ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of -- )
)
P.R. Contractors, Inc. ) ASBCA No. 52937
)
Under Contract No. DACW29-97-C-0031 )
APPEARANCE FOR THE APPELLANT: Mr. Cedric Patin
President
APPEARANCES FOR THE GOVERNMENT: Thomas H. Gourlay, Jr., Esq.
Engineer Chief Trial Attorney
Gwenn B. Nachman, Esq.
District Counsel
Anthony C. Occhipinti, Esq.
Engineer Trial Attorney
U.S. Army Engineer District,
New Orleans
OPINION BY ADMINISTRATIVE JUDGE TUNKS
This is an appeal from a contracting officer’s final decision terminating a contract
for default for failure to timely complete a construction contract.
FINDINGS OF FACT
1. On 8 November 1996, the New Orleans District of the Army Corps of Engineers
(Corps) issued Invitation for Bids (IFB) No. DACW29-97-B0027 to enlarge a levee in
Plaquemines Parish, Louisiana (R4, tab D).
2. After the low bidder withdrew its bid, the Corps asked P.R. Contractors, Inc.
(PR), the next low bidder, to verify its bid. PR verified its bid on 6 March 1997.
(Tr. 35-36; R4, tab C-22)
3. The Corps awarded Contract No. DACW29-97-C-0031 in the amount of
$1,049,277.50 to PR on 17 March 1997. The work included clearing and grubbing,
building access roads, ramps and stone pads, excavating fill from a borrow pit, hauling fill to
the site, enlarging the levee, building a berm on the flood side of the levee and a double
ramp at the Happy Jack Marina. The contract completion date was 240 days after receipt of
the notice to proceed (NTP). (R4, tab D; tr. 325)
2
4. FAR 52.249-10 DEFAULT (FIXED-PRICE CONSTRUCTION) (APR 1984), which was
incorporated into the contract by reference, provided, in part, as follows:
(a) If the Contractor . . . fails to complete the work within
[the time specified or any extension thereof], the Government
may, by written notice to the Contractor, terminate the right to
proceed with the work . . . .
(b) The Contractor’s right to proceed shall not be terminated
. . . if
(1) The delay . . . arises from unforeseeable causes
beyond the control and without the fault or negligence of the
Contractor . . . [or] delays of subcontractors or suppliers at any
tier arising from unforeseeable causes beyond the control and
without the fault or negligence of both the Contractor and the
subcontractors or suppliers . . . .
(R4, tab D)
5. The project was located on the southwest side of Louisiana Highway 23 (LA Hwy.
23). The levee ran in a north-south direction. The City Price drainage structure formed the
upper or northern limit of the project and the Hayes pumping station formed the lower or
southern limit. The east side of the levee was “protected” and trucks were not permitted to
haul on that side. The west side or the flood side could be used for hauling fill. (R4, tab D,
Drawing No. H-8-44755 at sheets 2, 3; tr. 188-89)
6. Specification section 00800, Special Contract Requirements, contained the
following provisions that are relevant, in part, to this appeal:
3. CONTRACT DRAWINGS, MAPS AND SPECIFICATIONS.
(DFARS 252.236-7001 - 1991 DEC).
. . . .
d. Omissions from the drawings or specifications . . . of
details of work which are manifestly necessary to carry out the
intent of the drawings and specifications, or which are
customarily performed, shall not relieve the Contractor from
performing such omitted . . . details of the work, but shall be
performed as if fully and correctly set forth and described in
the drawings and specifications.
3
. . . .
5. PHYSICAL DATA . . . .
. . . .
c. Transportation Facilities . . . . Access to the lower limit of
the . . . site for haul operations opposite B/L [levee baseline]
Station 104+50 is by Hwy. 23, then by unimproved corridors
across vacant and lightly wooded fields, then across an
unbridged drainage canal . . . then across a buried 18 inch water
main . . . onto existing levee. Access to the upper limit of the .
. . site for haul operations is by Hwy. 23, then along berms and
the crown of an existing levee within the . . . right-of way
corridor between Hwy. 23 and the back levee . . . . The
Contractor shall be responsible for maintaining the streets and
roads free from any mud tracking, spillage and/or other surface
pollution . . . . Stone pads [or] wash racks . . . as set forth on the
drawings at each haul corridor entrance to Hwy. 23 . . . shall be
required to maintain clean streets and roads . . . . The
Contractor must submit his/her access plans for approval prior
to mobilization . . . .
(R4, tab D)
7. Specification section 01100, General Provisions, contained the following
additional relevant provisions:
3. SAFETY PROVISIONS . . . .
. . . .
b. Accident Prevention Program.
. . . .
(4) . . . The Contractor shall not commence physical work
at the site until the program has been accepted . . . .
. . . .
6. RIGHTS-OF-WAY.
4
a. Rights-of-way for construction purposes and for access
through private lands . . . will be furnished by the Government . .
. as shown on the contract drawings . . . .
. . . .
15. ORDER OF WORK.
. . . .
b. Marina Ramp Area.
. . . .
2) The Contractor shall provide continuous access to the
Happy Jack Marina. The Contractor shall submit a
“Continuous Access Plan” . . . for approval . . . .
(R4, tab D)
8. Specification section 02220, Excavation, contained the following relevant
provisions:
3.3 Contractor-Furnished Borrow Areas.
3.3.1 General. The Contractor, at his/her option, may use
borrow areas other than those indicated . . . .
3.3.2 Time Extensions. No time extension to the contract
completion date will be granted . . . for delays incurred in
obtaining Contractor-furnished borrow areas . . . .
9. Specification section 02225, Embankment, contained the following relevant
provisions:
8.1 Access Roads.
8.1.1 . . . Plaquemines Parish . . . will identify the location of
access corridors as shown on the drawings . . . . The Contractor
shall construct stone pad and surfacing highway entrances as
detailed on the drawings . . . to maintain clear streets and roads .
. . .
5
. . . .
8.2 Ramps and Crossings.
8.2.1 Ramps . . . shall be constructed at the locations shown
on the drawings . . . .
(R4, tab D)
10. The contract incorporated sheets 1 through 12 of Drawing No. H-8-44755.
Sheets 2 and 3 depicted two “haul access” roads between LA Hwy. 23 and the levee. The
upper haul access road was at station 8+00 and the lower haul access road was at station
104+50. The drawings depicted “stone pads” or wash racks on each of the haul access
roads where they entered LA Hwy. 23 to protect the highway from mud and other pollutants.
(R4, tab D; tr. 190)
11. Sheets 2 and 3 also showed two “light access” roads between LA Hwy. 23 and
the levee. One of the light access roads entered the Happy Jack Marina at station 29+00.
The other intersected the levee at station 112+00. The contract did not define a light
access road. The drawings did not show stone pads on either of the light access roads. (R4,
tab D)
12. The contract did not specifically require PR to build turn-arounds (R4, tab D).
13. On 2 May 1997, the Corps requested PR to submit a revised Accident
Prevention Plan, stating that work at the site could not begin until an acceptable plan had
been submitted (R4, tab C-3).
14. PR acknowledged receipt of the NTP on 15 May 1997, establishing a contract
completion date of 10 January 1998 (R4, tab C-4).
15. At the pre-construction conference held on 15 May 1997, PR advised the Corps
that it was going to use an alternate borrow pit instead of the Government borrow pits
indicated on the drawings (tr. 65-66, 179).
16. On 17 June 1997, the Corps again requested PR to submit its revised Accident
Prevention Plan, stating that no work could begin at the site until an acceptable plan had
been submitted. The Corps also requested PR to submit its construction progress schedule,
submittal register and submittals. (R4, tab C-5)
17. On 27 June 1997, the Corps requested PR to submit its alternate borrow
submittal, stating that the contract precluded time extensions for delays in obtaining an
6
alternate borrow pit. The Corps also advised PR that about 18 percent of the contract time
had passed without any work being performed at the site. (R4, tab C-6; tr. 66-70, 179-80)
18. On 24 July 1997, the Corps again asked PR for its alternate borrow submittal,
reiterating that no time extensions would be granted for delays in obtaining an alternate
borrow pit. The Corps also advised PR that about one-third of the contract time had passed
without any work being performed at the site. (R4, tab C-7; tr. 70-71, 180-81)
19. On 8 September 1997, the Corps approved PR’s alternate borrow submittal.
The Corps also stated that 47 percent of the contract time had passed without any work at
the site and urged PR to begin work “without any further delays” (R4, tab C-8).
20. PR’s first earthwork subcontractor mobilized at the site on 17 September
1997, 125 days after the NTP was acknowledged (ex. Bd.-1 at Report No. 1; tr. 186).
21. PR submitted its access plan on 18 September 1997. The plan stated that PR
intended to proceed by “using the indicated whole access road in the attached sketches and
then on top of the levee[,] backing up, dumping and driving back to the same whole road.”
On the sketches, PR highlighted LA Hwy. 23 and the two haul access roads in green and the
two light access roads in pink. The legend stated that green denoted a “2 way haul access
road” and pink denoted a “2 way light access road.” (Ex. A-2; tr. 208) In view of the
legend, it appears that, in typing the plan, the word “whole” was mistakenly typed for the
word “haul” and we so find. The plan did not indicate which haul access road PR planned to
use or that it intended to have empty trucks exit using the light access road at the marina.
With one exception not relevant here, the Corps approved the plan on 19 September 1997
(ex. A-1).
22. In order to make the upper haul access road usable, PR had to strip the levee
from the north end, build a stone pad to protect the highways and construct ramps over the
levee to allow the trucks to use the upper haul access road. Although PR suggested at the
hearing that another contractor may have built a stone pad on the upper haul access road
during a prior project, it did not present any evidence that there was an existing stone pad on
the upper haul access road (tr. 296-98, 311-13). We conclude that PR did not build a stone
pad on the upper haul access road. The unrebutted testimony of Mr. John G. Fogarty, Jr.,
the Corpsproject engineer, establishes that PR did not build access ramps over the north
end of the levee until April 1998 (tr. 174-75, 296-98, 301, 313-14). We conclude that the
upper haul access road was not usable until at least April 1998.
23. Due to the physical limits of the levee and the fact that the protected side could
not be used for hauling, there were only two ways to perform the work. PR could have built
the levee cap and left the flood side berm open, which would have allowed access to the
upper haul access road for a short time. Once PR began building the berm, however, access
to the upper haul access road would have been blocked. (Tr. 188-89, 190-91) This method
7
was not viable because the upper haul access road was not usable until April 1998. The
other option was to build the levee and the flood side berm to their full width at the outset.
This approach would have blocked PR’s access to the upper haul access road after the first
day and is the plan PR chose to use (tr. 296, 300; see finding 21).
24. On the first day of hauling, PR’s trucks entered the site from the lower haul
access road (not from the upper haul access road as PR alleges it planned to do) and
dumped their loads on the south side of the marina (tr. 187-88). The first three empty
trucks tried to exit via the light access road at the marina. The Corps stopped PR from
using that road, stating it could only be used for personnel vehicles. (Tr. 208)
25. PR alleges that it next tried to cross the marina and to exit at the upper haul
access road. According to PR, a Corps employee prohibited it from crossing the marina
access. (Tr. 208, 348) There is insufficient evidence for us to find that the Corps issued
such a directive. PR did not identify the authorized Corps employee who issued the alleged
directive and there is no contemporaneous documentary evidence corroborating PR’s
assertion. In any event, PR could not have used the upper haul access road because the
upper haul access road was not usable until April 1998 (tr. 301, 313).
26. PR’s trucks turned around on the south side of the marina and exited via the
lower haul access road. In turning around, one or more of the trucks allegedly crossed onto
the property of a private landowner, Judge Emile E. Martin. Judge Martin and Mr. Hage,
appellant’s project manager, got into a heated argument. Judge Martin did not make any
other complaint regarding PR’s trucks crossing onto his property during the contract. (Tr.
207-10, 212-20, 280-81, 305-08) PR did not present any evidence showing that it could
have turned around in this area without crossing onto Judge Martin’s property.
27. PR built “turn-arounds” in locations where it was too narrow for its trucks to
turn around (tr. 210, 303, 332). Before the turn-arounds were built, some haul trucks had to
back out of the site (tr. 282). It is a common practice to build turn-arounds where the site
is too narrow to permit equipment to turn around (tr. 303-04).
28. The Corps extended the contract completion date to permit PR to perform the
work at the marina between 15 January and 15 April 1998 (R4, tab C-1 at Mod. P00001,
tabs C-10, C-34; tr. 76). The work at the marina had to be completed by that date in order to
avoid interfering with the shrimping season (R4, tab C-23; tr. 84).
29. PR’s first earthwork subcontractor demobilized and left the site on 12 January
1998 (ex. Bd.-1 at Report No. 28; R4, tab C-14).
30. On 20 January 1998, the Corps advised PR that the work was 32 percent
complete and requested PR to submit a plan showing how it intended to regain the approved
schedule (R4, tab C-14; tr. 78-79).
8
31. On 29 January 1998, the Corps received a letter from Contract Bond Claims
Management, Inc., a claims agent retained by PR’s surety, National American Insurance
Company (National American). The letter stated that the company was investigating a claim
that PR had failed to pay $190,986.56 in equipment rental fees in connection with this
project and requested the Corps to make all future contract payments to National American.
(R4, tab C-15; tr. 45)
32. On 3 February 1998, the Corps again expressed concern over PR’ s lack of
progress and asked PR how it planned to regain the schedule. The Corps also advised PR
that two equipment rental companies had contacted it regarding nonpayment of rental and/or
lease costs for equipment supplied to the project (R4, tab 16; tr. 79-80, 182-83).
33. On 11 March 1998, PR’s second earthwork subcontractor, H. L. Marshall,
began work at the site (ex. Bd.-1 at Report No. 28).
34. On 17 March 1998, the Corps issued an Interim Unsatisfactory Construction
Contractor Performance Evaluation Report to PR (R4, tab C-19; tr. 50-51, 80-82, 184).
35. On 18 March 1998, PR requested relief for a bid mistake, stating that it had
inadvertently omitted the cost of trucking from its estimate (R4, tabs C-20, C-21, C-28; tr.
34-36). The Corps denied the request on 30 March 1998 on the basis that PR had verified
its bid before contract award (R4, tab C-22; tr. 34-36).
36. The Quality Assurance Report (QAR) for 20 March 1998 provided as follows:
Mr. Marshall has been informed from locals [that] P & R
Construction’s reputation [from the] previous contract is not
good. They also informed Mr. Marshall that P & R did not pay
the Bank, Grocery, Truckers, Material suppliers etc. so
therefore, they will not sell (P & R) anything, nor will they
have anything to do with P& R Construction, making it
extremely difficult for the dirt sub to complete the Marina on
schedule.
(Ex. Bd.-1 at Report 33)
37. On 6 April 1998, National American advised the Corps that it had received
claims on several of PR’s contracts, including the subject contract, and requested that all
further contract funds be paid to National American (R4, tab C-24).
38. The work at the Happy Jack Marina was not completed by 15 April 1998 (tr.
185-86, 201).
9
39. On 24 April 1998, Marshall demobilized and left the site due to nonpayment
(ex. Bd.-1 at Report No. 58). Through-out the time Marshall worked at the site, PR had
difficulty paying its subcontractors and material suppliers (ex. Bd.-1 at Report Nos. 28
through 58; tr. 201).
40. The Corps deleted the uncompleted portion of the work at the marina on
28 April 1998 (tr. 54; R4, tabs C-1, C-34 at Mod. No. P00003).
41. On 7 May 1998, PR requested the Corps to make all payments due or to become
due on account of its contract to its surety, National American (R4, tab C-31).
42. On 14 May 1998, the Corps again expressed concern over PR’s lack of
progress, noting that PR had not worked at the site since 24 April 1998 (R4, tab C-32; tr.
82-83).
43. On 1 June 1998, PR asked National American to complete the work. In its
agreement with the surety, PR admitted that it could not pay “certain subcontractors and
suppliers of labor and//or materials” under this contract and that it “can not [sic] complete
the [project] without financial assistance . . . from the surety.” (R4, tab C-33 at 1, 2)
44. On 16 June 1998, the Corps issued a show cause notice to PR, requesting it to
present any excuses it had for failing to complete the work (R4, tab C-34). PR did not
respond (tr. 53; R4, tab C-35).
45. The contract completion date was ultimately extended until 30 June 1998 (R4,
tab C-2 at Mod. P00009; tr. 139).
46. On 1 July 1998, the contracting officer terminated the contract for default for
failure to timely complete the work (R4, tab C-1, Mod. No. P00009; tr. 29).
47. PR timely appealed the contracting officer’s decision to the Corps of
Engineers Board of Contract Appeals on 21 September 1998, where it was docketed as
ENG BCA No. 6428. The appeal was re-docketed as ASBCA No. 52937 on 12 July 2000.
48. On 1 October 1998, PR submitted “PR Contractor’s, Inc. Defense of
Termination for Failure to Perform” (PR’s Defense). This document provided, in part, as
follows:
Upon commencement of the work, the [Corps] issued a
directive to PR prohibiting haul trucks from crossing the
marina area. This directive constituted a constructive change
order of tremendous impact . . . .
10
. . . .
This [change] made performance by PR all but impossible, as
the much more expensive method of construction imposed by
the [Corps] required the work to be performed at an excessive
and unreasonable cost exceeding the financial and commercial
capabilities of PR to perform.
PR’s initial efforts to perform were abandoned after roughly
3 months, with costs exceeding production revenue, and
financial resources. Subsequently, after roughly 2 months of
inactivity, PR’s second effort to perform, spanning a 6-week
period, met with similar results. The work was abandoned again
and PR was terminated for default . . . .
(Ex. G-2; tr. 36-40)
DECISION
When the Government terminates a contract for default, it has the burden of proving
the propriety of its actions. Lisbon Contractors, Inc. v. United States, 828 F.2d 759,
763-65 (Fed. Cir. 1987). Under the default clause in this contract, FAR 52.249-10
DEFAULT (FIXED PRICE CONSTRUCTION) (APR 1984), the contracting officer had the right
to terminate the contract for default if PR failed to complete the work within the time
specified or any extension thereof. As extended, the contract completion date was
30 June 1998. It is undisputed that PR did not complete the contract by that date.
Accordingly, the Government has established a prima facie case that its termination for
default was proper.
The burden of proof now shifts to PR to prove that the default was beyond its control
and without its fault or negligence. Magna Enterprises, Inc., ASBCA No. 51188, 02-1
BCA ¶ 31,660 at 156,419. PR contends that the default should be excused because the
Corps changed the “means and methods” by which it planned to perform the work, causing
it to incur such excessive and unreasonable costs that it was financially incapable of
completing the contract (app. post-trial memo. at 1). PR alleges that the Corps changed the
way it planned to do the work in the following ways:
1. By directing the contractor to cease using the “light
access” road from the Happy Jack Marina to Hwy. 23.
2. By directing the contractor to cease crossing the Marina on
the levee crown.
11
3. By directing the contractor to cease turning trucks around in
the vicinity of Judge Martin’s property near the marina.
4. By directing and forcing without option, PR’s having to
build turnarounds in the marsh, outside the right of way.
(App. reply memo. at 1)
A contractor is responsible for having sufficient financial resources for the
performance of a contract and its financial inability to perform is not generally regarded as
beyond its control. Local Contractors, Inc., ASBCA No. 37108, 92-1 BCA ¶ 24,491 at
122,235, aff’d on reconsid., 92-1 BCA ¶ 24,693, aff’d, 988 F.2d 131 (Fed. Cir. 1993)
(table). In order for a default termination to be excused on the basis of financial incapacity,
the contractor must prove that its incapacity was caused by the Government. Danzig v. AEC
Corp., 224 F.3d 1333, 1339 (Fed. Cir. 2000), cert. denied, 532 U.S. 995 (2001). Although
we are satisfied that the cause of PR’s inability to perform was financial incapacity, PR has
failed to prove by preponderant evidence that the Corps was the cause of that incapacity.
PR’s four arguments rest on the premise that the Corps interfered with the manner
in which it planned to do the work. According to PR, it planned to enter the site at the upper
haul access road and exit on the light access road at the marina or at the lower haul access
road so that its trucks could avoid “cumbersome turn arounds.” The most reliable evidence
of how PR planned to perform the work is the access plan it submitted to the Corps for
approval on 18 September 1997. The plan indicated that PR intended to use “the indicated
[haul] access road in the attached sketches and then on top of the levee, backing up, dumping
and driving back to the same [haul] road,” meaning that PR planned to enter and exit using
the same haul access road. The plan did not indicate that PR planned to use the upper haul
access road or that it planned to have its empty trucks exit at the light access road at the
marina. Thus, PR’s access plan does not support the position it has taken in this appeal.
PR first argues that the Corps changed the contract by directing it to cease using the
light access road at the marina. According to PR, once its trucks were empty they were
light loads and should, therefore, have been allowed to use the light access road at the
marina. PR misconstrues the issue. The issue is not whether the empty trucks were light
loads, but whether LA Hwy. 23 was protected from “mud tracking, spillage and/or other
surface pollution” as required by Louisiana law. The contract required that roads used for
haul operations have stone pads built where they enter LA Hwy. 23. Since the contract did
not require a stone pad on the light access road at the marina, we conclude that the light
access road at the marina was not to be used as an exit for haul trucks.
PR next argues that the Corps changed the contract by directing PR to cease
“crossing the marina.” There is no evidence that the Corps ever issued such a directive and
12
we are convinced that PR never planned to cross the marina. PR’s access plan states that it
planned to exit back to the “same [haul] road.” In order for PR’s alleged plan to work,
both haul access roads had to be usable. However, the upper haul access road was not
usable until at least April 1998. Finally, given the physical limits of the levee and the
prohibition against running trucks on the protected side of the levee, there were only two
ways to perform the work: PR could have built the levee cap, left the berm open and
finished the berm at a later time, or it could have built the levee and the berm to full width
from the outset. Either method would have shut off access to the upper haul access road for
a majority of the contract. Thus, we cannot find that PR planned to cross the marina.
PR thirdly argues that the Corps improperly directed it to cease turning around in the
vicinity of Judge Martin’s property. PR did not present any evidence showing that its
trucks could have turned around in that area without incursion into Judge Martin’s property.
In the absence of any evidence showing that PR could have used that area to turn around, the
Corps acted properly in directing PR to turn around in another area.
PR lastly argues that the Corps changed the contract by directing it to build
turn-arounds. On this record we are unable to find that the Corps directed PR to build turn
arounds. Even if the Corps did direct PR to build turn-arounds, the construction of
turn-arounds is a common practice in this type of work and was necessary to perform the
work. DFARS 252.236-7001 - 1991 DEC, Contract Drawings, Maps and Specifications,
which was included in this contract, provided that “details of work which are manifestly
necessary to carry out the intent of the drawings and specifications, or which are
customarily performed, shall not relieve the Contractor from performing such omitted . . .
details of the work. . . .” Accordingly, we conclude that the Corps did not change the
contract by directing PR to build turn-arounds. Elter, S.A., ASBCA Nos. 52791 et al., 02-1
BCA ¶ 31,672 at 156,512.
The appeal is denied.
Dated: 30 July 2002
ELIZABETH A. TUNKS
Administrative Judge
Armed Services Board
of Contract Appeals
13
I concur
EDWARD G. KETCHEN
Administrative Judge
Armed Services Board
of Contract Appeals
(Signatures continued)
I concur I concur
MARK N. STEMPLER
Administrative Judge
Acting Chairman
Armed Services Board
of Contract Appeals
EUNICE W. THOMAS
Administrative Judge
Vice Chairman
Armed Services Board
of Contract Appeals
I certify that the foregoing is a true copy of the Opinion and Decision of the Armed
Services Board of Contract Appeals in ASBCA No. 52937, Appeal of P.R. Contractors, Inc.,
rendered in conformance with the Board's Charter.
Dated:
EDWARD S. ADAMKEWICZ
Recorder, Armed Services
Board of Contract Appeals
14