence was that the variations registers were
[2023] VCC 516
45
JUDGMENT
“essentially an accounting document updated progressively”. I accept this
evidence.
(i) I accept that there were numerous variations that were changed from
“under review” to “approved” in the register dated 21 June 2017, but then
“rejected” by the version dated 22 August 2017. However, I am satisfied
that this is explained by the fact that the relevant changes to “approved”
were mostly made by Insite Architect staff while Mr Palma was on leave,
and Mr Palma made the further changes following his return from leave,
having considered Mr Honeyborne’s representations.
(j) Further, many of those late rejections occurred (at least in part) as a result
of insufficient supporting information. As noted above, UCP concedes that it
had stopped providing information sought by Mr Palma from late 2016 or
early 2017.
Communications in relation to variations
(k) The tone and content of some of the emails from Mr and Mrs Honeyborne is
regrettable. However, there is no evidence that Mr Palma paid it any regard
or that it otherwise infected his independence as certifier.
(l) Mrs Honeyborne’s suggestion that the architect “keep quiet” about shelving
to storerooms [CB 10437], gets closest to the type of communication that
might amount to an attempt to suborn the architect, but there are difficulties
with UCP’s reliance on this email. It was not put to either Mr or Mrs
Honeyborne as having the effect alleged (or at all) and Mrs Honeyborne is
not a director or officer of PHHH. Its status is therefore too uncertain to
justify a finding of impropriety against PHHH.
(m) I have referred above to the suggestion that Mr Honeyborne sought to
dictate to Mr Palma how variations ought to be assessed. In my view, Mr
Honeyborne’s language was comfortably within the category of “strongly
[2023] VCC 516
46
JUDGMENT
worded representations” which the authorities accept as being “both usual
and proper”. Further, I have accepted Mr Palma’s evidence that he was not
in any way cowed by Mr Honeyborne’s somewhat strident approach to his
communication.
(n) On the issue of Mr Palma’s final assessment of PC16 Rev A matching that
of PHHH, I agree with PHHH’s submission that this was a function of
rudimentary arithmetic. I am satisfied that the other matters relied on by
UCP in this category are either not made out or do not evidence relevant
impropriety or lack of independence.
Defects
(o) My findings above apply equally to UCP’s submissions in this category. It is
commonly the case that the owner detects defects and requests that the
architect send notices of defects to the builder accordingly. The fact that Mr
Honeyborne might have done so in directive language does not alter the
fundamental character of what is essentially a routine communication.
(p) Equally, it is unsurprising that the architect would err on the side of caution
in notifying defects that might arguably manifest as a design defect (in
whole or in part) rather than a builders defect there are mechanisms in
the Contract for resolving these types of issues.
(q) Further, I do not accept that the evidence supports the assertion that a
great number of the defects identified in these AIs arose from defective
design”. This is an open question, and I am not persuaded that any adverse
conclusions about the conduct of the architect can be drawn from the
number or the content of the defect notices issue by the architect to UCP.
Did PHHH breach clause A6.4 of the Contract?
90 I have found above that Mr Honeyborne’s communications in relation to variation
claims and defects were comfortably within the category of “strongly worded
[2023] VCC 516
47
JUDGMENT
representations” which the authorities accept as being both usual and proper.
More broadly, I am not persuaded that PHHH’s representations in opposing
variation claims were an attempt to sway Mr Palma’s partiality or “compromise
the impartiality of the architect”.
91 Putting aside the occasionally strident or intemperate language, in my view
PHHH’s representations were essentially doing no more that propounding an
argument as to why particular variation claims were not a variation within the
meaning of the Contract, including (where relevant) by reference to the plans and
specifications. And, as I have observed above, the language discussed in UCP’s
submissions does not alter the essential character of the representations. In
each case, their focus was the subject matter of the variation claims or the lack
of supporting information.
92 The owner’s obligation under clause A6.4 of the Contract is to ensure that the
architect in acting as certifier “acts fairly and impartially, having regard to the
interests of both the owner and the contractor”. Thus, to my mind, a breach of
clause A6.4 requires proof that PHHH was deploying tactics that were directed to
undermining the architect’s fairness and impartiality. In my view, articulating
contractual grounds for the architect to refuse a variation claim, no matter how
frequently this occurs, are not so directed. Rather, they are directed at the merits
of the claim and, to that extent, should inform rather than undermine an impartial
review of the variation.
93 The position would be different if there was evidence that the owner was relying
on ulterior grounds unrelated to the merits of the variation claims, or other
improper leverage, to sway the architect in its favour. Obvious examples would
be the offer of financial incentives (such as more work in the future) or threats
(such as withdrawing existing work). Depending on the circumstances, it may
also extend to intimidation and bullying. For the reasons above, I am not
persuaded that the evidence in this case is sufficient to support a finding that
[2023] VCC 516
48
JUDGMENT
PHHH’s conduct amounted to improper intimidation or bullying, or otherwise
amounted to a breach of clause A6.4.
How should the disputed variations be resolved?
94 As I have determined that the architect did not fail to act fairly and impartially,
and therefore the architect’s decisions cannot be re-opened under clause H6 of
the Contract (or otherwise), it is not necessary for me to determine any of the
disputed variations. If it were necessary for me to do so, I would determine in
relation to each of the variations as set out below. Except as stated in my
summary, these variation claims were either wholly refused or not accepted by
the architect.
Variations which the experts agreed
95 The experts agreed that variations 31, 50, 53, 64, 81, 82, 83 and 90 ought to
have been allowed. Given that the expert evidence in this regard is
uncontradicted and reliable, I would have allowed an adjustment for a total of
$45,368.65 to the contract price for these variation claims. For the variation
claims summarised below, unless I note otherwise, the experts agreed that each
was a variation, but disagree on the quantum.
Variation 48 Rev A
96 This variation relates to framing and fire rating the columns and exterior face of
wall GF North elevation. It was the subject of AIs 190, 489, 586 and 653. The
architect determined that additional information was required for the architect to
properly assess it and no adjustment was issued.
97 Mr Buchanan assessed the variation at $14,996, and Mr Jeffery at $3,359.38.
UCP submits that I should prefer the evidence of Mr Buchanan for several
reasons, including the following:
(a) Mr Buchanan has taken into account areas of work facing the wall and
bulkhead, whereas Mr Jeffery has not.
[2023] VCC 516
49
JUDGMENT
(b) Mr Buchanan provided a comprehensive breakdown of the costing in
support of his valuation.
(c) Mr Buchanan stated that all of the timber framing is new work, the whole of
the cladding around the exterior of the column is new work and the left of
the column you can see that there’s the top hats and the fire check and
ComTex lining noted below the sill levels.
(d) Mr Buchanan disagreed that the drawing put to him by PHHH in evidence
was the existing position.
98 For its part, PHHH submits that:
(a) Mr Jeffrey made it clear he went back to first principles when assessing the
time and labour required rather than applying an abstract, per metre
assessment;
(b) Mr Buchanan accepted in cross-examination that he assessed a scope of
works that included the original scope of works, and thus accepted that the
works would have been less than he assessed (though he could not
quantify that); and
(c) UCP relies on evidence and propositions not put to the experts (at [193]
and [196] of its closing submissions).
99 I found Mr Buchanan’s assessment of the works (and therefore the likely costs)
associated with this variation more thorough and therefore more persuasive. And
while he accepted that the extent of additional works would be less than he had
allowed, he premised this evidence with the statement: if the first drawing on
924 are the conditions that were in place as part of the original contract”. Mr
Buchanan could not say that they were, and I accept UCP’s submission that they
were not. PHHH argues that the drawings relied on by UCP to support this
submission were not put to the experts, but the relevant drawings were in
[2023] VCC 516
50
JUDGMENT
evidence, and they speak for themselves. I would have allowed Mr Buchanan’s
figure of $14,996 for this variation.
Variation 55
100 This variation relates to the increased height of the glass balustrade on level 1
from 1.5 metres, to 1.8 metres then 2.4 metres. It was the subject of Notice of
Likely Delay 20 and AIs 347 and 440. Mr Buchanan assessed variation 55 at
$20,468.62. Mr Jeffery assessed it at $15,908.87.
101 UCP submits that Mr Buchanan’s opinion should be preferred for reasons
including the following:
(a) Mr Buchanan has made due allowances for additional labour associated
with transporting and manoeuvring the larger sheets of glass, whereas Mr
Jeffrey does not.
(b) Mr Buchanan disagreed with Mr Jeffery’s proposition that a credit was
needed for a deletion of the steel base plate as “none of the documentation
identifies any reduction in the steel supports in relation to this change.
There is no explanation why a credit should be required or expected.
102 PHHH submits that the difference between the valuations of Mr Buchanan and
Mr Jeffrey came down to the proposition that larger sheets of glass might require
more labour, together with the deletion of a base plate. It points to Mr
Buchanan’s concession the difference between he and Mr Jeffrey was a matter
on which reasonable minds might differ.
103 I again prefer Mr Buchanan’s evidence on this variation. I am satisfied that the
significantly larger (and therefore heavier) sheets of glass necessary for the
higher balustrade would involve a materially higher labour cost. Mr Jeffrey made
no allowance for this. I am also satisfied that there is insufficient evidence of a
saving in the overall cost of steel componentry for the higher balustrades to
[2023] VCC 516
51
JUDGMENT
justify a credit. I would therefore have allowed this claim for the $20,468.62
estimated by Mr Buchanan.
Variation 56 Rev A
104 This variation relates to replacement of eight sets of door grills and was the
subject of RFI 177 and AIs 295 and 590. Mr Buchanan assessed the variation at
$3,939.90, and Mr Jeffery at $1,337.45. The amounts involved in these
assessments are small and the areas of disagreement between the experts as
summarised in the parties’ submissions are matters of degree and not
substance. On this variation claim, I would have split the difference between the
two amounts and allowed $2,639.00.
Variation 58 Rev A
105 This variation relates to the supply and installation of suspended ceiling to
external areas and was the subject of AIs 430, 484, 486 and 591 and variation
adjustment 58. Mr Buchanan considered that UCP’s claim of $10,350 was
reasonable. Mr Jeffery assessed the claim at $3,611. UCP submits that:
(a) The two experts have agreed on the materials, but have disagreed on the
amount of labour required.
(b) Mr Buchanan disagreed with Mr Jeffery’s rate of $37 per square metre,
allowing instead a “built up” rate of $91.05, after allowing for “extra over”
costs and furring channels giving a total value of $13,843.35.
(c) Mr Jeffery asserted that the work is just doing an extra little bit of area”, but
does not show the basis for that opinion.
106 PHHH argues that UCP has correctly identified the divergence between Mr
Buchanan and Mr Jeffrey; namely, the fact that the variation was not a quote for
a one-off job, but additional work carried out with workers already on site. PHHH
says that economies of scale ought to apply.
[2023] VCC 516
52
JUDGMENT
107 In my view, Mr Buchanan’s opinion is more soundly based. I accept that some
allowance for the fact that the work was done by workers already on site is
justified. However, Mr Jeffrey’s reduction for this seems too high and is not
adequately supported. I would therefore have agreed with Mr Buchanan that
UCP’s claim of $10,350 was reasonable and allowed that sum.
Variation 59
108 This variation relates to extra framing and trowelling to form bulkheads for
service pipes at the ground floor carpark and was the subject of AIs 485 and 592.
Mr Buchanan assessed the variation at $4,278 and Mr Jeffery at $2,139. UCP
submits that:
(a) The experts agree with the rate to apply, which is $80.50. Mr Buchanan
considers 40 hours to be reasonable as does Mr Quigley.
(b) Mr Jeffery undervalues the amount of labour required.
(c) Mr Buchanan has taken a more realistic approach with respect to the
additional works to be undertaken, whilst still making an appropriate
concession on the rate to be applied.
109 PHHH again notes that the difference in time allowed by the experts essentially
arises from the fact that the variation was not a quote for a one-off job, but
additional work carried out with workers already on site. It submits that the latter
approach (being that adopted by Mr Jeffrey), more correctly reflects the likely
cost to UCP of the variation. It argues that Mr Buchanan conceded it was difficult
to determine the hours required and he conceded this was a matter on which
reasonable minds could disagree.
110 While I agree with PHHH that some allowance for the fact that the works would
be done by workers already on site, there is force in Mr Buchanan’s assessment
of the time likely to be taken by the work regardless of this allowance. Balancing
[2023] VCC 516
53
JUDGMENT
these competing arguments, I would have again split the difference between the
two assessments and allowed $3,258.50 for this claim.
Variation 62 Rev A
This variation relates to additional works to staircase 2 and was the subject of
AIs 215, 220, 230, 270, 378 and 593. Mr Buchanan assessed the variation at
$7,358.85 and Mr Jeffery at $6,199.65. The difference between these two
assessments is modest, and does not justify a detailed re-statement of the
parties’ submissions on this claim. I have considered these and determined that
Mr Buchanan’s assessment should be preferred. In particular, I accept Mr
Buchanan’s evidence that:
As far as I can make out from the original documentation, there was no
requirement for this magnetic hold open and that the cost to supply that
is the largest - is the reason for discrepancy. It requires to be installed to
hold the door open in the event of a fire and that has to be wired back to
the fire indicator panel and the fire control system so that it will operate in
a fire mode.” (T839 Line 8 15).
111 Further, Mr Buchanan’s report is supported by a Fire Engineering Report dated
11 November 2016, which indicates that the magnetic hold was the subject of a
variation. On this variation claim I would have allowed $7,358.85.
Variation 80
112 This variation relates to the bin store door and was the subject of AIs 306 and
311. The architect originally allowed an adjustment for this variation, but there is
some disconformity between the variations registers, Mr Palma’s statement and
the expert evidence as to the amount allowed. Mr Buchanan put it at $4,879.45.
Mr Palma’s evidence was that he agreed that his colleagues had correctly
assessed this as a variation while he was on leave but could not endorse the
value without additional information.
113 The differences between the experts on this variation claim echoes that of a
number of the other variation claims. Mr Jeffrey attributed his lower figure to his
labour rates being “based on somebody already on site” and different prices for
[2023] VCC 516
54
JUDGMENT
hardware. Having considered the basis for the assessments of both experts as
disclosed in their reports and evidence, I prefer Mr Buchanan’s assessment. It is
both more thorough and reasoned than Mr Jeffrey’s. I also note that it is closer to
the original allowance by Insite Architects, until that was withdrawn pending the
provision of further information. I would therefore have allowed $2,868.12 for this
variation claim.
Variation 84
114 This variation relates to the cost of employing cleaners on site before open days
and was the subject of variation adjustment 84. The architects approval and later
withdrawal of approval for this variation followed the same path as Variation 80
discussed above.
115 Mr Buchanan’s assessed the variation at $2,576, based on UCP’s claim for 64
hours of additional services, but at a lower hourly rate than that claimed by UCP
(that is, $35 per hour rather than the $75 per hour claimed). Mr Jeffrey did not
assess the variation in his report. However, in his oral evidence, Mr Jeffrey
agreed with Mr Buchanan that a rate of $35 per hour was fair and reasonable. Mr
Jeffrey was unable to comment on the 64 hours figure.
116 Mr Buchanan accepted in his oral evidence that his assessment of
reasonableness was as to the hourly rate, rather than as to whether or not the
works were done and the purpose of the works. However, there was no real
dispute that the claim should be allowed Mr Palma agreed in his witness
statement that his colleagues at Insite Architects were correct in accepting the
claim, but he could not endorse the value without further information. I interpolate
that, based on Mr Buchanan’s assessment that the hourly rate claimed by UCP
was more than double what was reasonable, it would appear that Mr Palma’s
request for more information was justified.
117 There is no evidence that UCP’s allowance of 64 hours of additional services
was excessive and Mr Buchanan was content to adopt that figure. I am therefore
[2023] VCC 516
55
JUDGMENT
content to accept Mr Buchanan’s assessment and would have allowed this
variation claim at the $2,576 assessed by Mr Buchanan.
Variation 88
118 This variation relates to fire indices of artificial turf and was the subject of AI 611
and variation adjustment 88. The architect’s variations register dated 22 August
2017 shows this as approved for $3,105, but the register dated the following day
records the variation as “not approved”. Mr Buchanan assessed the variation at
$3,105. Mr Jefferey did not assess this variation in his report, but noted in the
joint report following the expert conclave that he would need to see the relevant
invoice and fire report. In his evidence, he doubted the need for the fire indices,
but agreed that the value ascribed was “possibly” reasonable.
119 There seemed to me to be no real dispute among the experts that (if required)
this was a variation and the $3,105 value claimed by UCP was reasonable.
PHHH submits that no evidence was led that UCP needed to carry out these
works. I disagree, despite my reservations more generally about Mr Quigley’s
evidence, on this issue he did carry out an investigation about whether there
were standard fire indices available from the manufacturer and concluded that
“there were no fire indices available from the manufacturer”. To my mind that is
sufficient evidence that UCP was required to seek the opinion of a fire engineer
and I would have allowed this claim in the amount of $3,415.50 (being the $3,105
plus builder’s margin and GST).
Variation 89
120 This variation relates to the fire compartmentalisation between floors and the
requirement for a design accessibility report. It was the subject of AI 612 and
variation adjustment 89. It is similar to variation 88, in that Mr Jeffrey agreed that
Mr Buchanan’s view that the amount claimed of $2,785 was reasonable, “if it was
proved”. As to that, Mr Buchanan states in his report that UCP had submitted a
copy of the Fire Engineer’s invoice for $2,500 for revisions to the Fire
[2023] VCC 516
56
JUDGMENT
Engineering Report with the variation submission and the invoice appeared to
be in order. On that basis, it is likely that I would have allowed this claim for the
$2,785 determined by Mr Buchanan.
Variation 99
121 This variation relates to a CitiPower shutdown for painting of external façade. It
seems that this was one of two CitiPower shutdowns, but at the time the
evidence (including the expert evidence) about this variation was being given,
there was real uncertainty about whether this was a duplication of an earlier
CitiPower shut down claim. Mr Jeffrey’s evidence was to the effect that he could
not be satisfied that it was a distinct shutdown and was therefore not willing to
accept it as a variation. However, he agreed that if a second shutdown was
proven, Mr Buchanan’s assessment of the variation at $11,119.12 would be
correct.
122 UCP submits that it has since established by the documents in Tranche 14 that
there were two distinct CitiPower shutdowns, the first relating to an increase in
the height of the balustrade and claimed as part of CV 55, and this second one. It
seems the Powercor invoices for each were in identical amounts. It submits that
these documents show that UCP did in fact incur two separate power shut down
fees of $10,635.65 each. PHHH resists the late introduction of the Tranche 14
document and submits that, without those documents, UCP has failed to prove
the second shutdown.
123 For the reasons below, I refuse UCP’s tender of the Tranche 14 documents.
Further, I agree with PHHH that, in the absence of the evidence supplied by
those documents, UCP has failed to establish that CV 99 related to a separate
and distinct shutdown. Like Mr Palma, I am not satisfied (on the balance of
probabilities) that two Powercor invoices in identical amounts were rendered to,
and paid by, UCP.
[2023] VCC 516
57
JUDGMENT
Variation 94 Rev B
124 This variation relates to play area drainage overflow. As noted by UCP in its
submissions, this was the subject of a number of emails passing between the
architects, PHHH and UCP. The architect initially instructed UCP to proceed with
the work on the basis that the claim amount would be reviewed and approved by
a quantity surveyor. However, UCP refused to proceed with the variation works
on this basis. What happened thereafter is conveniently summarised in PHHH’s
written submissions in relation to this variation. I accept that summary, and agree
with PHHH that UCP has not established that any concluded agreement was
reached on $45,419 claim by UCP.
125 Turning to the expert evidence on the value of the variation, UCP relies upon the
assessment of Mr Quigley, at $45,419 and Mr Jeffery assesses the variation at
$8,607.75. UCP submits that Mr Quigley’s assessment should be preferred
essentially because the plumbing component alone (excluding builder works in
connection or BWIC) was quoted by the project plumber at $12,050 ex GST,
and the BWIC excluded from the plumbers’ quote were extensive.
126 PHHH submits that:
(a) Mr Palma gave evidence that the reason he did not approve the quantum of
the variation and wanted it assessed by a quantity surveyor was that he
considered it was worth around $7,000, not the $45,000 being claimed;
(b) Mr Palma confirmed he had a quantity surveyor assess it at around
$7,390.00;
(c) Mr Palma confirmed an invoice was never received reflecting the amount
claimed (either from UCP or a third party);
(d) Mr Jeffrey assessed the claim independently at $8,607.00;
(e) Mr Buchanan did not assess the claim;
[2023] VCC 516
58
JUDGMENT
(f) contrary to UCP’s submissions, in oral evidence Mr Quigley accepted that
he did not assess the variation; rather, he premised his opinion on the
assumption that the parties had agreed to the $45,419; and
(g) Mr Quigley also confirmed in his oral evidence he did not disagree with Mr
Jeffrey’s calculations.
127 I accept PHHH submissions above, and note that Mr Quigley evidence on this
issue is a good example of his tendency to vacillate and opine on issue outside
his core expertise, discussed further below. Thus, in the absence of any
assessment of this variation by Mr Buchanan, I would have accepted Mr Jeffrey’s
valuation of the variation at $8,607.75.
Variation 96
128 This variation relates to the demolition of a glass block wall located on level 1
east. The issue here is whether the relevant drawing (drawing A-11/1) shows that
the glass blocks are to be demolished. If so, the work to demolish the glass block
window is within the original scope of works and not a variation. Mr Buchanan
valued the claim at $2,668, but accepted that he was not opining on whether it
was within the scope of works. Mr Jeffrey considered that it was within the
original scope of works, and thus not a variation. However, he did not take issue
with Mr Buchanan’s valuation. Mr Quigley’s report does not deal with the correct
interpretation of drawing A-11/1, but in his oral evidence he said: “it’s quite
clearly represented graphically in a different way to two parallel dotted lines
which is the code for existing walls and windows and doors that are to be
demolished”.
129 The drawing in evidence is not sufficiently clear for me to form a concluded view
based on the drawing alone as to whether or not the lines representing the glass
block wall are marked for demolition. However, it is clear from Mr Jeffrey’s report,
that he gave close consideration to the relevant part of the drawing (including by
extracting a section of it in his report) and set out in detail the basis for his
[2023] VCC 516
59
JUDGMENT
conclusion. In my view, Mr Jeffrey’s report and evidence is considerably more
comprehensive and considered on this issue than Mr Quigley’s report, and
therefore more persuasive. I therefore agree with Mr Jeffrey that variation 97 was
not in fact a variation.
Variation 26 and 30
130 These variations are agreed by the parties as being the subject of dispute in the
proceeding, but were not the subject of evidence (except by Mr Buchanan) or
submission (except to the extent UCP confirmed its claim in respect of these
variations in a table at [282] of its written submissions). In both cases, the
variations were approved by the architect, but for an amount less than the claim.
In relation to variation 30, UCP claimed $26,723.00, the architect approved
$25,607.90 and Mr Buchanan valued the variation at $25,803.89 (including the
builder’s margin). In relation to variation 26, UCP claimed $13,190.50, the
architect approved $7,759.00, and Mr Buchanan opined that UCP’s claim was
reasonable.
131 In the absence of any expert evidence or analysis to the contrary, I accept Mr
Buchanan’s valuation of these variations. The difference between that
assessment and the architect’s calculation on variation 30 is less than $300. I will
say no more about it. The difference on variation 26 is more substantial
($5,413.50), and thus my reasons for accepting Mr Buchanan’s assessment
warrants some explanation.
132 PHHH sought to challenge Mr Buchanan’s evidence on variation 26 in cross-
examination, by suggesting that his calculation involved a “large degree of
speculation” about the area affected by the work. Mr Buchanan accepted that
there was a lack of detailed information about aspects of the work and that he
had inferred a value against an area based on the engineer’s instruction.
However, I am satisfied that Mr Buchanan’s analysis and the inferences he drew
as explained in his report and confirmed in oral evidence were soundly based,
[2023] VCC 516
60
JUDGMENT
and would have supported a finding that variation 26 should be assessed at a
value $5,413.50 higher that the value approved by the architect.
Is PHHH entitled to liquidated damages in the amount certified or some other
amount?
133 As with the variations, having failed to persuade me that the architect’s
assessments (and notably that manifested by PC16 Rev A) are infected by a
failure to act fairly and impartially for the reasons set out above, UCP is largely
precluded from challenging the architect’s assessment of EOTs and liquidated
damages. I have nevertheless set out below for completeness a summary of my
findings on these matters.
Is PHHH is entitled to liquidated damages?
134 PHHH claims, and the architect certified, liquidated damages payable by UCP to
PHHH of $324,000, calculated as 162 calendar days at $2,000 per day (Item 24
of Schedule 1 of the Contract). The 162 calendar days is the difference between
the date PHHH alleges UCP was required to achieve practical completion (9
February 2017), and the certified date of practical completion (21 July 2017).
135 UCP submits that PHHH is not entitled to liquidated damages for two reasons.
24
First, because PC16 Rev A should be set aside, on the basis that the architect
did not act fairly and impartially (noting that the liquidated damages claim is
pleaded on the basis of PC16 Rev A alone). It is unnecessary for me to say more
on this issue, except to note that PHHH disputes the assertion that its claim to
liquidated damages relies only on PC16 Rev A. It submits that if it also pleads
liquidated damages based on an entitlement under the Contract and breach of
that Contract.
136 UCP’s second and alternative argument is that the contractual pre-conditions to
liquidated damages in clause M10.1(a) are not satisfied. This clause provides:
24
UCP had relied on a further ground for opposing the claim for liquidated damages, namely, that it is a
penalty, but abandoned this ground at trial.
[2023] VCC 516
61
JUDGMENT
“If the owner notified the architect in writing under clause M9 [PHHH may
notify the architect in writing whether it will enforce its entitlement to
liquidated damages against UCP], then the architect must:
(a) notify [UCP] of [PHHH’s] decision within *one working day…”
137 On this alternative ground, UCP submits a follows:
(a) On 16 April 2017 at 9.20am, PHHH notified the architect by email of its
intention to claim liquidated damages.
(b) On 18 August 2017 at 3.27pm, the architect issued notice under clause
M9.1 (AI578) stating that the works had not reached practical completion by
the date for practical completion and PHHH is entitled to liquidated
damages.
(c) The architect failed to comply with the mandatory requirement to notify the
Builder within one working day. This was not simply a technical breach: it
can be safely inferred that the reason for the failure was that the Owner and
the Architect were pursuing their joint agenda to ensure that PC Rev 16 A
was advantageous to the Owner, rather than it being a fair assessment.
138 PHHH makes several submissions in response. First, that UCP cannot rely upon
clause M10.1(a), as it raised this alternative ground for opposing liquidated
damages for the first time in closing. It was neither pleaded nor foreshadowed in
opening submissions. PHHH refers to r13.05 of the Rules, submitting that:
“By this rule an averment of the due performance of all conditions
precedent is implied in every pleading document for this case; and the
opposite party must specify distinctly any conditions, the performance or
occurrence of which will be contested. If the opposite party does this, the
condition precedent and its performance or occurrence are put in issue,
and the burden of proving the performance or occurrence is cast upon
the party pleading.” (citations omitted)
139 Second, PHHH submits that its entitlement derives from clause M9 of the
Contract, not clause M10. Clause M10 merely obliges the architect to provide
notification of a right that has already accrued under clause M9, and make the
necessary deduction from any progress claim: it is not a pre-condition to the
[2023] VCC 516
62
JUDGMENT
accrual of the right. Thus any failure to comply with clause M10 does not affect
PHHH’s entitlement to liquidated damages. PHHH adds (in effect) that this
construction is reinforced by the fact that, in contrast to clause M9, a notice
under clause M10.1(a) is not required to be in writing.
140 Third, PHHH submits that there is “ample authority”
25
for proposition that strict
compliance with notice provisions is limited to very specific circumstances and
does not apply to notice requirement in clause M10.
141 Finally, PHHH argues that the documentary evidence “immediately preceding
those impermissibly relied on by UCP, establishes that the architect provided
UCP written notice on 16 August 2017 (AI 573), and thus on the same day as the
architect received notice from the owner.
142 In my view, UCP’s alternative basis for opposing the claim for liquidated
damages must also be rejected essentially for the reasons submitted by PHHH.
Further, each of the grounds relied on by PHHH (with the possible exception of
the pleadings point) is by itself a sufficient basis for rejecting UCP’s submissions.
More particularly:
(a) Clause M9 is effectively self-contained. On its proper construction, the
builder’s liability to pay the owner liquidated damages arises once the
elements of that clause are satisfied, and clause M10.1(a) does not operate
as a condition precedent to liability. It defies commercial common sense to
suggest that the owner’s entitlement accruing under clause M9 is lost
forever if the architect fails to comply strictly with the notice requirements
under clause M10.1(a).
(b) Similarly, even if I am wrong on that construction, I agree with PHHH that
clause M10.1(a) should not be construed strictly. Such a construction gets
no support from the authorities or from the Contract as whole.
25
JPA Finance Pty Ltd v Gordon Nominees Pty Ltd (2019) 58 VR 393.
[2023] VCC 516
63
JUDGMENT
(c) It is strongly arguable that the notice comprised in AI 573 is sufficient notice
for the purposes of clause M10.1(a), notwithstanding the subsequent notice
comprised in AI 578.
(d) If contrary to (a) above, the notice under clause 10M.1(a) did operate as a
condition precedent to the builder’s liability for liquidated damages, on
balance I would agree with PHHH that r13.05 of the Rules in effect
precludes UCP from raising this issue for the first time in closing.
What is the quantum of PHHH’s liquidated damages?
143 The quantum of liquidated damages to which PHHH is entitled is the number of
calendar days (if any) between the date of practical completion and the date of
actual completion, multiplied by $2,000. Item 22 of the Contract relevantly
defines practical completion as “Possession of the site plus 195 Working Days
(Commencement Date to be confirmed)”. The date “16
th
March 2016” has been
handwritten and initialled as part of Item 22 (apparently signifying the confirmed
“Commencement Date”).
144 The parties’ submissions on this issue cover:
(a) the date UCP took possession of the site under Item 22;
(b) the adjusted date for practical completion having regard the EOTs;
(c) conduct of PHHH which it is alleged prevented UCP from completing the
works within the time (the “prevention principle”); and
(d) whether PHHH took possession of the works on a date before formal
practical completion, with the result that the works are to be taken as having
reached practical completion on that earlier date.
On what date did UCP take possession of the site?
145 It is an agreed fact between the parties that UCP took possession of the
premises somewhere between 16 March and 8 April 2016. PHHH submits it is
[2023] VCC 516
64
JUDGMENT
the former (the date the contract was signed) and UCP argues that it is the latter
(when UCP started work).
146 UCP submits that possession is provided for in clause F1, which in turn refers to
item 30 in schedule 1. It argues that on a proper construction of item 30, official
documents are required to begin the works and thus possession “is not simply
access to the site but defined by the contractor having the official documents (as
defined) that it required to commence the works”. UCP asserts that it undertook
only “site procurement work” between 16 March and 8 April 2016. It notes that
the architect did not give direct evidence about UCP’s possession of the site and
instead based his conclusions on a review of documents.
147 PHHH submits in response that the date of possession was 16 March 2016
(when the contract was signed). PHHH argues that UCP has misconstrued the
contract, as:
(a) clause A4.1a is expressly subject to subclause A2.1e, which obliges UCP to
“…obtain all official documents required under this contract to complete the
works and any shown in item 30a of schedule 1”;
(b) “official documents” includes “any…permit [and]…any document listed in
item 30 of schedule 1”;
(c) item 30 of schedule 1 differentiates between official documents required to
begin the works but to be obtained by UCP and those required to complete
the works but to be obtained by the owner; and
(d) accordingly, “it is clear that the owner providing a copy of the building
permit was not a precondition to the commencement of the works, or, more
importantly, for possession”.
148 PHHH further contends that:
[2023] VCC 516
65
JUDGMENT
(a) Mr Palma gave unchallenged evidence that on 6 April 2016, he attended a
site meeting on the premises, where he noted demolition was continuing;
(b) UCP issued its first progress claim on 15 April 2016; and
(c) UCP has provided no admissible evidence of an alternative date.
149 In my view, UCP’s submissions should be rejected. Regardless of whether
PHHH or UCP were obliged to obtain the building permit, there is no basis in the
Contract for asserting that PHHH was obliged to provide the “building permit”
before the “works” could commence. It is inconsistent with item 30b of the
Contract (which expressly states the building permit is required to complete, not
begin, the works contrasting it from item 30b). Further, it ignores the reality that,
in projects of this scale, building permits are issued in stages.
150 In this case, the stage 1 building permit was issued on 22 March 2016, followed
by further stage permits (stage 2 on 11 May 2016 varied on 6 September 2016
and stage 3 on 17 May 2016). Taking UCP’s argument to its logical conclusion,
it did not have all the “official documents” (and thus “possession” under item 22)
until 17 May 2016. Although it appeared to put this proposition early in its written
submission (at [53] to [58]), it later seemed to be opting for 8 April 2018,
consistently with the range stated in the statement of agreed facts (at [169]).
151 In any case, in addition to the 17 May 2016 date being inconsistent with the
agreed facts, it defies common sense. It is clear that UCP had possession and
was undertaking substantial works at the site well before 17 May 2016. This also
reinforces the absurdity of any construction purporting to align “possession” with
receipt of all “official documents”, including building permits. I agree with PHHH
that UCP does not provide evidence or any other sustainable basis for any
alternative dates after the date of contract signing, with the result that the only
commercially sensible construction of the Contract is that the date of possession
was 16 March 2016 (contract signing).
[2023] VCC 516
66
JUDGMENT
What is the unadjusted date for practical completion?
152 The experts agree that the unadjusted date for practical completion (based on a
date of possession of 16 March 2016) is 10 February 2017. I note that the
architect calculated it to be 9 February 2017 for the purposes of PC 16 Rev A.
Neither party seeks to make anything of this one day discrepancy. Further, the
statement of agreed facts (incorporating table B) confirms that the certificate for
practical completion was issued by the architect on 21 July 2017 and that the
architect certified EOTs totalling 4.5 days. Because this was inside the allowance
for delay due to disruptive weather in item 20 of schedule 1 to the Contract, the
162 days for liquidated damages certified by the architect by PC 16 Rev A is
therefore the number of days between 9 February and 21 July 2017.
153 UCP submits that the date for practical completion should be adjusted from the 9
February 2017 date certified by the architect on any or all of three grounds,
namely:
(a) the architect’s certification of UCP’s applications for EOTs should be
revised in its favour;
(b) the conduct of PHHH contributed to the delay (“prevention principle”) and
UCP is therefore entitled to a further extension of time; and
(c) PHHH took possession of the site early, thereby bringing forward the date
for practical completion.
Extensions of time
154 In its reply closing submissions, UCP refers to Mr Palma’s evidence to the effect
that UCP’s EOT claims did not comply with the Contract because there had been
no service (or no service in a timely manner) of a Notice of Likely Delay pursuant
to the provisions of section L “Adjustment of time”. It then submits:
“On the Owner’s case, the EOTs were either not valid claims under the
Contract, or the claims were simply not made. In either case it is
submitted that the Court can, as the Tribunal did in Allmore
Constructions, assess the merits of the EOT claims. The Owner cannot
have it have its cake and eat it as well.”
[2023] VCC 516
67
JUDGMENT
155 I have set out above my reasons for rejecting UCP’s reliance on the construction
of clause H6 of the Contract in Allmore in relation claims made by UCP, but
rejected or not assessed by the architect. However, it is not clear from this brief
passage in UCP’s reply submissions whether UCP is here advancing a different
argument. Namely, that the court (standing in the shoes of the architect) can rely
on clause H6 to assess claims for extension of time where (according to Mr
Palma) no Notice of Likely Delay was given. Put another way, is UCP here
arguing that where no Notice of Likely Delay under section L of the Contract is
given, this brings it under clause H6, because the “contractor has not made a
*claim to adjust the contract”?
156 If so, the argument is misconceived. Section L of the contract imposes an
obligation on the contractor to give timely notice of any anticipated delay. It is not
the source of the claim to adjust the contract. Clause L1.4 clearly provides that
(emphasis in original): “The requirements for making a *claim to adjust the
contract and the procedures to be followed are stated in section H”. “Claim to
adjust the contract” includes claims to adjust the date for practical completion
(clause S1). Thus clause H6 is potentially engaged when a contractor has not
made a claim to adjust the contract under clause H1, not when it has not given a
under notice of likely delay under section L.
157 The analysis below is therefore concerned only with claims for EOTs under
clause H1 that were either rejected or not assessed by the architect. And, once
again, it proceeds on the assumption that I am wrong in finding that the architect
did not fail to act fairly and impartially, and therefore the architect’s decisions
cannot be re-opened under clause H6 of the Contract (or otherwise).
158 PHHH commences its written closing submissions on the EOTs in issue topic by
submitting that little weight should be given to the evidence of Mr Quigley, and
Mr Watson’s evidence should be preferred. I broadly agree with these
submissions. In particular, the difference between Mr Quigley’s first and second
[2023] VCC 516
68
JUDGMENT
reports are striking and inadequately explained or supported by source
documents. Further, Mr Quigley’s apparent willingness to resile from or qualify
the conclusions in his second report in the joint report and in his oral evidence
further undermined his credibility. I therefore agree with PHHH that where the
experts disagree, I prefer Mr Watson’s evidence.
EOT 1- Asbestos removal
159 Some time was spent in evidence on the question of whether the particular
asbestos removal undertaken by UCP was that expressly contemplated under
the Contract and thus not properly the subject of a claim for an EOT. In any
event, both experts agreed that an extension of 5 working days was appropriate
and I would have allowed that claim.
EOT 2 - Delay in provision of CAD files
160 UCP claimed delays under EOT for “CAD files and RFI’s for Steel shop
drawings”. The claim was rejected by the architect. Mr Quigley allowed 14 days
for EOT 2 and maintained this view after the expert conclave. Mr Watson agreed
that there was a delay in the provision of the CAD files, but only allowed 8 April
to 18 April if there was not overlap with EOT 1, and zero days if there is an
overlap.
161 UCP contends for Mr Quigley’s calculation, essentially on the basis that Mr
Watson has not properly applied the contractual provision for overlapping delays
in clause L6. PHHH disputes that Mr Watson has overlooked the relevant
provision of the Contract and submits that, in any event, both experts could only
say that there was a potential for a delay. Mr Watson’s evidence was that he was
unable to ascertain what the actual impact was, and Mr Quigley ultimately
accepted that he could not say whether in fact the delay in provision of CAD files
led to a delay in the works.
162 In my view, UCP has failed to adduce sufficient evidence (from the experts or
otherwise) that the delay in the provision of the CAD files in fact led to a delay in
[2023] VCC 516
69
JUDGMENT
the works. Given UCP bears the onus to establish this EOT claim, I agree with
PHHH that this EOT is not made out
EOTs - 3 to 7 disruptive weather
163 The experts agreed that an EOT of 6.25 days, over the 10 day allowance in the
Contract is appropriate. I would therefore have allowed this claim at 6.25 days.
EOT 8 Ground floor column stiffening
164 By EOT 8, UCP claimed 68 working days due to additional works strengthening
the ground floor columns. It was rejected by the architect. According to UCP, Mr
Quigley originally allowed a period of 68 days, but was prepared to reconsider
that figure after considering Mr Watson’s report, and reduced his assessment to
30 days. Mr Watson’s allowance in the joint report and in evidence was 8 days in
evidence.
165 UCP argues that Mr Quigley’s assessment should be preferred on the basis that
UCP sent the architect a Notice of Likely Delay on 8 June 2016 and the architect
did not provide the final structural steel solution until 26 July 2016. It says the
relevant works could not commence until 9 August 2016. PHHH submits that Mr
Watson took into account the timing of the matters relied on by UCP in reaching
his 8-day assessment and his evidence was otherwise more credible. In contrast,
Mr Quigley’s first report allowed zero days, his assessment then jumped to 68
days on spurious grounds and in the joint report Mr Quigley again changed his
opinion to “greater than 8 days but less than 68 days”, noting that the difference
“depends on the circumstances”.
166 I agree with PHHH that Mr Watson’s evidence was more reliable for the reasons
it gives, and I would therefore have allowed 8 days for this EOT claim.
EOT 9 - cleats
167 The experts agreed that the appropriate allowance for this EOT claim is 26 days,
and I would have allowed this claim accordingly.
[2023] VCC 516
70
JUDGMENT
EOTs 10-13 - disruptive weather
168 EOT 10, 11, 12 and 13 were claimed by UCP for inclement weather (rain). All
four EOTs were rejected by the architect. Mr Quigley allowed 4.3 days for these
EOTs on the assumption that the external works (including cladding) were not
completed due to rain. If the external works were completed, Mr Quigley would
have allowed 2.375 days. Mr Watson allowed 0.625 days.
169 Mr Watson gave evidence that:
In my view, the delays for EOTs 12 and 13 would not have critically
delayed the works. They affected landscaping, whereas in my view,
works were able to progress inside and that was the critical path at the
time.”
170 Mr Quigley responded that:
At the conclave I reinforced my position and based on information Mr
Watson provided to 2.375 days and the query I had at the time was in
relation to the activities that were underway on site, my view was that if
external cladding was still proceeding then that was a critical trade and if
the weather had delayed that - and I think obviously it would have
delayed the external cladding - then that would have delayed the
completion of the work.
171 Accordingly, the issue between the experts was whether the delay was in the
critical path and, in particular, whether the delay coincided with external cladding
works. On the evidence, that is unclear. As the joint report notes, the site diary
refers to landscaping works, rather than cladding works and (as PHHH submits),
no evidence was given that the cladding works were in fact delayed by the
weather. As with EOT 2, I would therefore have assessed this claim as zero.
EOT 20 - increased height of balustrade
172 EOT 20 is connected to and claimed for delays as a result of variation 55, being
the required increased height of balustrade. The architect rejected EOT 20 on
the basis that it should not have caused a delay, noting that “a power shutdown
is part of the building programme”.
173 UCP submits that the EOT should be allowed at 10 days, relying on Mr Quigley’s
second report (in his first report, Mr Quigley allowed no delay). UCP argued that
[2023] VCC 516
71
JUDGMENT
Mr Quigley’s evidence should be preferred, because his assessment was based
on the fact that the change in height would have required new shop drawings to
be prepared and the purchase of new materials, whereas Mr Watson’s
assessment was unsupported by evidence. PHHH submitted that Mr Quigley
could not adequately explain how the information provided caused his opinion to
change, including that his evidence as to whether the delay was caused by the
need to re-do shop drawings alone, or this combined with the need for additional
materials, was inconsistent and vague.
174 I agree with PHHH that Mr Quigley’s answers in oral evidence were equivocal
and unconvincing, and ultimately inconsistent with his second report. Mr Watson,
on the other hand, was able to clearly explain that his opinion was based on the
fact that variation 55 only claimed for additional glass, so there was no
justification for a claim for delay associated with shop drawings and re-ordering.
While I also have some reservations about Mr Watson’s evidence, I am satisfied
on balance that UCP has failed to discharge its burden of proof in respect of EOT
20 and would have rejected this claim.
EOT 36 - fire dampers
175 EOT 36 relates to variation 79 for level 1 fire dampers. In his first report, Mr
Quigley considered that there should be no EOT for variation 79 because other
works were going on at the time. In his second report, Mr Quigley allowed 12
days on the basis that UCP was instructed to install fire dampers after the
ductwork and ceiling were already installed. Mr Watson was not able to form a
view on the EOT on the materials before him. UCP submits that, in the absence
of evidence from Mr Watson, I should accept Mr Quigley assessment. It also
notes that Mr Quigley maintained his assessment following the expert conclave.
176 PHHH submits in substance that:
[2023] VCC 516
72
JUDGMENT
(a) Mr Quigley accepted during oral evidence that what he meant by the
reasoning in his first report was this variation was not the sort of thing that
would delay the critical path;
(b) in Mr Quigley’s second report, he changes his opinion based on
assumptions he was asked to make regarding the critical path, and he was
asked to assume the very thing he was asked to opine on; and
(c) the assumptions adopted by Mr Quigley have not been proved.
177 I accept PHHH’s submissions. Despite the absence of evidence from Mr Watson,
the onus lies on UCP to prove the claim on the balance of probabilities and in my
view, it has failed to do so.
EOT 44 - overflow drains to play area
178 EOT 44 was submitted due to variation 94 Rev B. EOT 44 cited “checkpoint
surveyor requirement on 19th June 2017 to add overflow system details to
children’s play areas”. The position taken by the two experts in respect of this
claim are essentially the same as those taken in respect of EOT 36, and PHHH’s
criticisms of Mr Quigley’s evidence also mirror those made about his evidence on
that earlier EOT. Further, in evidence Mr Quigley accepted that he came up with
the allowance of 30 days for this EOT, only after being asked in correspondence
to assume the very fact that he had been asked to opine on.
179 As with EOT 36, I agree with PHHH’s submissions. In particular, I accept that Mr
Quigley’s estimate was premised on the assumption that the work on variation 94
Rev B was the only issue holding up the certificate of occupancy. I therefore
again find that UCP has failed to prove any entitlement under EOT 44.
Can UCP rely on the prevention principle?
180 It is not clear whether this issue is pressed by UCP. Its written closing
submissions make passing reference to it the context of the liquidated damages
claim, but did not develop any argument in written or oral closing submissions in
[2023] VCC 516
73
JUDGMENT
support of the application of the principle. It received somewhat more coverage
in the parties’ written opening submission. Regardless, I agree with PHHH’s
written opening submission that the prevention principle does not apply in
circumstances where:
(a) the Contract contains provision for an extension of time in respect of delays
caused by the owner;
26
and
(b) the contractor would have been entitled to an extension of time, but for the
fact that it failed to comply with the preconditions for obtaining the
extension, the satisfaction of which was within its control (failing to comply
with the notice provisions).
Prolongation costs
181 I also note in passing that UCP included in its counterclaim (and briefly
referenced in its oral opening submissions) claims for prolongation costs. I made
rulings during the course of the hearing excluding material comprising
paragraphs of witness statements, spreadsheets and other documents, which
UCP sought to adduce in evidence in support of its prolongation costs. PHHH
therefore submits that:
“It is apparent from the absence of any admissible evidence of loss and
damage at trial, coupled with the fact that clause H6 of the building
contract would not in any event avail the Defendant in the
circumstances…that the Defendant no longer presses it prolongation
costs claim (particularly in the absence of any submissions in this regard
in its Closing Submissions). Therefore this aspect of the Counterclaim
should be dismissed.”
182 As with the issue of the prevention principle, UCP did not expressly resile from its
claim for prolongation cost, but it did not take issue with PHHH’s submission
above in either its written reply submissions or in oral closing submissions. Nor
did UCP otherwise seek to advance any claim for prolongation costs in closing.
26
S.M.K. Cabinets v Hili Modern Electrics Pty Ltd [1984] VR 391 at 396 per Brooking J.
[2023] VCC 516
74
JUDGMENT
In those circumstances I agree with PHHH that this aspect of UCP’s
counterclaim should be dismissed, for the reasons it gives.
Did PHHH take possession of the site early, and thereby bring forward the
date of practical completion?
183 Clause M8 of the Contract relevantly provides that if the owner takes possession
of the works before the architect issues the notice of practical completion, the
works are to be treated as having reached practical completion. Relying on this
clause, UCP submits that practical completion occurred when PHHH moved
furniture into the “Zebra room” of the Happy Hippo childcare centre on around 10
April 2017, or when it later arranged and conducted open days, with the first of
these taking place on 10 May 2017. UCP submits that the relevant conduct of
PHHH is:
“[N]ot merely its conduct in accessing the site, it is its assumption of the
possession required to take full control of the parts of the site so as to
invite third parties onto it, furnishing it for the purposes of its business
and preparing for the commencement of business by way of open days”.
184 PHHH submits in response that:
(a) clause F2 of the Contract obliges UCP to give access to the site on
reasonable terms, which occurred;
(b) the court cannot equate partial access with practical completion (particularly
given UCP claims variations and EOTs beyond those dates);
(c) there is a distinction between occupation for limited purposes and in limited
areas while works continue, and occupation for the purpose of practical
completion;
(d) UCP has not provided any authority for the proposition that Mrs
Honeyborne’s limited use of a limited section of the premises constitutes
occupation for the purpose of determining the date of practical completion;
[2023] VCC 516
75
JUDGMENT
(e) Mr Palma gave evidence that there were outstanding issues at this time;
and
(f) UCP did not challenge the certificate of practical completion and it does not
form part of UCP’s counterclaim.
185 Neither party cited any authority on the question of whether limited access to the
site of the kind that occurred in around April of May 2017 is “taking possession”
for the purposes of clauses along the lines of clause M8 of the Contract, and I
am not aware of any. However, construing the Contract as a whole (including
having regard to clause F2 which expressly provides for giving the owner access
on reasonable terms), it is clear that “possession” in clause M8 contemplates
something considerably more comprehensive than apparently occurred in this
case, essentially for the reasons submitted by PHHH.
186 Further, clause M8 refers to the owner taking “possession of the *works”, not the
other defined term “site”. Works” is defined as the “completed construction set
out in the *contract documents (briefly described in item 5 of schedule 1”. The
site” is defined as “the place at which the *works are to be constructed”. In my
judgment, “possession” for the purposes of clause M8 thus contemplates
conduct consistent with the owner assuming responsibility for the construction,
and probably in a manner that limits or excludes the contractor from undertaking
further works. There is no suggestion that the limited and temporary access to
the site for the purposes of conducting open days for prospective parents, in any
way materially impinged on or assumed responsibility for UCP’s ongoing
construction activities.
187 Accordingly, had I determined that I could revisit PC 16 Rev A, I would have
found that there was no evidence of PHHH formally taking possession of the
works under the Contract at any time before Mr Palma issued the certificate of
practical completion on 21 July 2017. I would therefore have held that the date of
practical completion stands at 21 July 2017.
[2023] VCC 516
76
JUDGMENT
Amounts owed by UCP to PHHH for breach of contract and restitution
188 In summary, I have determined that the decisions of the architect are not vitiated
as the architect did not fail to act impartially or fairly. Thus, pursuant to PC 16
Rev A, the total adjusted Contract Price is as certified by the architect, being
$4,241,638.36 plus the further $8,864.44 allowed in PC 16 Rev A, totalling
$4,250,506.80. Further, the decision of the architect in relation to liquidated
damages and utilities stands and I find that PHHH is owed $331,361.98 in
respect of these amounts. It follows that the architect’s certification in PC 16 Rev
A that UCP owes PHHH $322,493.54 also stands.
189 PHHH claims that UCP’s failure to pay PC 16 Rev A constitutes a breach of
subclause N6.1 of the Contract. It is not in dispute that UCP has not paid PC 16
Rev A and, accordingly, UCP has breached subclause N6.1 of the Contract by
failing to pay the amount certified as owing by it to PHHH under PC 16 Rev A
being $322,493.54.
190 Clause N15 of the Contract provides that each party must pay interest on any
money that it owes the other but fails to pay on time, at the rate specified in item
28 of schedule 1, which is 10% per annum. This is the rate claimed by PHHH
and I accept that this is the rate applicable the above sum from 10 March 2018
(being the date on which PC 16 Rev A was due, and as claimed by PHHH) to the
date of judgment.
191 In addition to the breach of contract claim, PHHH claims restitution for the
difference between the adjusted contract price, as certified by the architect, and
the amount of progress claims paid by PHHH. The parties agree that PHHH has
paid UCP a total of $4,539,281.37. I have determined that the total adjusted
contract price is as certified by the architect is $4,250,506.80. The difference
between these two amounts is $288,774.57. PHHH submits that it is entitled to
restitution of the overpaid amount “as it would be unfair and unjust for [UCP] to
retain such overpayment and be so unjustly enriched”. I agree.
[2023] VCC 516
77
JUDGMENT
Is PHHH entitled to damages for defective work by UCP?
192 In addition to the payments PHHH claims pursuant to PC 16 Rev A, PHHH
claims damages for breach of contract for alleged defects in the works
undertaken by UCP. There are five issues in respect of PHHH’s defects claims,
as follows:
(a) whether the alleged defect is in fact a defect in the works undertaken by
UCP, as distinct from a design defect;
(b) how to resolve differences in the expert evidence on the cost of rectification
of the defect;
(c) whether PHHH’s claim should be reduced because it refused to allow UCP
to undertake the rectification works (including whether PHHH is entitled to
claim a builders margin as part of the cost of rectification); and
(d) whether PHHH’s sale of the property reduces the damages it is entitled to
claim.
193 The general principles to be applied in determining the measure of damages
recoverable by PHHH for UCP’s defective work is not in dispute. That measure is
the difference between the contract price of the work and the cost of making the
work conform the Contract. However, that general rule is subject to the
qualification that the undertaking of the work necessary to produce conformity
must be a reasonable course to adopt.
194 The decision of the High Court in Bellgrove v Eldridge
27
(“Bellgrove”) from which
these principles are derived, and subsequent leading authorities (notably
Tabcorp Holdings Ltd v Bowen Investments Pty Ltd
28
(“Tabcorp”)) examining
those principles, were considered in detail by the Court of Appeal in Metricon
Homes Pty Ltd v Softley
29
(“Metricon”). I discuss the application of these
27
(1954) 90 CLR 613.
28
(2009) 236 CLR 272.
29
[2016] VSCA 60, per Robson AJA, Warren CJ and Tate JA agreeing, at [178] to [202].
[2023] VCC 516
78
JUDGMENT
principles in more detail below, in discussing the effect of PHHH’s sale of the
childcare centre in June 2018 on its defects claims.
What defects are agreed?
195 The parties agree defects as to both liability and quantum totalling $15,998, as
follows:
(a) storeroom plumbing ($743.00);
(b) disabled toilets ($4,089.00);
(c) shade sail ($7,050.00);
(d) mechanical air extraction ($257.00);
(e) north western masonry wall ($600.00);
(f) second floor water ingress ($250.00);
(g) waterproofing peeling away ($660.00); and
(h) giraffe roof leak ($2,349.00).
What is UCP’s liability for the disputed defects?
Glass safety barrier (balustrade)
196 PHHH accepts that the weight of the expert evidence on this alleged defect is
that it was a design issue. However, it submits that “the clear (unchallenged and
uncontradicted) evidence of Mr Palma was that, having started the work other
than in accordance with the structural design drawings, Mr Palma gave UCP two
options. First, proceed with the structural design drawings (start again). Second,
continue as they were, but on the basis that UCP was responsible for having a
structural engineer approve that method (UCP chose this option). PHHH argues
that it follows that UCP was responsible for the design.
[2023] VCC 516
79
JUDGMENT
197 Unsurprisingly, UCP relies on the weight of the expert evidence to argue that this
is a design defect, rather than a construction issue, for which it is not
responsible. It refers to the following evidence:
(a) Mr Quigley in his report states the alleged defects with the glass safety
barrier is a design defect, which he maintains in the joint report;
(b) Mr Lorich agrees, and maintains that view in the joint report;
(c) although Mr Naughton did not agree it was a design defect, he conceded in
evidence that the 10mm glass supplied by UCP was in accordance with the
project specification and that he was not aware of any instruction to the
builder specifying a 12mm thickness; and
(d) Mr Naughton also appeared to agree that the engineer had found that
10mm glass was acceptable, providing the spans were not greater that
900mm centre to centre (it was not suggested that the as-built balustrade
exceeded this allowance).
198 PHHH bears the onus of establishing that the as-built balustrade did not conform
to the design drawings and specifications and, in my view, it has failed to do so,
essentially for the reasons given by UCP. Despite my reservations about aspects
of Mr Quigley’s evidence, in my view his assessment of design issues was
generally more consistent and reliable. He was also supported in this
assessment by Mr Lorich, who impressed me as a careful and reliable witness
within his area of expertise. I therefore reject PHHH’s claim for damages in
respect of the glass balustrade.
Wall specification
199 The experts agreed that this was a defect, but disagreed on quantum. Mr
Buchanan assessed the rectification at $27,345.00, and Mr Naughton at
$30,439.52. PHHH submits that I should split the difference on these
assessments because Mr Buchanan accepted that the difference is marginal and
[2023] VCC 516
80
JUDGMENT
comes down to methodology and the use of margins and “it seems pointless
arguing over the difference”.
200 UCP submits that I should apply Mr Buchanan’s calculation on the basis that:
(a) he is more qualified and experienced on matters of quantities; and
(b) Mr Naughton’s calculations were presented during the running of the trial
with limited ability for Mr Buchanan to interrogate the figures presented by
Naughton.
201 I agree with UCP that Mr Buchanan is relatively more qualified and experienced
on matters of quantities. Further, his assessments and evidence more generally
impressed me as both considered and balanced. And it is essentially for that
reason that I am inclined to agree with Mr Buchanan that the difference between
his and Mr Naughton’s assessments were marginal and it is pointless to spend
time seeking to separate the two. I will therefore adopt the approach suggested
by PHHH and split the difference at $28,892.26.
Fire rating
202 Liability for this defect is agreed. On the question of quantum I am satisfied that:
(a) it was also agreed at the conclave that, as the rectification of this defect had
already been carried out, the experts would assess quantum based on
costs actually incurred and Mr Naughton would supply the relevant
invoices; and
(b) at trial it transpired that not all the potentially relevant invoices, quotes and
remittance advices had been supplied to the experts, so I ordered a further
limited conclave between Mr Naughton and Mr Buchanan to consider that
further material;
[2023] VCC 516
81
JUDGMENT
(c) it appears that one of the further invoices produced at this time (an invoice
dated 4 September for $9,476) had not previously been discovered or
included in the court book;
(d) the total of the invoices was $40,184.30:
(e) Mr Buchanan accepted that the invoices appeared to be in order and
referred back to quotes, he was unable to comment on the reasonableness
of the invoiced value compared to his assessment;
(f) Mr Buchanan’s revised assessment following the further limited conclave
and review of all invoices and quotes, was $29,185; and
(g) the criticisms in UCP’s written reply submission of both the late and
piecemeal provision of supporting documents by PHHH and of Mr
Naughton’s approach to the scope of the rectification work, have some
force.
203 In these circumstances and based on my preference for Mr Buchanan’s
assessments and evidence as discussed above, I prefer Mr Buchanan’s revised
assessment of $29,185 to undertake necessary rectification work, over an
uncritical acceptance of the invoices rendered to PHHH for the work.
204 Further, Mr Buchanan and the other experts (other than Mr Naughton) were
denied the opportunity to fully interrogate and discuss the invoices and other
documents during the conclaves and at trial. It seems the fault for this lies with
PHHH. To my mind, this is in substance a failure by PHHH to adduce proof on
the balance of probabilities of its loss beyond that accepted by Mr Buchanan. I
will therefore assess damages for this defect claim in the sum of $29,185.00.
[2023] VCC 516
82
JUDGMENT
Door sealing
205 The parties agreed in their written closing submissions this defect should be
assessed at $2,919.00, representing the consensus reached by the experts
during the conclave. I assess damages accordingly.
Eave soffit lining
206 The experts agreed that this was a defect, and assessed quantum as $55,282,
not including the cost of sarking. The expert costing of the sarking was Mr
Naughton at $8,590.00, Mr Lorich at $4,075.00 and Mr Buchanan at $4,968.00.
PHHH submits that I should assess damages at the midway point between the
highest and lowest expert costings. PHHH argues that I should prefer the
opinions of Mr Lorich and Mr Buchanan as:
(a) their opinions are close; and
(b) Mr Quigley considered that the work could be completed in two days, rather
than the four allowed by Naughton.
207 I will assess damages for this defect at Mr Buchanan’s figure of $4,968.00,
essentially for the reasons submitted by UCP. As I have already noted, I
generally prefer the evidence of Mr Buchanan on these matters over Mr
Naughton, and on this particular defect, that evidence also finds support from Mr
Lorich and Mr Quigley.
Rainwater retention system
208 UCP does not cavil with PHHH’s assertion in closing submissions that it was
agreed that this was a defect. Further, I accept that Mr Honeyborne gave
unchallenged evidence that $1,375.00 was paid to SWR plumbing for these
works and note that this appears to be towards the lower end of the various
expert assessments of likely cost. I would therefore assess damages for this
defect at $1,375.00.
[2023] VCC 516
83
JUDGMENT
Rainwater harvesting
209 Similarly, UCP does not cavil with PHHH’s assertion in closing submissions that
“it was agreed this was a defect. Quantum was also agreed at $5,198.05.
Accordingly, I assess damages for this defect in that amount.
Roofing
210 The roofing works were undertaken by Mackey Bros, under a sub-contract with
UCP. As noted above, the Mackey parties were joined by UCP as third parties in
the proceeding, but later reached a settlement with UCP pursuant to which the
Mackey parties paid $100,000 to UCP. Against that background, it is perhaps
unsurprising that the experts agree that there were a number of roofing defects.
The principal differences between the experts arise from:
(a) the assessment of the cost of scaffolding (both the direct cost and whether
that cost should attract a builder’s margin); and
(b) whether or not particular items of defective work is properly attributable to
the Mackey parties.
211 In the joint report, UCP’s roofing expert Mr Wenning costed the roofing defects at
a total of $98,151.63, PHHH’s roofing expert Mr Quick at $135,663.39, the
Mackay parties’ roofing expert Mr Djurovitch at $82,637.57 and PHHH’s
generally quantities expert Mr Naughton at $105,159.73. UCP asserts that the
appropriate revised quantum of Mr Wenning is $98,955, having regard to alleged
concessions he made at trial.
212 On the question of the cost of the scaffolding and whether it ought to be included
as a line item(and therefore attract a margin), Mr Quick costed it at $55,000,
Mr Wenning at $50,000, and Mr Naughton at $48,000. Mr Naughton and Mr
Quick considered that it should attract a margin, Mr Wenning disagreed. PHHH
submits that I should prefer Mr Naughton’s assessment, on the basis that he was
the only expert to give a detailed breakdown of this item, together with detailed
drawings. PHHH further argues that Mr Wenning’s basis for not allowing for a
[2023] VCC 516
84
JUDGMENT
margin on scaffolding cost (because it accounted for half the total cost) was
misconceived.
213 In its written reply submissions, UCP submits that PHHH has overlooked Mr
Wenning’s full explanation for not adding a margin. His evidence was that a cost
of $50,000 was “an unrealistic figure to put, say, 20 or 30 per cent in a
competitive environment”, and a cost as high as $50,000 would not attract any
loading. In commenting on Mr Wenning’s evidence more generally, UCP further
submitted (in effect) that, having made some appropriate concessions during the
evidence, Mr Wenning’s evidence should be preferred.
214 I agree with UCP that Mr Wenning presented as the most balanced of the three
witnesses giving concurrent evidence on these issues. That is not intended to
suggest that Mr Quick and Mr Naughton’s evidence was unbalanced. Rather, the
differences between each of the experts on the roofing issues were generally
minor and subtle, and so weighing the evidence of each of the witnesses is
likewise a subtle exercise. On balance, I was more persuaded by Mr Wenning on
the areas of difference, including in relation to the scaffolding.
215 On the individual items making up the balance of the claim, I agree with PHHH
that as Mr Djurovitch was not a witness at trial, I should disregard his evidence
(including his contribution to the joint report). However, I agree with UCP that:
(a) Mr Naughton is not a roofing expert and therefore his methodology on the
costings needs to be approached with some caution;
(b) on some items there is real doubt about the extent of Mackay Bros role in
the works, including because some items may have been contributed to by
the relocation of mechanical plant on the roof; and
(c) Mr Wenning gave a plausible explanation for his assessments generally
being lower than Mr Quicks (namely, by allowing for the involvement of
apprentices at a lower cost), whereas Mr Quick seemed to say that he did
[2023] VCC 516
85
JUDGMENT
not allow for apprentices essentially because it was easier to reconcile
costs using licensed plumber’s rates.
216 For these reasons, coupled with my general preference for Mr Wenning’s
evidence as discussed above, I accept UCP’s submission that the damages for
the roofing defects should be assessed consistently with Mr Wenning’s
assessment as $98,955.00.
Should PHHH’s damages be reduced because it denied UCP the
opportunity to undertake rectification works at lower cost?
217 UCP submits that PHHH is not entitled to claim damages in an amount which
exceeds the loss it would have suffered had it taken reasonable steps available
to it, to try to minimise its loss. It argues in effect that that PHHH is only entitled
to recover damages in respect of the cheaper of two equally effective means of
remedying a defect, and in this case the cheaper means was allowing UCP to
undertake rectification works.
30
It also appears to suggest that PHHH’s conduct
amounted to a repudiation of the damage limitation period provided for in the
Contract, but I agree with PHHH that there is no pleaded allegation of
repudiation, so this issue can be disregarded.
218 UCP relies in support of its argument on the decision of the NSW Supreme Court
in The Owners - Strata Plan No 76674 v Di Blasio Constructions Pty Ltd
31
(“Di
Blasio”) in which Ball J held (citations omitted):
32
In the case of building contracts, it is also generally accepted that the
owner must give the builder a reasonable opportunity to rectify any
defects. Often, of course, the building contract itself requires the owner
(sic) to repair defects or sets out a procedure by which defects are to be
made good. But, even if it does not, the owner is required to give the
builder an opportunity to minimise the damages it must pay by rectifying
the defects, except where its refusal to give the builder that opportunity is
reasonable or where the builder has repudiated the contract by refusing
to conduct any repairs. That obligation may be an aspect of the duty to
mitigate, since it may be less expensive for the builder rather than a third
party to rectify the defects, particularly if the builder is still on site. But the
obligation is not simply an aspect of the duty to mitigate. The cost to the
30
Citing McKone v Johnson [1966] 2 NSWR 471, 474476 (Sugerman JA).
31
[2014] NSWSC 1067.
32
Ibid at [43]-[44].
[2023] VCC 516
86
JUDGMENT
builder of undertaking the repairs is likely to be less than the amount that
a third party would charge the owner for the same work. In that case, the
owner is not mitigating its loss, but rather the builder's damages.
219 As PHHH notes in its submissions, in the immediately following paragraphs, Ball
J held (citations omitted):
33
The question of what is reasonable depends on all the circumstances of
the particular case. One relevant factor is what attempts the builder has
made to repair the defects in the past and whether, in the light of the
builder's conduct, the owner has reasonably lost confidence in the
willingness and ability of the builder to do the work…
It is for the defendant to prove that the plaintiff has acted unreasonably.
It is not for the plaintiff to prove that it acted reasonably.
220 UCP also cites to Turner Corporation Ltd (Receiver and Manager Appointed) v
Austotel Pty Ltd
34
(“Turner”) in which Cole J held:
35
There is, in my view, no room for a wider common law right in the
Proprietor to treat non-compliance with the contractual obligation with the
Builder as a separate basis for claiming damages being the cost of
having a third party rectifying or completing defective or omitted works.
This is because the contract specifies and confers upon the Proprietor its
right flowing from such breach; that is, the parties have, by contract
agreed upon the consequences for each of the Proprietor and the
Builder, both as to rights and powers flowing from and the consequences
of, such breach… It also follows, in my view, that the Proprietor has no
entitlement to recover the costs of works performed by others at the
request of the Proprietor unless prior to such work being performed the
Architect has given the notice required by cl 5.06.1 prior to the date of
practical completion or pursuant to cl 5.06.01 as incorporated by cl
6.11.05 after the date of practical completion.
221 UCP argues that during a defects liability period, an owner is generally not
permitted to recover damages from the contractor for the cost of rectifying the
contractor’s defective works unless the owner has first given the contractor the
opportunity to undertake the necessary rectification work, at the contractor’s
expense, and the contractor has failed to perform the required rectification work.
Defects liability provisions confer a positive right upon the contractor to mitigate
or even eliminate the owner’s loss or damage flowing from the contractor’s
33
Ibid at [45]-[46].
34
(1994) 13 BCL 378.
35
Ibid at [395].
[2023] VCC 516
87
JUDGMENT
breach of obligation (that is, to reduce or eliminate a loss for which the contractor
would otherwise be liable).
36
222 Applying those principles in this case, UCP submits the Contract expressly
allowed UCP to rectify defects. Indeed, UCP was to correct any defects or
finalise any incomplete necessary work, whether before or after the date of
practical completion, within the agreed time as stated in an instruction (clause
M11). If UCP fails to correct the work within the time nominated under clause
M11 or fails to show reasonable cause for the failure together with a timetable for
correcting the problem, PHHH could use another person to correct the problem
at the cost of UCP (clause M12).
223 In relation to the particular defects that UCP argues are affected by the
application of these principles, UCP submits as follows:
(a) On 28 August 2017 the architect issued an instruction to UCP to correct
defects, but the following day, Mrs Honeyborne emailed Mr Palma saying:
“Tamar [Soliman] issued notices and it has gone legal now, we don’t want
them there as we don’t want a barney in our business. They are not to
attend as they were (sic) issued with AI over 14 days ago and they are in
breech (sic)”.
(b) On 29 August 2017, Mr Palma emailed UCP advising he had been
instructed not to allow UCP on site, and Mr Soliman of UCP had responded
the following day asking “how are we going to attend to defects?”.
(c) On 16 July 2018, 4 days before the expiry of the damage limitation period,
the architect issued AI 649, a 129 page instruction including the report of Mr
Naughton. There were further exchanges between the architect and UCP in
relation to the defects in early August 2018, including an email from UCP to
36
P&M Kaye Ltd v Hosier & Dickinson Ltd [1972] 1 WLR 146, 166 (Diplock LJ); Egan v State Transport
Authority (1982) 31 SASR 481, 484-485.
[2023] VCC 516
88
JUDGMENT
the architect on 9 August 2018 noting that UCP was arranging “subbies” to
attend to the defects.
(d) On 28 August 2018 UCP wrote to PHHH making an offer to attend to the
following defects:
(i) Item 7.3 wall specifications fire rating;
(ii) Item 7.6 eave soffit lining;
(iii) Item 7.9 rainwater retention system;
(iv) Item 7.10 rainwater harvesting;
(v) Item 7.13 - storeroom plumbing;
(vi) Item 7.14 disabled toilets;
(vii) Item 7.15 shade sails;
(viii) Item 7.16 mechanical air extraction;
(ix) Item 7.17 north western masonry wall; and
(x) Water leaking to the ground floor soffit.
(e) On 31 August 2018, PHHH responded to UCP’s letter conditionally
accepting UCP’s offer to attend the site to rectify items 7.6, 7.10, 7.11, 7.13,
7.14 and 7.17, with the remaining items either already being attended to or
requiring further instructions.
(f) PHHH’s condition was that UCP pay $10,000.00 to Mr Naughton for the
preparation and finalisation of his expert report identifying the defects. UCP
argues that this is not a mechanism under the contract. Under clause M12.1
of the Contract, it is for the architect to determine whether the proposal to
correct the problem is acceptable.
[2023] VCC 516
89
JUDGMENT
(g) On 18 September 2018, UCP wrote to PHHH rejecting the conditional
acceptance and reinstating their initial offer to rectify the defects set out in
the correspondence of 28 August.
(h) On 20 September 2018, PHHH wrote to UCP stating that they required
more time to obtain instructions. UCP again expressed their willingness and
ability to rectify the defects on 20 September 2018.
(i) On 25 September 2018, the UCP requested that PHHH provide a response
to the offer made on 18 September 2018.
(j) Contrary to Mr Honeyborne’s oral evidence that he did not want UCP to
return because he had lost confidence in UCP, Mr Honeyborne’s position
at the relevant time was that attendance at the site was conditional on
payment of fees due to Mr Naughton.
(k) The architect as PHHH’s agent had instructed UCP to attend to defects on
28 August 2017, which is inconsistent with the evidence that Mr
Honeyborne now gives that he had lost confidence.
(l) UCP was ready, willing and able to attend to rectify certain defects.
224 PHHH submits that the authorities relied on by UCP do not support UCP’s case,
referring in particular to the passage in Di Blasio immediately following that relied
on by UCP (and set out above). PHHH argues that Bell J in Di Blasio held it was
not unreasonable in that case for the plaintiff to refuse the defendant an
opportunity to rectify defects because the plaintiff took the reasonable step of
engaging an expert to identify the defects, and the builder’s response was
inadequate.
225 PHHH further argues that clauses M12 and M14 impose obligations on UCP to
rectify defects, and confer a benefit to PHHH, including M12.2 a right to use
another person to rectify the problem. It says that in Turner, the obligation was
[2023] VCC 516
90
JUDGMENT
on the owner to allow the contractor to rectify defects. PHHH submits that the
actions of PHHH were otherwise reasonable because of the following:
(a) In August and September 2018 when the parties were purporting to discuss
arrangements for UCP to undertake rectification works there were four legal
proceedings underway between the parties (this proceeding, a garnishee
proceeding, an adjudication proceeding and a guarantee proceeding) and
communications were occurring principally through solicitors.
(b) Mr Honeyborne gave evidence that due to the matters which occurred after
practical completion, he had lost confidence in UCP.
(c) In relation to UCP’s reliance on Mrs Honeyborne’s refusal to allow it on site
in August 2017 (about 11 months before expiry of the damage limitation
period), Mrs Honeyborne gave unchallenged evidence this was because
she did not want any unpleasantness to occur in the childcare centre, and
referred to matters going legal which suggests a breakdown in
relationship between the parties.
(d) Mrs Honeyborne gave unchallenged evidence of later allowing UCP to
attend the site on numerous occasions, despite her concerns.
(e) The suggestion that UCP was ready, willing, and able to rectify the defects
in August and September 2018 ought to be given little weight. At that time,
it was conducting the proceeding through its current solicitors, and filed a
defence denying almost all of the defects. This suggestion should be seen
as formulaic legalese designed to provide a basis for resisting PHHH’s
defect claims.
(f) UCP’s submissions imply that it lost an opportunity that otherwise would
have been available in August 2018. However, UCP appeared to accept
that the rectification works would be completed by subcontractors. UCP is
able to pursue those subcontractors, and was able to join them to the
[2023] VCC 516
91
JUDGMENT
proceeding (as it did for the roofing subcontractors). It has lost no right, but
rather made a forensic decision to deny liability up until trial.
226 I agree with UCP that clauses M11 and M12 of the Contract do contemplate that
UCP would ordinarily be given the opportunity to rectify defects before PHHH is
free to engage a third party to undertake the work. PHHH correctly submits that
the provisions do not in terms confer on UCP a right to rectify. However, read
together, I am satisfied that clause M11 and M12 contemplate and implement a
regime under which UCP must correct the defects identified in the relevant
instruction, with PHHH being entitled to use another person to correct the
problem at the cost of the contractor” under clause M12.1, only after UCP has
failed to comply with clause M11.
227 The next question on this issue is more difficult. It is in substance the question
asked by clause M12.1 of the Contract: Did UCP fail to correct a defect or finalise
any incomplete necessary work within the time required under the Contract? It is
far from clear from the exchanges between the parties after the architect issued
AI 649 whether there was a point at which UCP could be said to have “failed”
within the terms of clause M12.1. Certainly it did so in respect of particular
defects that were not part of its offer on 28 August 2018 to rectify, but neither
party has attempted to make submissions about the effect of any alleged failure
by UCP in respect of particular defects.
228 Instead, each party has sought to deal with the consequences of their respective
submissions globally, as follows:
(a) PHHH has argued that UCP has failed to establish that PHHH acted
unreasonably in restricting or refusing UCP access to the site to rectify
defects, and so PHHH was within its rights to engage third parties to
undertake all of the necessary rectification work; and
[2023] VCC 516
92
JUDGMENT
(b) UCP submits in substance that, had it been given the opportunity itself to
rectify the defects, it would not have incurred the cost of a builder’s margin
on the rectification work:
“Accordingly should the Court award any damages for defective work, it
should be discounted to reflect the cost to the Builder had the Builder
performed the works by deducting the builder’s margin for any costings
based on third parties rectifying the works.”
229 In relation to PHHH’s submissions, I am not assisted by evidence of exchanges
between the parties in August 2017 suggesting PHHH was denying UCP access
to the site at around this time. In my view, this was superseded by the issue
almost a year later (on 16 July 2018) of AI 649 attaching Mr Naughton’s report
and the exchanges that followed. On the other hand, there is some force in
PHHH’s submissions that UCP’s offers to attend to rectify in around August 2018
were largely window dressing, given the level of disputation between the parties
at this time. The same can probably be said of PHHH’s conditional offer to allow
UCP on site to undertake rectification works.
230 Having said this, in my view, it is not enough for PHHH to rely on UCP’s asserted
failure to demonstrate that PHHH was acting unreasonably in refusing access to
UCP. To my mind, this overlooks the primacy to be afforded to PHHH’s
contractual obligations under clause M11 and M12 discussed above. If (as I have
found) the Contract obliges PHHH to afford UCP the opportunity to rectify defects
and it has failed to do so, this is a breach of the Contract that is not saved by
UCP failing to establish the unreasonableness of PHHH’s conduct. The question
of unreasonableness only arises in relation to PHHH’s duty to mitigate, and
PHHH’s breach is anterior to any question of mitigation.
231 Further, if the question of mitigation were engaged, I am satisfied that PHHH’s
refusal to allow UCP to rectify the defects was unreasonable, for two reasons.
First, Mr Honeyborne may well have lost confidence in UCP, but it is clear from
the correspondence in July to September 2018 discussed above that he was not
relying on this as a basis for refusing UCP access to the site. On the contrary, he
[2023] VCC 516
93
JUDGMENT
purported to agree that UCP could have access to undertake particular
rectification work, as long as it first paid $10,000 towards the cost of Mr
Naughton’s report. Second, I agree with UCP that PHHH had no basis under the
Contract (or otherwise) to impose that condition. Under clause M12.1 of the
Contract, it is for the architect to determine whether the proposal to correct the
problem is acceptable.
232 Doing the best I can in the absence of guidance from the parties as to how to
apply these findings to particular defects, I propose to adopt the course proposed
by UCP, given my findings in its favour on this issue. That is, I will discount
PHHH’s damages for the defects that UCP offered to rectify by the amount of the
builder’s margin on those particular defects. There was some divergence of view
between the experts as to what that margin should be, but as I have generally
preferred the evidence of Mr Buchanan on the quantification of the defects, I will
apply the margin that he used. Mr Buchanan’s evidence was that this was 25%,
comprising 10 percent for preliminaries and 15% for the builder’s margin.
233 The relevant defect items (that is, those that UCP offered to rectify) in respect of
which the quantum was either agreed or has been assessed by me above are as
follows (the amount assessed is also shown below):
(a) item 7.3 wall specification fire rating: $29,185.00;
(b) item 7.6 eave soffit lining: $4,698.00;
(c) item 7.9 rainwater retention system: $1,375.00;
(d) item 7.10 rainwater harvesting: $5,198.05;
(e) item 7.13 storeroom plumbing: $743.00;
(f) item 7.14 disabled toilets: $4,089.00;
(g) item 7.15 shade sail: $7,050.00;
[2023] VCC 516
94
JUDGMENT
(h) item 7.16 mechanical air extraction: $257.00; and
(i) item 7.17 north western masonry wall: $600.00.
234 As far as I can tell, the final item in the list of those that UCP offered to rectify
(described as “Water leaking to ground floor soffit”) has not been the subject of
claim or assessment. Applying a 25% discount to the quantum assessed on the
total of the other amounts (being $53,195.05), leads to a reduction of $13,298.76
in the damages I will award to PHHH for the defects.
Does PHHH’s sale of the property reduce the amount of the defects
damages it can claim?
235 PHHH sold the property to a third-party purchaser by a contract of sale dated 17
April 2018, with settlement occurring on 22 June 2018. UCP submits that PHHH
is not entitled to damages for the costs to rectify defects that it did not incur as a
result of the sale. It argues that:
(a) the lease between PHHH and Happy Hippo is a standard form LIV lease
and does not provide for any obligation on Happy Hippo to rectify defects;
(b) PHHH completed the sale and parted with any interest in the property after
commissioning the Naughton report and before giving any notice of the
defects to UCP;
(c) PHHH therefore had no interest in the defects being repaired, or any ability
to carry them out, before it invoked the contractual regime for the correction
of defects;
(d) only $4,723.80 was expended on defect rectifications before the settlement
of the sale of the property; and
(e) the remainder of the invoices as claimed by Mr Honeyborne in his lay
witness statement of 30 October 2020 were all expended after the sale of
the property had occurred;
[2023] VCC 516
95
JUDGMENT
236 UCP submits that the fact that the works will not in fact be carried out and the
sale of the property are relevant to the reasonableness of rectification. It argues
that where PHHH has elected to sell the building without carrying out the repairs,
where it has refused UCP the opportunity to effect the repairs, and where it has
presented a grossly inflated damages claim, “the conclusion asserts itself that
this is not an action to recover bona fide loss, but rather to extract a windfall at
the expense of the Builder”.
237 PHHH submits in response that whether the rectification works were carried out
before selling the property is irrelevant, provided the amount claimed is
reasonable. It adds that the reasonableness question is one of fact, it does not
depend upon the likelihood of the works being completed and UCP (as the party
bearing the onus of establishing unreasonableness) has not produced evidence
that any of the rectification works were unreasonable. PHHH further argues that:
(a) much of the cost of rectification works has already been incurred;
(b) Mr Honeyborne gave evidence that PHHH intends to reimburse the landlord
for the completion of these works;
(c) UCP’s submission that PHHH is seeking to “extract a windfall” and that
“there will be no rectification” are baseless and cannot be asserted as they
were never put to Mr Honeyborne; and
(d) UCP has been indemnified by the third parties in the sum of $100,000 for
the roofing defects. Therefore, UCP is suggesting it is unreasonable for
PHHH who paid for UCP to carry out this work (which was defective) to
receive this money as it no longer owns the premises, and it is more
reasonable for UCP, who was responsible for the defective work, to be paid
twice over for the defective work.
[2023] VCC 516
96
JUDGMENT
238 As noted above, the submissions differ on whether the sale of the property, or
the likelihood of the works being carried out, are relevant to the reasonableness
question.
239 In Bellgrove, the High Court held that the possibility that rectification work will not
be carried out does not prevent a claim for damages.
37
In Director of War
Services v Harris,
38
Gibbs J held that a sale of the property does not of itself
affect the right to damages, but may be relevant to the question of
reasonableness:
“…If the owner subsequently sold the building, or gave it away, to a third
person, that would not affect his accrued right against the builder to
damages according to the same measure. The fact that the building had
been sold might be one of the circumstances that would have to be
considered in relation to the question whether it would be reasonable to
effect the remedial work.” (at 278)
240 In Linden Gardens Trust Ltd v Lenesta Sludge Disposals Ltd,
39
Griffiths LJ (with
whom Keith, Bridge, Ackner and Browne-Wilkinson LLJ agreed) held (citations
omitted):
“In contracts for the sale of goods, the purchaser is entitled to damages
for delivery of defective goods assessed by reference to the difference
between the contract price and the market price of the defective goods,
irrespective of whether he has managed to sell on the goods to a third
party without loss..”
241 In De Cesare v Deluxe Motors Pty Ltd,
40
Doyle CJ, Bollen and Nyland JJ held
that Gibbs J was “correct in saying that in principle the relevance of the sale of
the building is limited to its relevance to the question of whether it would be
reasonable to effect the remedial work”.
41
242 In Westpoint Management Ltd v Chocolate Factory Apartments Ltd,
42
Giles JA
(with whom McColl and Campbell JJA agreed) noted the tension between the
37
Bellgrove at p620.
38
[1968] Qd R 275.
39
[1993] 3 All ER 417.
40
(1996) SASR 28.
41
Ibid at 35.
42
[2007] NSWCA 253.
[2023] VCC 516
97
JUDGMENT
undesirability of extensive evidentiary inquiries, and the compensatory principle
of damages, his Honour held:
43
Ordinarily the court is not concerned with the use to which a plaintiff puts
its damages, and if the likelihood of the plaintiff carrying out the
rectification work were a consideration in the award of damages there
would be the potential for expensive and time-consuming factual
enquiries. On the other hand, adherence to the compensatory nature of
damages suggests that, if the plaintiff will not put itself in the position it
would have been in had the contract been performed, the plaintiff should
not be given the means of doing so.
243 His Honour went on to say:
44
Relevance of the plaintiff's intention to carry out the rectification work to
reasonableness is accepted in, for example, Chitty on Contracts, 29th
ed, at 20-016, and Hudson's Building and Engineering Contracts, 11th ed
at 8-138. It appears to have been accepted in De Cesare v Deluxe
Motors Pty Ltd - indeed, sale of the building may have relevance through
whether or not the rectification work will be carried out. If truly going to
reasonableness, I do not think consideration of whether or not the
plaintiff will carry out the rectification work is inconsistent with Bellgrove v
Eldridge, since the regard to it is part of arriving at the plaintiff's
compensable loss. Once there is compensable loss, the court is not
concerned with the plaintiff's use of the compensation.
But the plaintiff's intention to carry out the rectification work, it seems to
me, is not of significance in itself. The plaintiff may intend to carry out
rectification work which is not necessary and reasonable, or may intend
not to carry out rectification work which is necessary and reasonable.
The significance will lie in why the plaintiff intends or does not intend to
carry out the rectification work, for the light it sheds on whether the
rectification is necessary and reasonable. Putting the same point not in
terms of intention, but of whether or not the plaintiff will carry out the
rectification work, whether the plaintiff will do so has significance for the
same reason, and not through the bald question of whether or not the
plaintiff will carry out the rectification work. That question is immaterial,
see Bellgrove v Eldridge.
So if supervening events mean that the rectification work cannot be
carried out, it can hardly be found that the rectification work is
reasonable in order to achieve the contractual objective: achievement of
the contractual objective is no longer relevant. If sale of the property to a
contented purchaser means that the plaintiff did not think and the
purchaser does not think the rectification work needs to be carried out, it
may well be found to be unreasonable to carry out, the rectification work.
An intention not to carry out the rectification work will not of itself make
carrying out the work unreasonable, but it may be evidentiary of
unreasonableness; if the reason for the intention is that the property is
perfectly functional and aesthetically pleasing despite the non-complying
work, for example, it may well be found that rectification is out of all
43
[2007] NSWCA 253 [54].
44
Ibid at [59]-[61].
[2023] VCC 516
98
JUDGMENT
proportion to achievement of the contractual objective or to the benefit to
be thereby obtained.”
244 In Cordon Investments Pty Ltd v Lesdor Properties Pty Ltd,
45
Bathurst CJ (with
whom Macfarlan and Meagher JJA agreed) cited and applied the above
passage. The court held that a lack of intention to carry out the rectification work,
the transfer of the property from the defendant to an owners corporation and the
absence of any evidence that the defects were affecting the use and occupation
of the building or the common property, indicated that rectification works were
unreasonable.
46
245 In my view, the weight of the authorities distils to the proposition that the sale of
the relevant property can be evidence of a lack of intention to carry out works,
which in turn can inform the question of unreasonableness. However, it is clear
that a sale by itself does not prove unreasonableness. I would add that the
decision of the High Court in Tabcorp strongly reinforces the proposition that the
starting point is the innocent party’s strict contractual entitlement. Great care
should be taken with submissions that “rested on a loose principle of
‘reasonableness’ which would radically undercut the bargain which the innocent
party had contracted for an make it very difficult to determine in any particular
case on what basis damages would be assessed”.
47
246 The substance of UCP’s submissions is that:
(a) PHHH completed the sale and parted with any interest in the property after
commissioning the defects report, and before giving any notice of the
defects to UCP;
(b) PHHH therefore had no interest in the defects being repaired, or any ability
to carry them out; and
45
[2012] NSWCA 184.
46
Ibid at [230].
47
Tabcorp at [19].
[2023] VCC 516
99
JUDGMENT
(c) PHHH refused to allow UCP to rectify the defects under the contractual
regime.
247 In my judgment, none of these facts come close to establishing
unreasonableness of the kind discussed in the authorities. Further, it is clear (as
submitted by PHHH) that:
(a) most of the rectification work had in fact been carried out by the time of the
trial regardless of the sale; and
(b) no attempt was made by UCP in the cross-examination of Mr Honeyborne
to gainsay his evidence that he intended to reimburse the landlord or to
identify particular items of rectification that would never be undertaken or
were otherwise unreasonable.
248 Finally, and perhaps most importantly, the expert evidence (and most notably the
evidence of UCP’s own expert Mr Buchanan) established to my satisfaction that
each item of rectification work for which I have assessed damages was
objectively necessary and reasonable.
249 I therefore award PHHH damages for defects totalling $187,490.31, less the
$13,298.76 for the margin on the works UCP offered to rectify, resulting in a
damages award to PHHH for defects of $174,191.55.
Variation 37 Claim
250 On 12 December 2016, the architect certified that UCP was entitled to variation
37 and PHHH was liable to pay $167,608.54 for this variation. PHHH paid the
assessed variation amount on 21 January 2017. On about 6 July 2018 (over 18
months after certification), PHHH served a dispute notice in respect of variation
37. PHHH pleads an entitlement to repayment of the $167,608.54, on the basis
the Contract documents obliged UCP to construct steel framing to support the
timber floor joists in the level 2 floor structure of the building and it failed to do so.
[2023] VCC 516
100
JUDGMENT
On that basis, it submits that it “primarily claims damages for breach of contract
in respect of Variation 37”.
251 UCP pleads in response that it was only required to construct in accordance with
the contractual drawings, which stipulated steel beams of 300mm depth (1B4),
timber floor joists of 400mm depth and 10mm thick cleat plates with two M20
bolts located within each steel beamand that the structural design was changed
in September 2016 “to enable connection between the 400mm joists and the
300mm beam by extending the cleats and specifying three rather than two M20
bolts”. UCP asserts that the contractual drawings did not require connection
between the steel beam and timber floor joist and that PHHH was required to
supplement the design. UCP also points to the very late service of PHHH’s
notice of dispute
252 There was discrete and detailed expert engineering evidence given on this issue
from Mr Drew for PHHH and Mr Herbert for UCP. Based on this evidence, PHHH
characterises the issue as “boiling down to a question on ultimate responsibility
for shop drawings from a sequencing as opposed to a structural perspective.
UCP submits that describing the dispute of this variation as a sequencing issue
is a mischaracterisation that assumes the answer to the question. It says that: “At
its heart, the dispute over CV 37 is a documentation issue and the extent to
which the design intent was expressed in the documentation.
253 In my view, for the same reason that UCP cannot rely on clause H6 to review the
architect’s assessments of variations, PHHH is unable to circumvent the
procedure under clause A8 to re-open the architect’s certification of variation 37.
PHHH’s dispute notice was submitted more than a year after 20 working days of
the architect’s variation 37 on 12 December 2016. Thus, PHHH is not entitled to
dispute variation 37 at all, whether it purports to do so on the basis of breach of
contract or otherwise. PHHH has not argued that the architect’s decision in
[2023] VCC 516
101
JUDGMENT
relation to variation 37 is open to re-assessment by reason of partiality or on any
other ground.
254 For completeness, had it been necessary to determine the validity of variation
37, I would have endorsed the architect’s approval of the variation essentially for
the reasons stated by UCP, including that I generally preferred the evidence of
Mr Herbert where it conflicted with Mr Drew. There is also force in UCP’s
submission that the variation was supported by Amiens Consulting, whose
assessment had been commissioned by the architect, and Mr Palma’s evidence
that he accepted the variation was not UCP’s fault. I agree with UCP that: “The
relevant engineering drawings did not provide section details for the connection
ultimately used by the engineer and built by the builder”.
Utilities Claim
255 As with variation 37 and for the same reasons, in my view the last word on this
issue is PC 16 Rev A, which certifies utilities totalling $7,361.98, comprising
$401.98 for water usage and $6,960 for electricity usage. It is not open to either
party to now seek to challenge that certification for the reasons previously
explained.
256 If the position were otherwise, I would have agreed with PHHH that utilities are
payable by UCP under Contract on the basis that:
(a) pursuant to clause N1.1a of the Contract, the Contract Price allows for
everything reasonably required in accordance with the contract to complete
the *works”;
(b) Mr Palma gave unchallenged evidence that “I understand this to include the
provision of power and water to the site, both of which are essential to
carrying out the works”; and
(c) Mr Honeyborne gave evidence that the utilities claim included amounts that
were, on reflection, not due to UCP’s usage, resulting in an allowance for
[2023] VCC 516
102
JUDGMENT
utilities of $4141.79, not $10,006.31 set out in the statement of agreed
facts.
Incidental matters
257 There are two incidental matters that arose during proceedings, which I indicated
would be the subject of further elucidation in these reasons. These were:
(a) UCP’s application to amend its counterclaim; and
(b) the admissibility of pages that UCP sought to add to the tender list after the
evidence at trial had concluded.
UCP’s application to file and serve further amended counterclaim
Background
258 On 31 August 2018, UCP filed its original defence and counterclaim. On 4
December 2018, UCP filed an amended counterclaim, separating its
counterclaim from its defence. By paragraph 47 of its original defence and
counterclaim (which became paragraph 9 of the amended counterclaim, but was
otherwise unamended), UCP pleaded that:
“In breach of clauses A6.4, H6 and J5, the Plaintiff has failed to ensure
that the Architect, as certifier, adjusted the contract price and the date for
practical completion fairly and honestly in accordance with the relevant
quotations/variations”.
259 Thus at all times up to and including the start of the trial, UCP essentially relied
only on clause H6 (together with the allegation of the architect’s impartiality and
the breach of clause A6.4) as the source of its entitlement to have the architect’s
certifications of variation and EOTs revisited by the court, standing in the shoes
of the architect. Neither party relied on, or otherwise referenced, the regime for
disputing the architect’s certificates under clause A8.
260 On the first day of the trial (22 February 2021), both parties sought to make what
were, for the most part, uncontroversial amendments to their pleadings. PHHH
sought to rely on a draft amended defence to amended counterclaim that
[2023] VCC 516
103
JUDGMENT
updated details of the alleged Contract Price, amended paragraph numbering
and sought to amend paragraph 4 and add a new paragraph 4A. This had
apparently been sent to UCP’s solicitors about a week before trial.
261 UCP sought to rely on a draft amended counterclaim (also updating details of the
alleged Contract Price and revising and further particularising its claim amounts),
and a draft reply to PHHH’s draft amended defence and amended defence to
amended counterclaim. These had apparently been provided to PHHH’s
solicitors a day or so before trial.
262 PHHH’s proposed amendments to paragraph 4 and its proposed paragraph 4A
was the first substantive pleading referring to the dispute regime in paragraph A8
of the Contract. The proposed amendment to paragraph 4 essentially recited the
alleged effect of clauses H6 and A8 of the Contract. The proposed new
paragraph 4A positively asserted that UCP had failed to dispute the architect’s
certifications (or failure to certify) under clause A8 and was therefore not entitled
to raise such a dispute.
263 In its proposed reply to the proposed new paragraph 4A, UCP denied the effect
of clause A8 as alleged by PHHH and, “further or alternatively”, sought to raise
an argument to the effect that PHHH had waived reliance, or was estopped from
relying, on strict compliance with the time limits imposed by the Contract. UCP’s
proposed reply generated debate on the first day of trial. In particular, while UCP
initially disclaimed any need to plead relief under clause A8, PHHH was
concerned to ensure that UCP did not use the proposed reply or other
amendment as a Trojan horse to introduce an estoppel or other fresh claim
that went beyond reliance on clause H6.
264 The debate continued on the second day of trial, in the course of and after each
party’s openings. By the end of that day, it had become apparent that UCP was
seeking to agitate issues that necessitated additions to UCP’s draft further
amended counterclaim. An updated draft was provided by UCP overnight and
[2023] VCC 516
104
JUDGMENT
was discussed at the commencement of the third day. Given the extent of the
amendments and the importance of the application for the future conduct and,
potentially, the outcome of the trial, I adjourned the trial for the rest of that day to
allow the parties time to file and serve any affidavits and outlines of submissions.
265 UCP duly filed and served submissions and an affidavit of Ms Nomikos, the
principal lawyer of Macpherson Kelley, UCP’s solicitors. PHHH filed submissions
and an affidavit of Mr Honeyborne and Mr Noble, the principal lawyer of Noble
Lawyers, PHHH’s solicitors. I heard the application on 25 February 2021 and
gave my preliminary ruling that day. I indicated to the parties that I would settle
and elaborate on that ruling in my final reasons for decision in the proceeding,
unless either party needed the settled ruling sooner. Neither party expressed
such a need.
Summary and outcome
266 UCP’s proposed amendments are in two categories. First, revisions and some
further particulars to its claim amounts and what it alleged is the correct Contract
price. Second, amendments alleging that:
(a) UCP had issued notices of dispute pursuant to clause A8 during the course
of the Contract;
(b) PHHH is estopped from relying on strict time limits in the Contract;
(c) UCP had suffered loss and damage by reason of PHHH’s alleged failure to
ensure the architect acted fairly and impartially; and
(d) UCP had suffered damages in the amount of variations and prolongation
claims, that ought to have been granted by the architect.
267 The first category of amendments were essentially agreed, although there was a
dispute over some of UCP’s revised figures. This was resolved in UCP’s further
[2023] VCC 516
105
JUDGMENT
amended counterclaim as filed. PHHH objected to all of the second category of
amendments.
Submissions
268 In both oral and written submissions, UCP identifies a number of reasons why
leave ought to be granted. These are (in summary):
(a) the pleadings in relation to clause A8 and estoppel are necessary to
respond to PHHH’s reliance on clause A8 as a bar to UCP’s claim, which
PHHH raised for the first time in opening submissions;
(b) the interests of justice would favour the amendments being allowed and any
inconvenience and delay would be ameliorated because the interests of
justice would be met;
(c) not allowing the amendments could radically change the outcome of the
final trial; UCP would suffer irreparable prejudice as the true issues in
controversy could not be determined;
(d) the amendments sought were not markedly different from the existing case
and stood within the parameters of the current dispute UCP was simply
seeking to impose a recognised category of relief on what was already
alleged;
(e) this was not the case where UCP was seeking to waste court resources
and time by “seeking to treat the trial hearing as a bargaining counter in the
strategic forensic activities”; and
(f) on the question of whether those behind PHHH would suffer significant
personal stress if the trial were vacated after three days, UCP submitted
that while the stress to litigants is “a respectable and proper consideration”,
stress is inherent to a commercial undertaking for profit on both sides and
would be experienced by litigants in any event.
[2023] VCC 516
106
JUDGMENT
269 In respect of the reason for the lateness of the amendment application, UCP
submitted it was not aware that clause A8 was being raised as a bar to its
counterclaim until opening submissions and, in any case, UCP had never
suggested that clause H6 was the sole clause of the Contract being relied on.
UCP argued that: “it can[not] seriously be said that… the defendant’s plan,
considered plan was to argue all of this on the basis only of [clause] H6”.
270 PHHH in its oral and written submissions identified a number of considerations
that weighed against the grant of leave. These are (in summary):
(a) while clause A8 is a bar to claim, this bar was not raised as a defence by
PHHH clause A8 was only referred to as part of PHHH’s defence to
identify that it was relevant to the construction of clause H6;
(b) the case in UCP’s counterclaim (relying on clauses H6 and A6.4 of the
Contract) is the case that was pleaded for two-and-a-half-years and was the
case UCP opened on in written and oral submissions. The addition of
clause A8 to its counterclaim drastically departs from this position; and
(c) the claim UCP sought to add in relation to clause A8 was “markedly
different” to the claim pursued pursuant to clause H6 and would necessitate
new evidence including the deposition of different witnesses.
271 Further, counsel for PHHH submitted that even if the further amendments then
proposed by UCP were allowed, this would not have the effect UCP sought (that
is, forming the basis of an increase to the Contract Price). For UCP to be able to
rely on clause A8, it would need to first allege that clause H4 had been breached,
and then particularise each variation claim and EOT it was entitled to under
clauses J to L of the Contract (as applicable), clause H4 and then clause A8.
PHHH submitted that by only including pleadings in relation to clause A8, UCP
was seeking to bypass the relevant questions of entitlements that were a
necessary prerequisite to such a pleading.
[2023] VCC 516
107
JUDGMENT
Ruling
272 Having considered both the written and oral submissions of the parties, on 25
February 2021, I ruled that UCP’s application to introduce a claim involving
reliance on clause A8 of the contract and notices purportedly served thereunder,
would be dismissed. More specifically I ordered that UCP’s “application to file
and serve a proposed further amended counterclaim in the form of the document
exhibited to the affidavit of Victoria Nomikos sworn 24 February 2021, by adding
proposed paragraphs 9A-E, 12, and C in the prayer for relief and by making any
further amendment to paragraph 9, is dismissed”.
273 I otherwise allowed both applications, made further orders for the filing and
service of further pleadings accordingly and ordered that UCP pay PHHH’s costs
of and incidental to the UCP’s application. As noted above, I gave brief reasons
for my ruling, but indicated that I would elaborate on those reasons in my
reasons for judgment in the proceeding generally. I do so as follows.
Reasons for ruling
274 It is trite that the power to grant leave to amend a statement of claim is
discretionary. The High Court in Aon Risk Services Australia v Australian
National University
48
(“Aon”) held:
“An application for leave to amend a pleading should not be approached
on the basis that a party is entitled to raise an arguable claim, subject to
payment of costs by way of compensation. There is no such entitlement.
All matters relevant to the exercise of the power to permit amendment
should be weighed.”
49
275 The question is “what do the interests of justice dictate?”.
50
The interests of
justice will vary greatly depending on the circumstances.
51
I am to consider and
weigh a wide range of factors as set out in Aon, including:
52
(a) whether there will be a substantial delay caused by the amendment;
48
(2009) 239 CLR 175.
49
Aon Risk Services Australia Ltd v Australian National University (2009) 239 CLR 175 at 217 [111].
50
Traffic Technique Pty Ltd v Burgmann [2020] VSCA 319 at [58].
51
Traffic Technique Pty Ltd v Burgmann [2020] VSCA 319 at [58].
52
Caroll v Goff [2021] VSCA 267 at [75].
[2023] VCC 516
108
JUDGMENT
(b) the extent of any wasted costs;
(c) whether there is an irreparable element of unfair prejudice caused by the
amendment;
(d) concerns of case management arising from the stage in the proceeding
when the amendment is sought;
(e) whether allowing the amendment will lessen public confidence in the judicial
system; and
(f) whether a satisfactory explanation has been given for seeking the
amendment at the stage when it is sought.
276 These factors are echoed in the provisions of Civil Procedure Act 2010 (“CPA”),
including:
(a) section 7, which provides that the overarching purpose of the CPA is to
facilitate the just, efficient, timely and cost-effective resolution of the real
issues in dispute”;
(b) section 8, under which the court must give effect to the overarching purpose
in the exercise of its powers; and
(c) section 9, under which the court may further the overarching purpose in
making any order or giving any direction.
53
277 Like in Traffic Technique Pty Ltd v Burgmann,
54
the matters to be considered in
this case are finely balanced. On the one hand, UCP ought to be able to have
the substantive merits of its case heard and determined. On the other hand,
PHHH should not suffer irreparable prejudice as a result of allowing the
contested amendments. I was satisfied on balance that the interests of justice lie
in denying the contested amendments.
53
Civil Procedure Act 2010 (Vic) s 9.
54
[2020] VSCA 319.
[2023] VCC 516
109
JUDGMENT
278 The contested amendments would have caused substantial delay. Had those
amendments been allowed, the trial would be adjourned for a fourth time. At the
time, there was no available trial date until at least August 2021 and thus the
delay would have been at least another six months.
279 A delay of this duration was unacceptable because, at the time of UCP’s
application, there had already been substantial delay to the proceedings:
(a) PHHH had commenced these proceedings in April 2018; and
(b) the trial had been adjourned three times:
(i) the first listed trial date was 8 July 2019, which was adjourned due to
appeal of the court’s decision regarding security for costs;
(ii) the second listed trial date was 29 June 2020, which was adjourned
due to the defendant’s joinder of third parties; and
(iii) the third listed trial date was 23 November 2020, which was adjourned
to give the third parties additional time to prepare for trial.
280 Further, the prejudice this delay would cause to PHHH would be irreparable and
was unacceptable. First, the contested amendments and the delay they would
have occasioned would have cause significant financial hardship for PHHH. I
agree with PHHH’s submission that:
(a) PHHH had been preparing for the trial of the case in the amended
counterclaim for almost two years, and the claims it sought to add materially
differed from (and added to) this case; and
(b) had the amendments been allowed, PHHH would be required to re-do and
substantially add to witness statements, and undertake extensive
investigations into the dozens of alleged dispute notices and any
responses, before to be able to respond to the new allegations.
[2023] VCC 516
110
JUDGMENT
281 Second, in my view, UCP’s proposed new pleading relying on clause A8 of the
Contract and estoppel itself constituted a substantive new claim. However, I
agree with PHHH’s submission that amendments proposed by UCP at the time
of the application were an incomplete articulation of a fresh claim relying on
clause A8. As UCP effectively conceded, to constitute a complete claim, it would
have been necessary for UCP to add pleadings and particulars of breaches of
clause H4.
282 More particularly, as I noted in the course of oral submissions, to substantiate
claims under clause A8, UPC would first need to establish entitlement to each
variation or EOT claim under the relevant provisions of the Contract. It would
then need to identify and particularise the architect’s alleged failure under clause
H4 (that is, whether it was a failure to decide within 20 days or whether it was
decided in 20 days but decided incorrectly). At the time of the application, there
was no claim made pursuant to clause H4. Further, none of the proposed
amendments in relation to clause A8 informed UCP’s allegation of PHHH’s
breaches of clauses A6.4, H6 or J5 provisions which UCP had relied on for
over two years.
283 Third, in my view, the financial and non-financial difficulties that PHHH would
suffer as a result of the amendments could not be adequately compensated by
an order for costs. I was satisfied that PHHH would suffer substantial and
probably irreparable prejudice in the form of considerable stress and anxiety for
the director Mr Honeyborne, and Mrs Honeyborne, which would be prolonged
and exacerbated by the substantial further delay and the additional legal and
other expenses the amendments would cause. In an affidavit of Mr Honeyborne
dated 25 February 2021, Mr Honeyborne deposed (and I accepted) that:
(a) disputes relating to this development had been “a constant source of stress
and anxiety” for Mr Honeyborne and his wife, Mrs Honeyborne, and an
adjournment would exacerbate these circumstances;
[2023] VCC 516
111
JUDGMENT
(b) Mr Honeyborne had been personally bearing the expenses incurred as a
result of the proceedings (in addition to other proceedings relating to this
development);
(c) Mr and Mrs Honeyborne’s family finances had been strained due to the
expenses incurred as a result of the proceeding and they had to enter a
loan agreement to provide working capital for the childcare business run by
Mrs Honeyborne;
(d) during June 2020, Mr and Mrs Honeyborne “came seriously close to losing
[their] business” as a result of the financial stress caused by the expense of
the proceedings; and
(e) Mr Honeyborne had been “barely able to contain the elevated levels of [his]
anxiety and stress” since the defendant’s solicitors served Mr Honeyborne
(and thereby PHHH) with a statutory demand for payment of $100,000 on
the second day of trial.
284 Fourth, as I also noted during the trial, the amendments sought could not be
explained by anything other than an oversight. UCP had elected to pursue its
claim through the narrow window of clause H6. Its proposed amendments sought
to open a second window, to an entirely new claim. I do not accept UCP’s
submission that the amendment was necessary to respond to PHHH’s reliance
on clause A8 as a bar. PHHH did not raise clause A8 in this way clause A8
was raised to inform the construction of clause H6, which UCP had relied on in
its counterclaim. UCP now contends that its success at trial could depends on an
alternative ground based on an alleged failure in the dispute resolution procedure
under clause A8, that ground ought to have been pleaded well before the three
days into the trial.
[2023] VCC 516
112
JUDGMENT
Admissibility of Tranche 14
Background
285 On 13 April 2021, by email, UCP provided copies of documents it sought to the
court book and, namely tender drawings, a second Powercor invoice and
payment records from UCP (“Tranche 14”) and an amended court book index.
PHHH objected to the purported addition of Tranche 14 to the court book and
requested that the court disregard Tranche 14, on the basis that it was not
appropriate for UCP to attempt to introduce further document after evidence in
the proceeding was closed and given that PHHH had not agreed to the
documents.
286 Shortly thereafter, I indicated my preliminary view that Tranche 14 would not be
received as part of the tender for the reasons provided by PHHH. I invited parties
to make submissions, if UCP were to press the issue, and I indicated that I would
address the issue in these reasons. On 20 April 2021, UCP filed submissions in
relation to the inclusion of Tranche 14, and PHHH did the same on 23 April 2021.
287 In its written submissions, UCP narrowed the tender drawings it sought to add to
a single tender drawing, drawing H05 Rev T1 a civil engineering tender
drawing prepared by Perrett Simpson and Stantin Consulting Engineers, which
relates to the overflows issue and variation 94. UCP submitted that this drawing
was important for the court’s deliberation, given that it was referred to in the
expert report of Mr Jeffrey,
55
one of PHHH’s experts, and UCP’s written closing
submissions. According to UPC, it was only seeking to correct an administrative
error by adding the drawing to the court book, since the drawing was referenced
in the court book index.
288 In its written submissions, PHHH agreed to the inclusion of the drawing as a
document referred to by Mr Jeffrey, but on the basis that no witnesses had been
taken to the document during oral evidence.
55
The written submissions refer to this being a report by Mr Naughton, but this was corrected in an
email on behalf of UCP dated 22 April 2021.
[2023] VCC 516
113
JUDGMENT
289 In relation to the second Powercor invoice and associated payment records
(“Powercor documents”), UCP sought to tender these on the basis that, absent
those documents, there was a “serious risk of a mischaracterisation of UCP’s
credit. UCP noted that the invoice was the subject of oral evidence of Mr Potter,
who stated that the invoice had been claimed twice, but he “wouldn’t say it was
double dipping”. And, as I observed during the trial, there was only one invoice in
evidence before me at that time. UCP further submitted that such
mischaracterisation of UCP’s conduct may result in a miscarriage of justice,
when there is evidence available to support that there were two discrete invoices.
290 PHHH submitted that UCP sought to add the Powercor documents to make good
its claim to variation 99, by providing a narrative around matters that were not the
subject of evidence at trial. PHHH submitted that it was unfair to include the
Powercor documents, since Mr Palma was cross examined on the one Powercor
invoice in the court book. In relation to UCP’s concern about a suggestion that it
had engaged in double-dipping, PHHH agreed not to allege double-dipping in
relation to the Powercor invoices.
Ruling
291 It was not in dispute that the question of whether UCP ought be given leave to (in
effect) reopen its case and tender any of the Tranche 14 documents, is a matter
entirely within my discretion. I also note that Rule 34A.29 of the Rules provides
that: “Save with the leave of the Court or by consent of the parties, a party shall
not tender in evidence at the trial of a proceeding a document a copy of which
the party was required to include in the court book of the party but which the
party did not include.
292 Since PHHH consents to the addition of drawing H05 Rev T1, the tender of this
drawing is accepted by consent, in accordance with rule 34A.29.
293 In respect of the Powercor documents, I agree with PHHH’s submissions that it
would be unfair to admit this document after the evidence has closed, particularly
[2023] VCC 516
114
JUDGMENT
as PHHH is effectively denied the opportunity to put the document to Mr Palma.
Further, since PHHH has not pressed the “double-dipping” argument, the
admission of Powercor documents is not necessary to head off any suggestion of
sharp practice by UCP.
- - -
Certificate
I certify that these 114 pages are a true copy of the judgment of his Honour Judge
Woodward delivered on 5 April 2023.
Dated: 5 April 2023
Darcy White
Associate to his Honour Judge Woodward