DOT US Department of Transportation
PHMSA Pipeline and Hazardous Materials Safety Administration
OPS Office of Pipeline Safety
Southwest Region
Principal Investigator Gene Roberson
Region Director R. M. Seeley
Date of Report
7/ 11/2011
Subject Failure Investigation Report Mid-Valley Pipeline Internal Corrosion
Operator, Location, & Consequences
Date of Failure 3/1/2010
Commodity Released
Crude Oil
City/County & State Longview/Gregg County, TX
OpID & Operator Name
12470 Mid-Valley Pipeline Company
Unit # & Unit Name 9754 Haynesville Area
SMART Activity # 129379
Milepost / Location Mid-Valley Tank Farm, Longview, TX
Type of Failure Internal corrosion in manifold area of tank farm
Fatalities
0
Injuries 0
Description of area
impacted
Operators facility only. In HCA for surface water, but no water affected.
Property Damage $16,018
Failure Investigation Report Mid-Valley Pipeline Internal Corrosion
3/1/2010
Page 2 of 5
Executive Summary
On March 1, 2010 Sunoco Pipeline Company made a notification to the National Response Center
reporting a crude oil release on their Mid-Valley Pipeline (Mid-Valley) system. Upon review of the
information an investigator from the Southwest Region was dispatched to the accident site.
At approximately 8:10 am CST, March 1, 2010, Mid-Valley identified a release of crude oil in the
manifold area of the Mid-Valley tank farm in Longview, TX. The header consisted of 8.625diameter,
0.350wall, Grade A (24,000 SMYS) pipe. The Mid-Valley facility is manned during normal business
hours and all line ups for deliveries are performed manually. Only emergency valves have automatic
actuation. Mid-Valley employees had lined up the manifold for the days deliveries and product was
being received into the station. At approximately 8:10 am, crude oil was observed gushingfrom the
soil in the manifold area. Mid-Valley responded by calling Lion Oil to shut down their pump, stopping
the delivery. The flow was stopped at approximately 8:18 am. Observations in the manifold area
indicated that a buried section of the manifold piping that delivered crude oil to tanks # 13 and #14 was
releasing product due to an unknown reason. The section of manifold piping had an MOP of 275 psig,
and was operating at less than 150 psig when the release occurred.
One hundred ninety eight (198) barrels of crude oil were estimated to have been released and 196
barrels were recovered from the secondary containment area with-in Mid-Valley’s site. Mid-Valley
isolated the underground section of the manifold piping and installed blind flanges to isolate it from the
above ground header. Once the spill was controlled, approximately 25 feet of 8” buried header was
then excavated for evaluation and/or removal. Upon excavation, it was determined that the release
originated from two localized spots of internal corrosion in the header. Mid-Valley has determined that
crude oil feed to tanks #13 and #14 is not essential to their operations and has chosen to not replace
this section of the header. It was established that the section of piping that failed was subject to
pressure as a dead leg with no flow during normal operations.
Failure Investigation Report Mid-Valley Pipeline Internal Corrosion
3/1/2010
Page 3 of 5
System Details
Mid-Valley provides Midwest refiners with access to various crude streams available at Longview, Texas,
including West Texas intermediate (WTI) and West Texas sour via West Texas Gulf Pipe Line Company
and foreign and Gulf of Mexico crude sourced from Beaumont/Nederland, Texas. Mid-Valley includes
approximately 1,100 miles of pipe (mostly 20” and 22”).
Mid-Valley is 55.3% owned and operated by Sunoco Logistics Partners, L. P., which is a master limited
partnership formed to acquire, own and operate refined product and crude oil pipelines and terminal
facilities, including those of Sunoco, Inc. Sunoco Logistics, through Sunoco Pipeline and another
subsidiary, Sunoco Partners Marketing & Terminals L.P., transport, terminal, and store refined products
and crude oil in 12 states.
The unit consists of approximately 228 miles of 20” mainline, a 44 mile 12” lateral, and a 20 mile 8”
lateral, eight mainline pump stations, two lateral pump stations and two breakout tank facilities
(Longview and Haynesville).
The Longview breakout tank facility consists
of 14 tanks and the manifold system where
the accident occurred. Mid-Valley identified
this facility as an HCA-could-affect area due
to the proximity near the Sabine River. Mid-
Valley had constructed secondary on-site
containment as preventative and mitigative
measure to lessen the impact of any releases
in the facility. This containment prevented
the spill from leaving the Longview Tank
facility and thus mitigating its impact to the
associated HCA. (See Appendix C)
Events Leading up to the Failure
The Longview Tank Facility has a common header that interconnects the 14 breakout tanks. The station
is aligned manually to deliver product into the appropriate tank. This morning Mid-Valley employees
had manually lined up the manifold valves to receive a shipment of crude oil from Lion Oil into the #7
tank. Upon start up at approximately 8:10 am, crude oil was observed gushing from the soil in the
manifold area. Mid-Valley responded by calling Lion Oil to shut down their pump, stopping the delivery
to Mid-Valley. The flow was stopped at approximately 8:18 am. The release had occurred from one of
several buried lines within the manifold area.
Sunoco reported the release to the NRC at approximately 11:41 CDT on March 1, 2010. (See Appendix
A)
Emergency Response
Mid-Valley’s technician activated the Emergency Response Plan for the local site. All flows into and out
of the site were shut down. The rupture resulted in the release of 198 barrels of crude oil, which was
contained in secondary containment on Mid-Valley’s site. No explosion or fire occurred. Emergency
contractors were on site recovering released crude oil within 45 minutes of the release.
Failure Investigation Report Mid-Valley Pipeline Internal Corrosion
3/1/2010
Page 4 of 5
Summary of Return-to-service
Following the emergency response, Mid Valley isolated the failed section of manifold pipe from the
system. Upon isolation with blind flanges, the manifold was pressured up, monitored and visually
inspected for system integrity. The manifold was returned to service the evening of March 1, 2010
when Mid-Valley was confident that all systems were safe.
Investigation Details
At approximately 8:10 am CST, March 1, 2010, Mid-Valley Pipeline Co. (Mid-Valley) reported to the
National Response Center a release of crude oil in the manifold area of the Mid-Valley tank farm in
Longview, TX. PHMSA’s Southwest Region received the incident notification and dispatched an
investigator to the site. The investigator arrived on site at 3 pm that afternoon. Vacuum trucks had
picked up most of the released product by the time an inspector arrived on site. It was observed that no
crude oil had been released beyond Mid-Valley’s facility site. Clean up was continuing for a very small
amount of crude that remained in the secondary containment area. The operator’s written report can
be seen in Appendix B.
The MOP of the manifold is 275 psig and the incident occurred at less than 150 psig. The leak was
observed at approximately 8:10 am and the station was shut down by 8:18 am. The investigation
showed that the incident was initially discovered by the technician on site who observed the release and
acted promptly to shut in and secure the manifold.
Through the investigation we learned that there is a common header at this facility and depending on
the product movement some sections would see product movement and some sections would not. The
entire header does see a common pressure. The investigation was unable to determine why this section
leaked when it did. This specific section was not flowing product and it has not for a long time. The
pressures were consistent with other times and no other operational anomalies were identified.
The operator removed approximately 25 feet of 8 5/8 inch pipe that contained the failure section to
evaluate the cause. According to the operator, this section of line will not be replaced.
The PHMSA Investigator was able to view the release site on the pipe, but close examination was limited
due to its location. Further review was to be done after removal was complete. Cause appeared to be
from internal corrosion. Photos of the failed section can be seen in Appendix D.
Mid-Valley will monitor the manifold system for conditions conducive to internal corrosion with the
installation of internal coupons. To address conditions of Mid-Valley’s IMP program, coupon holders
had been installed prior to the release for monitoring internal corrosion and local procedures for
operation and monitoring were being developed. This coupon monitoring system has since been placed
in-service. Additionally, Mid-Valley has completed a facility piping review to identify other potential no
flow/low flow areas in the manifold that pose a risk of internal corrosion and developed corrective
action plans where appropriate.
The section of pipe was not sent to a lab for analysis. Direct observation determined the failure was due
to two localized spots of internal corrosion in the buried header. The failed section was a dead leg of
pipe that was subject to pressure fluctuations with no flow during normal operations.
Metallurgical Analysis
Failure Investigation Report Mid-Valley Pipeline Internal Corrosion
3/1/2010
Page 5 of 5
Findings and Contributing Factors
The leak occurred at approximately 8:10 on March 1, 2010. The discovery and isolation was prompt and
operator’s actions were appropriate.
While the leak occurred at a facility that could impact an HCA no product reached the HCA.
The failure initiated from 2 isolated incidences of internal spot corrosion, at the 6:00 o’clock position in
the header. No other indications of internal corrosion were found in the header after it was removed
and investigated.
Appendices
A Telephonic Notice Report NRC #932647
B Written Accident Report 20100014
C Operator and System Maps
D Failure Site Photos
Appendix A Telephonic Notice Report NRC#932647
-----Original Message-----
From: HQS-PF-fldr-[email protected] [mailto:HQS-PF-fldr-[email protected]]
Sent: Monday, March 01, 2010 10:49 AM
To: PHP Accident/Incident Cadre <PHMSA>; CMC-01 (OST)
Subject: NRC#932647
NATIONAL RESPONSE CENTER 1-800-424-8802
***GOVERNMENT USE ONLY***GOVERNMENT USE ONLY***
Information released to a third party shall comply with any
applicable federal and/or state Freedom of Information and Privacy Laws
Incident Report # 932647
INCIDENT DESCRIPTION
*Report taken by: CIV NYDIA RAWLS at 11:41 on 01-MAR-10
Incident Type: FIXED
Incident Cause: UNKNOWN
Affected Area:
Incident occurred on 01-MAR-10 at 08:15 local incident time.
Affected Medium: LAND GROUND
_______________________________________________________________________
REPORTING PARTY
Name: DAVID BORN
Organization: SUNOCO PIPELINE CO.
Address: ONE FLOUR DANIEL DRIVE
BLDG A, LEVEL 3
SUGARLAND, TX 77478
SUNOCO PIPELINE CO. reported for the responsible party.
PRIMARY Phone: (281)6376497
Type of Organization: PRIVATE ENTERPRISE
_______________________________________________________________________
SUSPECTED RESPONSIBLE PARTY
Name: DAVID BORN
Organization: MID-VALLEY PIPELINC CO.
Address: 1010 COX DAIRY ROAD
LONGVIEW, TX 75604
PRIMARY Phone: (281)6376497 CELLULAR Phone: (713)7022091
________________________________________________________________________
INCIDENT LOCATION
1010 COX DAIRY ROAD County: GREGG
City: LONGVIEW State: TX Zip: 75604
PUMP STATION
_______________________________________________________________________
RELEASED MATERIAL(S)
CHRIS Code: OIL Official Material Name: OIL: CRUDE
Also Known As:
Qty Released: 190 BARREL(S)
________________________________________________________________________
DESCRIPTION OF INCIDENT
CALLER IS REPORTING A RELEASE OF CRUDE OIL FROM AN ON SHORE PIPELINE
DUE TO UNKNOWN CAUSES. MATERIAL RELEASED ONTO LAND AT THE LONGVIEW
STATION.
________________________________________________________________________
SENSITIVE INFORMATION
________________________________________________________________________
INCIDENT DETAILS
Package: N/A
Building ID:
Type of Fixed Object: OTHER
Power Generating Facility: NO
Generating Capacity:
Type of Fuel:
NPDES:
NPDES Compliance: UNKNOWN
______________________________________________________________________
IMPACT
Fire Involved: NO Fire Extinguished: UNKNOWN
INJURIES: NO Hospitalized: Empl/Crew: Passenger:
FATALITIES: NO Empl/Crew: Passenger: Occupant:
EVACUATIONS:NO Who Evacuated: Radius/Area:
Damages: NO
Hours Direction of
Closure Type Description of Closure Closed Closure
N
Air:
N Major
Road: Artery:N
N
Waterway:
N
Track:
Environmental Impact: UNKNOWN
Media Interest: NONE Community Impact due to Material:
______________________________________________________________________
REMEDIAL ACTIONS
PIPELINE WAS SHUT DOWN, RELEASE WAS CONTAINED TO THE PROPERTY AND
THE RETENTION DEPRESSION (POND AREA).
Release Secured: YES
Release Rate:
Estimated Release Duration:
______________________________________________________________________
WEATHER
Weather: PARTLY CLOUDY, 58ºF Wind speed: 5 MPH Wind directi
______________________________________________________________________
ADDITIONAL AGENCIES NOTIFIED
Federal: NONE
State/Local: NONE
State/Local On Scene: NONE
State Agency Number: NONE
_______________________________________________________________________
NOTIFICATIONS BY NRC
DHS PROTECTIVE SECURITY ADVISOR (PSA DESK)
01-MAR-10 11:49 (703)2355724
DOT CRISIS MANAGEMENT CENTER (MAIN OFFICE)
01-MAR-10 11:49 (202)3661863
U.S. EPA VI (MAIN OFFICE)
(866)3727745
GULF STRIKE TEAM (MAIN OFFICE)
01-MAR-10 11:49 (251)4416601
JFO-LA (COMMAND CENTER)
01-MAR-10 11:49 (225)3366513
NATIONAL INFRASTRUCTURE COORD CTR (MAIN OFFICE)
01-MAR-10 11:49 (202)2829201
NOAA RPTS FOR TX (MAIN OFFICE)
01-MAR-10 11:49 (206)5264911
PIPELINE & HAZMAT SAFETY ADMIN (OFFICE OF PIPELINE SAFETY (AUTO))
01-MAR-10 11:49 (202)3660568
TCEQ (MAIN OFFICE)
01-MAR-10 11:49 (512)2392507
TEXAS STATE OPERATIONS CENTER (COMMAND CENTER)
01-MAR-10 11:49 (512)4242208
_______________________________________________________________________
ADDITIONAL INFORMATION
CALLER WILL NOTIFY THE TX RAILROAD COMMISSION (TRRC) AND THE OIL
AND GAS DIVISION NEXT.
______________________________________________________________________
*** END INCIDENT REPORT #932647 ***
Report any problems by calling 1-800-424-8802
PLEASE VISIT OUR WEB SITE AT
http://www.nrc.uscg.mil
Appendix B Written Accident Report 20100014
Page 1 of 13
NOTICE: This report is required by 49 CFR Part 195. Failure to report can result in a civil penalty not to
exceed $100,000 for each violation for each day that such violation persists except that the maximum civil
penalty shall not exceed $1,000,000 as provided in 49 USC 60122.
OMB NO: 2137-0047
EXPIRATION DATE: 01/31/2013
U.S Department of Transportation
Pipeline and Hazardous Materials Safety Administration
Report Date:
No.
20100014 - 15090
--------------------------
(DOT Use Only)
ACCIDENT REPORT - HAZARDOUS LIQUID
PIPELINE SYSTEMS
A federal agency may not conduct or sponsor, and a person is not required to respond to, nor shall a person be subject to a penalty for failure to comply
with a collection of information subject to the requirements of the Paperwork Reduction Act unless that collection of information displays a current valid
OMB Control Number. The OMB Control Number for this information collection is 2137-0047. Public reporting for this collection of information is estimated
to be approximately 10 hours per response (5 hours for a small release), including the time for reviewing instructions, gathering the data needed, and
completing and reviewing the collection of information. All responses to this collection of information are mandatory. Send comments regarding this
burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden to: Information Collection Clearance
Officer, PHMSA, Office of Pipeline Safety (PHP-30) 1200 New Jersey Avenue, SE, Washington, D.C. 20590.
INSTRUCTIONS
Important: Please read the separate instructions for completing this form before you begin. They clarify the information requested and provide specific
examples. If you do not have a copy of the instructions, you can obtain one from the PHMSA Pipeline Safety Community Web Page at
http://www.phmsa.dot.gov/pipeline.
PART A - KEY REPORT INFORMATION
Report Type: (select all that apply)
Original: Supplemental: Final:
Yes Yes
Report Status: Submitted
Create Date: 05/12/2010
1. Operator's OPS-issued Operator Identification Number (OPID): 12470
2. Name of Operator MID - VALLEY PIPELINE CO
3. Address of Operator:
3a. Street Address 525 FRITZTOWN ROAD
3b. City SINKING SPRING
3c. State Pennslyvania
3d. Zip Code 19608
4. Local time (24-hr clock) and date of the Accident: 03/01/2010 08:10
5. Location of Accident:
Latitude: 32.48325
Longitude: -94.83034
6. National Response Center Report Number (if applicable): 932647
7. Local time (24-hr clock) and date of initial telephonic report to the
National Response Center (if applicable):
03/01/2010 11:41
8. Commodity released: (select only one, based on predominant
volume released)
Crude Oil
- Specify Commodity Subtype:
- If "Other" Subtype, Describe:
- If Biofuel/Alternative Fuel and Commodity Subtype is
Ethanol Blend, then % Ethanol Blend:
%:
- If Biofuel/Alternative Fuel and Commodity Subtype is
Biodiesel, then Biodiesel Blend (e.g. B2, B20, B100):
B
9. Estimated volume of commodity released unintentionally (Barrels): 198.00
10. Estimated volume of intentional and/or controlled release/blowdown
(Barrels):
11. Estimated volume of commodity recovered (Barrels): 196.00
12. Were there fatalities? No
- If Yes, specify the number in each category:
12a. Operator employees
12b. Contractor employees working for the Operator
12c. Non-Operator emergency responders
12d. Workers working on the right-of-way, but NOT
associated with this Operator
12e. General public
12f. Total fatalities (sum of above)
13. Were there injuries requiring inpatient hospitalization? No
- If Yes, specify the number in each category:
13a. Operator employees
13b. Contractor employees working for the Operator
13c. Non-Operator emergency responders
Page 2 of 13
13d. Workers working on the right-of-way, but NOT
associated with this Operator
13e. General public
13f. Total injuries (sum of above)
14. Was the pipeline/facility shut down due to the Accident? Yes
- If No, Explain:
- If Yes, complete Questions 14a and 14b: (use local time, 24-hr clock)
14a. Local time and date of shutdown: 03/01/2010 08:12
14b. Local time pipeline/facility restarted: 03/01/2010 14:00
- Still shut down? (* Supplemental Report Required)
15. Did the commodity ignite? No
16. Did the commodity explode? No
17. Number of general public evacuated: 0
18. Time sequence (use local time, 24-hour clock):
18a. Local time Operator identified Accident: 03/01/2010 08:10
18b. Local time Operator resources arrived on site: 03/01/2010 08:10
PART B - ADDITIONAL LOCATION INFORMATION
1. Was the origin of Accident onshore? Yes
If Yes, Complete Questions (2-12)
If No, Complete Questions (13-15)
- If Onshore:
2. State: Texas
3. Zip Code: 75604
4. City Longview
5. County or Parish Gregg
6. Operator-designated location: Milepost/Valve Station
Specify: MP 0
7. Pipeline/Facility name: Longview Station
8. Segment name/ID: Lion Oil Manifold Header
9. Was Accident on Federal land, other than the Outer Continental Shelf
(OCS)?
No
10. Location of Accident: Totally contained on Operator-controlled property
11. Area of Accident (as found): Underground
Specify: Under soil
- If Other, Describe:
Depth-of-Cover (in): 18
12. Did Accident occur in a crossing? No
- If Yes, specify below:
- If Bridge crossing
Cased/ Uncased:
- If Railroad crossing
Cased/ Uncased/ Bored/drilled
- If Road crossing
Cased/ Uncased/ Bored/drilled
- If Water crossing
Cased/ Uncased
- Name of body of water, if commonly known:
- Approx. water depth (ft) at the point of the Accident:
- Select:
- If Offshore:
13. Approximate water depth (ft) at the point of the Accident:
14. Origin of Accident:
- In State waters - Specify:
- State:
- Area:
- Block/Tract #:
- Nearest County/Parish:
- On the Outer Continental Shelf (OCS) - Specify:
- Area:
- Block #:
15. Area of Accident:
PART C - ADDITIONAL FACILITY INFORMATION
1. Is the pipeline or facility: Interstate
2. Part of system involved in Accident: Onshore Pump/Meter Station Equipment and Piping
- If Onshore Breakout Tank or Storage Vessel, Including Attached
Appurtenances, specify:
3. Item involved in Accident: Pipe
Page 3 of 13
- If Pipe, specify: Pipe Body
3a. Nominal diameter of pipe (in): 8.625
3b. Wall thickness (in): .35
3c. SMYS (Specified Minimum Yield Strength) of pipe (psi): 25,000
3d. Pipe specification: Grade A
3e. Pipe Seam , specify: Longitudinal ERW - Unknown Frequency
- If Other, Describe:
3f. Pipe manufacturer: Unknown
3g. Year of manufacture: 1976
3h. Pipeline coating type at point of Accident, specify: Coal Tar
- If Other, Describe:
- If Weld, including heat-affected zone, specify:
- If Other, Describe:
- If Valve, specify:
- If Mainline, specify:
- If Other, Describe:
3i. Manufactured by:
3j. Year of manufacture:
- If Tank/Vessel, specify:
- If Other - Describe:
- If Other, describe:
4. Year item involved in Accident was installed: 1976
5. Material involved in Accident: Carbon Steel
- If Material other than Carbon Steel, specify:
6. Type of Accident Involved: Rupture
- If Mechanical Puncture Specify Approx. size:
in. (axial) by
in. (circumferential)
- If Leak - Select Type:
- If Other, Describe:
- If Rupture - Select Orientation: Circumferential
- If Other, Describe:
Approx. size: in. (widest opening) by 2
in. (length circumferentially or axially) 2
- If Other Describe:
PART D - ADDITIONAL CONSEQUENCE INFORMATION
1. Wildlife impact: No
1a. If Yes, specify all that apply:
- Fish/aquatic
- Birds
- Terrestrial
2. Soil contamination: Yes
3. Long term impact assessment performed or planned: No
4. Anticipated remediation: Yes
4a. If Yes, specify all that apply:
- Surface water
- Groundwater
- Soil Yes
- Vegetation
- Wildlife
5. Water contamination: No
5a. If Yes, specify all that apply:
- Ocean/Seawater
- Surface
- Groundwater
- Drinking water: (Select one or both)
- Private Well
- Public Water Intake
5b. Estimated amount released in or reaching water (Barrels):
5c. Name of body of water, if commonly known:
6. At the location of this Accident, had the pipeline segment or facility
been identified as one that "could affect" a High Consequence Area
(HCA) as determined in the Operator's Integrity Management Program?
Yes
7. Did the released commodity reach or occur in one or more High
Consequence Area (HCA)?
Yes
7a. If Yes, specify HCA type(s): (Select all that apply)
- Commercially Navigable Waterway:
Was this HCA identified in the "could affect"
Page 4 of 13
determination for this Accident site in the Operator's
Integrity Management Program?
- High Population Area:
Was this HCA identified in the "could affect"
determination for this Accident site in the Operator's
Integrity Management Program?
- Other Populated Area
Was this HCA identified in the "could affect"
determination for this Accident site in the Operator's
Integrity Management Program?
- Unusually Sensitive Area (USA) - Drinking Water Yes
Was this HCA identified in the "could affect"
determination for this Accident site in the Operator's
Integrity Management Program?
Yes
- Unusually Sensitive Area (USA) - Ecological
Was this HCA identified in the "could affect"
determination for this Accident site in the Operator's
Integrity Management Program?
8. Estimated cost to Operator :
8a. Estimated cost of public and non-Operator private
property damage paid/reimbursed by the Operator
$
8b. Estimated cost of commodity lost $ 150
8c. Estimated cost of Operator's property damage & repairs $ 1,134
8d. Estimated cost of Operator's emergency response $ 11,470
8e. Estimated cost of Operator's environmental remediation $ 3,264
8f. Estimated other costs $
Describe:
8g. Estimated total costs (sum of above) $ 16,018
PART E - ADDITIONAL OPERATING INFORMATION
1. Estimated pressure at the point and time of the Accident (psig): 140.00
2. Maximum Operating Pressure (MOP) at the point and time of the
Accident (psig):
150.00
3. Describe the pressure on the system or facility relating to the
Accident (psig):
Pressure did not exceed MOP
4. Not including pressure reductions required by PHMSA regulations
(such as for repairs and pipe movement), was the system or facility
relating to the Accident operating under an established pressure
restriction with pressure limits below those normally allowed by the
MOP?
No
- If Yes, Complete 4.a and 4.b below:
4a. Did the pressure exceed this established pressure
restriction?
4b. Was this pressure restriction mandated by PHMSA or the
State?
5. Was "Onshore Pipeline, Including Valve Sites" OR "Offshore
Pipeline, Including Riser and Riser Bend" selected in PART C, Question
2?
No
- If Yes - (Complete 5a. 5f. below)
5a. Type of upstream valve used to initially isolate release
source:
5b. Type of downstream valve used to initially isolate release
source:
5c. Length of segment isolated between valves (ft):
5d. Is the pipeline configured to accommodate internal
inspection tools?
- If No, Which physical features limit tool accommodation? (select all that apply)
- Changes in line pipe diameter
- Presence of unsuitable mainline valves
- Tight or mitered pipe bends
- Other passage restrictions (i.e. unbarred tee's,
projecting instrumentation, etc.)
- Extra thick pipe wall (applicable only for magnetic
flux leakage internal inspection tools)
- Other -
- If Other, Describe:
5e. For this pipeline, are there operational factors which
significantly complicate the execution of an internal inspection tool
run?
- If Yes, Which operational factors complicate execution? (select all that apply)
- Excessive debris or scale, wax, or other wall buildup
Page 5 of 13
- Low operating pressure(s)
- Low flow or absence of flow
- Incompatible commodity
- Other -
- If Other, Describe:
5f. Function of pipeline system:
6. Was a Supervisory Control and Data Acquisition (SCADA)-based
system in place on the pipeline or facility involved in the Accident?
Yes
If Yes -
6a. Was it operating at the time of the Accident? Yes
6b. Was it fully functional at the time of the Accident? Yes
6c. Did SCADA-based information (such as alarm(s),
alert(s), event(s), and/or volume calculations) assist with
the detection of the Accident?
No
6d. Did SCADA-based information (such as alarm(s),
alert(s), event(s), and/or volume calculations) assist with
the confirmation of the Accident?
No
7. Was a CPM leak detection system in place on the pipeline or facility
involved in the Accident?
No
- If Yes:
7a. Was it operating at the time of the Accident?
7b. Was it fully functional at the time of the Accident?
7c. Did CPM leak detection system information (such as
alarm(s), alert(s), event(s), and/or volume calculations) assist
with the detection of the Accident?
7d. Did CPM leak detection system information (such as
alarm(s), alert(s), event(s), and/or volume calculations) assist
with the confirmation of the Accident?
8. How was the Accident initially identified for the Operator? Local Operating Personnel, including contractors
- If Other, Specify:
8a. If "Controller", "Local Operating Personnel", including
contractors", "Air Patrol", or "Guard Patrol by Operator or its
contractor" is selected in Question 8, specify the following:
Operator employee
9. Was an investigation initiated into whether or not the controller(s) or
control room issues were the cause of or a contributing factor to the
Accident?
Yes, specify investigation result(s): (select all that apply)
- If No, the Operator did not find that an investigation of the
controller(s) actions or control room issues was necessary due to:
(provide an explanation for why the operator did not investigate)
- If Yes, specify investigation result(s): (select all that apply)
- Investigation reviewed work schedule rotations,
continuous hours of service (while working for the
Operator), and other factors associated with fatigue
Yes
- Investigation did NOT review work schedule rotations,
continuous hours of service (while working for the
Operator), and other factors associated with fatigue
Provide an explanation for why not:
- Investigation identified no control room issues Yes
- Investigation identified no controller issues Yes
- Investigation identified incorrect controller action or
controller error
- Investigation identified that fatigue may have affected the
controller(s) involved or impacted the involved controller(s)
response
- Investigation identified incorrect procedures
- Investigation identified incorrect control room equipment
operation
- Investigation identified maintenance activities that affected
control room operations, procedures, and/or controller
response
- Investigation identified areas other than those above:
Describe:
PART F - DRUG & ALCOHOL TESTING INFORMATION
Page 6 of 13
1. As a result of this Accident, were any Operator employees tested
under the post-accident drug and alcohol testing requirements of DOT's
Drug & Alcohol Testing regulations?
Yes
- If Yes:
1a. Specify how many were tested: 1
1b. Specify how many failed: 0
2. As a result of this Accident, were any Operator contractor employees
tested under the post-accident drug and alcohol testing requirements of
DOT's Drug & Alcohol Testing regulations?
No
- If Yes:
2a. Specify how many were tested:
2b. Specify how many failed:
PART G APPARENT CAUSE
Select only one box from PART G in shaded column on left representing the APPARENT Cause of the Accident, and answer
the questions on the right. Describe secondary, contributing or root causes of the Accident in the narrative (PART H).
Apparent Cause:
G1 - Corrosion Failure
G1 - Corrosion Failure - only one sub-cause can be picked from shaded left-hand column
Corrosion Failure Sub Cause:
- If External Corrosion:
1. Results of visual examination:
- If Other, Describe:
2. Type of corrosion: (select all that apply)
- Galvanic
- Atmospheric
- Stray Current
- Microbiological
- Selective Seam
- Other:
- If Other, Describe:
3. The type(s) of corrosion selected in Question 2 is based on the following: (select all that apply)
- Field examination
- Determined by metallurgical analysis
- Other:
- If Other, Describe:
4. Was the failed item buried under the ground?
- If Yes :
4a. Was failed item considered to be under cathodic
protection at the time of the Accident?
If Yes - Year protection started:
4b. Was shielding, tenting, or disbonding of coating evident at
the point of the Accident?
4c. Has one or more Cathodic Protection Survey been
conducted at the point of the Accident?
If "Yes, CP Annual Survey" Most recent year conducted:
If "Yes, Close Interval Survey" Most recent year conducted:
If "Yes, Other CP Survey" Most recent year conducted:
- If No:
4d. Was the failed item externally coated or painted?
5. Was there observable damage to the coating or paint in the vicinity of
the corrosion?
- If Internal Corrosion:
6. Results of visual examination: Localized Pitting
- Other:
7. Type of corrosion (select all that apply): -
- Corrosive Commodity
- Water drop-out/Acid
- Microbiological Yes
- Erosion
- Other:
- If Other, Describe:
8. The cause(s) of corrosion selected in Question 7 is based on the following (select all that apply): -
- Field examination Yes
- Determined by metallurgical analysis
- Other:
Page 7 of 13
- If Other, Describe:
9. Location of corrosion (select all that apply): -
- Low point in pipe Yes
- Elbow
- Other:
- If Other, Describe:
10. Was the commodity treated with corrosion inhibitors or biocides? Yes
11. Was the interior coated or lined with protective coating? No
12. Were cleaning/dewatering pigs (or other operations) routinely
utilized?
Not applicable - Not mainline pipe
13. Were corrosion coupons routinely utilized? Not applicable - Not mainline pipe
Complete the following if any Corrosion Failure sub-cause is selected AND the "Item Involved in Accident" (from PART C,
Question 3) is Tank/Vessel.
14. List the year of the most recent inspections:
14a. API Std 653 Out-of-Service Inspection
- No Out-of-Service Inspection completed
14b. API Std 653 In-Service Inspection
- No In-Service Inspection completed
Complete the following if any Corrosion Failure sub-cause is selected AND the "Item Involved in Accident" (from PART C,
Question 3) is Pipe or Weld.
15. Has one or more internal inspection tool collected data at the point of the
Accident?
No
15a. If Yes, for each tool used, select type of internal inspection tool and indicate most recent year run: -
- Magnetic Flux Leakage Tool
Most recent year:
- Ultrasonic
Most recent year:
- Geometry
Most recent year:
- Caliper
Most recent year:
- Crack
Most recent year:
- Hard Spot
Most recent year:
- Combination Tool
Most recent year:
- Transverse Field/Triaxial
Most recent year:
- Other
Most recent year:
Describe:
16. Has one or more hydrotest or other pressure test been conducted since
original construction at the point of the Accident?
No
If Yes -
Most recent year tested:
Test pressure:
17. Has one or more Direct Assessment been conducted on this segment? No
- If Yes, and an investigative dig was conducted at the point of the Accident::
Most recent year conducted:
- If Yes, but the point of the Accident was not identified as a dig site:
Most recent year conducted:
18. Has one or more non-destructive examination been conducted at the
point of the Accident since January 1, 2002?
No
18a. If Yes, for each examination conducted since January 1, 2002, select type of non-destructive examination and indicate most
recent year the examination was conducted:
- Radiography
Most recent year conducted:
- Guided Wave Ultrasonic
Most recent year conducted:
- Handheld Ultrasonic Tool
Most recent year conducted:
- Wet Magnetic Particle Test
Most recent year conducted:
- Dry Magnetic Particle Test
Most recent year conducted:
- Other
Most recent year conducted:
Describe:
G2 - Natural Force Damage
- only one sub-cause can be picked from shaded left-handed column
Page 8 of 13
Natural Force Damage Sub-Cause:
- If Earth Movement, NOT due to Heavy Rains/Floods:
1. Specify:
- If Other, Describe:
- If Heavy Rains/Floods:
2. Specify:
- If Other, Describe:
- If Lightning:
3. Specify:
- If Temperature:
4. Specify:
- If Other, Describe:
- If Other Natural Force Damage:
5. Describe:
Complete the following if any Natural Force Damage sub-cause is selected.
6. Were the natural forces causing the Accident generated in
conjunction with an extreme weather event?
6a. If Yes, specify: (select all that apply)
- Hurricane
- Tropical Storm
- Tornado
- Other
- If Other, Describe:
G3 - Excavation Damage - only one sub-cause can be picked from shaded left-hand column
Excavation Damage Sub-Cause:
- If Previous Damage due to Excavation Activity:
Complete Questions 1-5 ONLY IF the "Item Involved in Accident" (from PART C, Question 3) is Pipe or Weld.
1. Has one or more internal inspection tool collected data at the point of
the Accident?
1a. If Yes, for each tool used, select type of internal inspection tool and indicate most recent year run: -
- Magnetic Flux Leakage
Most recent year conducted:
- Ultrasonic
Most recent year conducted:
- Geometry
Most recent year conducted:
- Caliper
Most recent year conducted:
- Crack
Most recent year conducted:
- Hard Spot
Most recent year conducted:
- Combination Tool
Most recent year conducted:
- Transverse Field/Triaxial
Most recent year conducted:
- Other
Most recent year conducted:
Describe:
2. Do you have reason to believe that the internal inspection was
completed BEFORE the damage was sustained?
3. Has one or more hydrotest or other pressure test been conducted
since original construction at the point of the Accident?
- If Yes:
Most recent year tested:
Test pressure (psig):
4. Has one or more Direct Assessment been conducted on the pipeline
segment?
- If Yes, and an investigative dig was conducted at the point of the Accident:
Most recent year conducted:
- If Yes, but the point of the Accident was not identified as a dig site:
Most recent year conducted:
5. Has one or more non-destructive examination been conducted at the
point of the Accident since January 1, 2002?
5a. If Yes, for each examination, conducted since January 1, 2002, select type of non-destructive examination and indicate most
recent year the examination was conducted:
Page 9 of 13
- Radiography
Most recent year conducted:
- Guided Wave Ultrasonic
Most recent year conducted:
- Handheld Ultrasonic Tool
Most recent year conducted:
- Wet Magnetic Particle Test
Most recent year conducted:
- Dry Magnetic Particle Test
Most recent year conducted:
- Other
Most recent year conducted:
Describe:
Complete the following if Excavation Damage by Third Party is selected as the sub-cause.
6. Did the operator get prior notification of the excavation activity?
6a. If Yes, Notification received from: (select all that apply) -
- One-Call System
- Excavator
- Contractor
- Landowner
Complete the following mandatory CGA-DIRT Program questions if any Excavation Damage sub-cause is selected.
7. Do you want PHMSA to upload the following information to CGA-
DIRT (www.cga-dirt.com)?
8. Right-of-Way where event occurred: (select all that apply) -
- Public
- If "Public", Specify:
- Private
- If "Private", Specify:
- Pipeline Property/Easement
- Power/Transmission Line
- Railroad
- Dedicated Public Utility Easement
- Federal Land
- Data not collected
- Unknown/Other
9. Type of excavator:
10. Type of excavation equipment:
11. Type of work performed:
12. Was the One-Call Center notified?
12a. If Yes, specify ticket number:
12b. If this is a State where more than a single One-Call Center
exists, list the name of the One-Call Center notified:
13. Type of Locator:
14. Were facility locate marks visible in the area of excavation?
15. Were facilities marked correctly?
16. Did the damage cause an interruption in service?
16a. If Yes, specify duration of the interruption (hours)
17. Description of the CGA-DIRT Root Cause (select only the one predominant first level CGA-DIRT Root Cause and then, where
available as a choice, the one predominant second level CGA-DIRT Root Cause as well):
Root Cause:
- If One-Call Notification Practices Not Sufficient, specify:
- If Locating Practices Not Sufficient, specify:
- If Excavation Practices Not Sufficient, specify:
- If Other/None of the Above, explain:
G4 - Other Outside Force Damage
- only one sub-cause can be selected from the shaded left-hand column
Other Outside Force Damage Sub-Cause:
- If Damage by Car, Truck, or Other Motorized Vehicle/Equipment NOT Engaged in Excavation:
1. Vehicle/Equipment operated by:
- If Damage by Boats, Barges, Drilling Rigs, or Other Maritime Equipment or Vessels Set Adrift or Which Have Otherwise Lost
Their Mooring:
2. Select one or more of the following IF an extreme weather event was a factor:
- Hurricane
- Tropical Storm
- Tornado
- Heavy Rains/Flood
- Other
Page 10 of 13
- If Other, Describe:
- If Previous Mechanical Damage NOT Related to Excavation:
Complete Questions 3-7 ONLY IF the "Item Involved in Accident" (from PART C, Question 3) is Pipe or Weld.
3. Has one or more internal inspection tool collected data at the point of
the Accident?
3a. If Yes, for each tool used, select type of internal inspection tool and indicate most recent year run:
- Magnetic Flux Leakage
Most recent year conducted:
- Ultrasonic
Most recent year conducted:
- Geometry
Most recent year conducted:
- Caliper
Most recent year conducted:
- Crack
Most recent year conducted:
- Hard Spot
Most recent year conducted:
- Combination Tool
Most recent year conducted:
- Transverse Field/Triaxial
Most recent year conducted:
- Other
Most recent year conducted:
Describe:
4. Do you have reason to believe that the internal inspection was
completed BEFORE the damage was sustained?
5. Has one or more hydrotest or other pressure test been conducted
since original construction at the point of the Accident?
- If Yes:
Most recent year tested:
Test pressure (psig):
6. Has one or more Direct Assessment been conducted on the pipeline
segment?
- If Yes, and an investigative dig was conducted at the point of the Accident:
Most recent year conducted:
- If Yes, but the point of the Accident was not identified as a dig site:
Most recent year conducted:
7. Has one or more non-destructive examination been conducted at the
point of the Accident since January 1, 2002?
7a. If Yes, for each examination conducted since January 1, 2002, select type of non-destructive examination and indicate most
recent year the examination was conducted:
- Radiography
Most recent year conducted:
- Guided Wave Ultrasonic
Most recent year conducted:
- Handheld Ultrasonic Tool
Most recent year conducted:
- Wet Magnetic Particle Test
Most recent year conducted:
- Dry Magnetic Particle Test
Most recent year conducted:
- Other
Most recent year conducted:
Describe:
- If Intentional Damage:
8. Specify:
- If Other, Describe:
- If Other Outside Force Damage:
9. Describe:
G5 - Material Failure of Pipe or Weld - only one sub-cause can be selected from the shaded left-hand column
Use this section to report material failures ONLY IF the "Item Involved in Accident" (from PART C, Question 3) is "Pipe" or
"Weld."
Material Failure of Pipe or Weld Sub-Cause:
1. The sub-cause selected below is based on the following: (select all that apply)
- Field Examination
Page 11 of 13
- Determined by Metallurgical Analysis
- Other Analysis
- If "Other Analysis", Describe:
- Sub-cause is Tentative or Suspected; Still Under Investigation
(Supplemental Report required)
- If Construction, Installation, or Fabrication-related:
2. List contributing factors: (select all that apply)
- Fatigue or Vibration-related
Specify:
- If Other, Describe:
- Mechanical Stress:
- Other
- If Other, Describe:
- If Original Manufacturing-related (NOT girth weld or other welds formed in the field):
2. List contributing factors: (select all that apply)
- Fatigue or Vibration-related:
Specify:
- If Other, Describe:
- Mechanical Stress:
- Other
- If Other, Describe:
- If Environmental Cracking-related:
3. Specify:
- Other - Describe:
Complete the following if any Material Failure of Pipe or Weld sub-cause is selected.
4. Additional factors: (select all that apply):
- Dent
- Gouge
- Pipe Bend
- Arc Burn
- Crack
- Lack of Fusion
- Lamination
- Buckle
- Wrinkle
- Misalignment
- Burnt Steel
- Other:
- If Other, Describe:
5. Has one or more internal inspection tool collected data at the point of
the Accident?
5a. If Yes, for each tool used, select type of internal inspection tool and indicate most recent year run:
- Magnetic Flux Leakage
Most recent year run:
- Ultrasonic
Most recent year run:
- Geometry
Most recent year run:
- Caliper
Most recent year run:
- Crack
Most recent year run:
- Hard Spot
Most recent year run:
- Combination Tool
Most recent year run:
- Transverse Field/Triaxial
Most recent year run:
- Other
Most recent year run:
Describe:
6. Has one or more hydrotest or other pressure test been conducted
since original construction at the point of the Accident?
- If Yes:
Most recent year tested:
Test pressure (psig):
7. Has one or more Direct Assessment been conducted on the pipeline
segment?
- If Yes, and an investigative dig was conducted at the point of the Accident -
Page 12 of 13
Most recent year conducted:
- If Yes, but the point of the Accident was not identified as a dig site -
Most recent year conducted:
8. Has one or more non-destructive examination(s) been conducted at
the point of the Accident since January 1, 2002?
8a. If Yes, for each examination conducted since January 1, 2002, select type of non-destructive examination and indicate most
recent year the examination was conducted: -
- Radiography
Most recent year conducted:
- Guided Wave Ultrasonic
Most recent year conducted:
- Handheld Ultrasonic Tool
Most recent year conducted:
- Wet Magnetic Particle Test
Most recent year conducted:
- Dry Magnetic Particle Test
Most recent year conducted:
- Other
Most recent year conducted:
Describe:
G6 Equipment Failure - only one sub-cause can be selected from the shaded left-hand column
Equipment Failure Sub-Cause:
- If Malfunction of Control/Relief Equipment:
1. Specify: (select all that apply) -
- Control Valve
- Instrumentation
- SCADA
- Communications
- Block Valve
- Check Valve
- Relief Valve
- Power Failure
- Stopple/Control Fitting
- ESD System Failure
- Other
- If Other Describe:
- If Pump or Pump-related Equipment:
2. Specify:
- If Other Describe:
- If Threaded Connection/Coupling Failure:
3. Specify:
- If Other Describe:
- If Non-threaded Connection Failure:
4. Specify:
- If Other Describe:
- Other Equipment Failure:
5. Describe:
Complete the following if any Equipment Failure sub-cause is selected.
6. Additional factors that contributed to the equipment failure: (select all that apply)
- Excessive vibration
- Overpressurization
- No support or loss of support
- Manufacturing defect
- Loss of electricity
- Improper installation
- Mismatched items (different manufacturer for tubing and tubing
fittings)
- Dissimilar metals
- Breakdown of soft goods due to compatibility issues with
transported commodity
- Valve vault or valve can contributed to the release
- Alarm/status failure
- Misalignment
- Thermal stress
Page 13 of 13
- Other
- If Other, Describe:
G7 - Incorrect Operation - only one sub-cause can be selected from the shaded left-hand column
Incorrect Operation Sub-Cause:
- If Tank, Vessel, or Sump/Separator Allowed or Caused to Overfill or Overflow:
1. Specify:
- If Other, Describe:
- If Other Incorrect Operation:
2. Describe:
Complete the following if any Incorrect Operation sub-cause is selected.
3. Was this Accident related to (select all that apply): -
- Inadequate procedure
- No procedure established
- Failure to follow procedure
- Other:
- If Other, Describe:
4. What category type was the activity that caused the Accident?
5. Was the task(s) that led to the Accident identified as a covered task
in your Operator Qualification Program?
5a. If Yes, were the individuals performing the task(s) qualified for
the task(s)?
G8 - Other Accident Cause -
only one sub-cause can be selected from the shaded left-hand column
Other Accident Cause Sub-Cause:
- If Miscellaneous:
1. Describe:
- If Unknown:
2. Specify:
PART H - NARRATIVE DESCRIPTION OF THE ACCIDENT
Lion Oil called Sunoco Control Room to initiate a delivery to Mid-Valley Pipeline at Longview Station. Sunoco Control Center advised Lion that when MVPL
personnel completed the line up for delivery, Sunoco CC would advise Lion to start delivery.
Lion appears to have started actions for the delivery prior to being notified by Sunoco CC that line up was complete.
This resulted in a higher than normal line pressure at the Longview Station manifold yet the pressure was within the design limits. This higher pressure
appears to have caused the failure at the point where internal corrosion had occurred.
File Full Name
PART I - PREPARER AND AUTHORIZED SIGNATURE
Preparer's Name Kenneth David Born
Preparer's Title Area DOT Compliance Supervisor
Preparer's Telephone Number 281-637-6497
Preparer's E-mail Address [email protected]
Preparer's Facsimile Number 281-637-6425
Authorized Signature's Name Kenneth David Born
Authorized Signature Title Area DOT Compliance Supervisor
Authorized Signature Telephone Number 281-637-6497
Authorized Signature Email [email protected]
Date 05/12/2010
Appendix C Operator and System Maps
Appendix D Failure Site Photos
Figure 1 Leak site
Leak Site
Figure 2 Exposed view of leak site
Figure 3 Close up View of Internal Corrosion
Figure 4 Removed pipe split open Internal and External Views