Rail delay compensation claims
2019-20 rail periods 5-7 (21 July 2019 to 12 October 2019)
Publication date: 9 January 2020
Next publication date: 2 April 2020
Background
This factsheet contains information on
delay compensation claims made by
passengers on rail services in Great
Britain. These statistics contain:
Delay compensation claim volumes
(received and closed per rail period);
The response rate of those claims
closed;
The volume of those claims closed
which were approved.
Train operators have a target to process
delay compensation claims within one
month of receipt. This is specified in
condition 33.2 of the National Rail
Conditions of Travel (NRCoT).
Definitions
Volume of claims closed:
The claim is closed when the train
operator issues payment for a
successful claim or when the passenger
was informed that their claim was
rejected. These statistics include claims
made by passengers, regardless of train
operator delay compensation scheme.
Claims closed within 20 working days
(percentage): ORR use 20 working
days as a proxy for the one month target
referred to in the NRCoT.
Volume of claims approved:
The volume of delay compensation
claims closed where the passengers
claim has been successful and
approved.
Responsible Statistician: Ben Hubbard
Public Enquiries: E-mail: [email protected] Media Enquiries: Tel: 0207 282 2094
Website: https://dataportal.orr.gov.uk/
Between 21 July and 12 October 2019
(2019-20 rail periods 5 to 7):
There were 1.4 million delay
compensation claims closed by train operators.
This is an increase of 13.2% from 1.3 million claims
during the same three rail periods in 2018-19.
This is primarily due to changes in delay
compensation schemes for some train operators
since last year, which has meant more passengers
are eligible for delay compensation.
Overall, 98.0% of delay compensation claims were
closed within 20 working days.
This is an increase of 2.7 percentage points from the
same three rail periods in 2018-19.
16 out of 23 train operators either increased or
maintained their response rate within 20 working days
compared to the same three rail periods in 2018-
19.
Of these claims closed, 84.5% of claims were
approved by train operators.
This is an increase of 2.1 percentage points from the
same three rail periods in 2018-19.
Effects of delay compensation scheme changes on claim volumes:
A major reason for the 13.2% increase in delay compensation claims between rail periods 5 to 7
2019-20 compared to the previous year is due to a number of train operators switching to the
Delay Repay 15 (DR 15) compensation scheme during the last year. The switch to DR 15 means
the threshold to claim compensation is lower (15 minutes), where previously it was 30 minutes in
most cases, so therefore more passengers are eligible to claim delay compensation.
The table below shows that for the six operators that have changed to a DR 15 delay
compensation scheme in 2019-20, all these operators have shown an increase in the volume of
claims closed. Overall, these six operators account for an increase of 139,577 claims closed
between the same three rail periods in 2018-19 and 2019-20. This increase is despite most of
these operators seeing an increased train performance in 2019-20 Q2 compared to the same
quarter last year (see the
* = East Midlands Railway and Southeastern changed to DR 15 during 2019-20 rail period 6.
** = Great Western Railway now operates DR 15 with some season tickets on a traditional charter scheme.
*** = Transport for Wales Rail was operating as Arriva Trains Wales during 2018-19 rail periods 5 to 7.
Response rate to claims closed:
Nationally, 98.0% of delay
compensation claims were
closed within 20 working
days in 2019-20 during rail
periods 5 to 7. There were
15 train operators which
closed more than the
national average within 20
working days.
There were 16 out of the 23
train operators which either
increased or maintained
their response rate within 20
working days compared to
the same three rail periods
in 2018-19, with 7 operators
having a lower response
rate compared to the same
rail periods last year.
Train operator
Volume of claims closed and
delay compensation scheme,
2019-20 rail periods 5 to 7
Volume of claims closed and
delay compensation scheme,
2018-19 rail periods 5 to 7
Volume increase
Southeastern 87,093 (DR 15*) 49,496 (DR 30) +37,597
Great Western Railway 71,380 (DR 15**) 40,446 (Traditional) +30,934
Greater Anglia 149,274 (DR 15) 125,846 (DR 30) +23,428
East Midlands Railway 37,789 (DR 15*) 16,152 (DR 30) +21,637
Northern 63,516 (DR 15) 50,006 (DR 30) +13,510
Transport for Wales Rail 17,179 (DR 15) 4,708 (Traditional***) +12,471
Passenger Rail Performancestatistical release for more information).
100.0%
100.0%
100.0%
100.0%
100.0%
100.0%
100.0%
100.0%
100.0%
100.0%
99.9%
99.9%
99.9%
99.6%
98.7%
97.2%
96.6%
96.3%
95.8%
93.1%
91.7%
90.8%
83.2%
0
1
0
0
0
0
0
0
0
33
0
1
49
0
6
7
66
1
-2
-3
-6
-1
-17
-300 -260 -220 -180 -140 -100 -60 -20 20 60
0 1 1 2 2
CrossCountry
Greater Anglia
Heathrow Express
London Overground
Merseyrail
ScotRail
Southeastern
TfL Rail
Govia Thameslink
Great Western Railway
c2c
South Western Railway
TransPennine Express
TfW Rail
West Midlands Trains
Grand Central
Hull Trains
Northern
Chiltern Railways
Virgin Trains West Coast
London North Eastern…
East Midlands Railway
Caledonian Sleeper
Delay compensation claims response
rate within 20 working days, 2019-20 rail
periods 5 to 7
Percentage point
change on 2018-19
periods 5 to 7
Delay compensation statistics by train operator,
2019-20 rail periods 5 to 7:
Delay compensation claims closed, percentage of claims approved, and response rate
within 20 working days by train operator, 2019-20 rail periods 5 to 7
Train operator
Delay compensation
scheme
Claims closed
Response within
20 working days
Percentage of
claims approved
c2c Delay Repay (DR 15) 4,666 99.9% 80.4%
Caledonian Sleeper Delay Repay (DR 30) 2,559 83.2% 95.7%
Chiltern Railways Traditional 5,096 95.8% 73.8%
CrossCountry Delay Repay (DR 30) 26,885 100.0% 94.5%
East Midlands Railway
1
Delay Repay (DR 15*) 37,789 90.8% 91.4%
Govia Thameslink Railway Delay Repay (DR 15) 320,546 100.0% 85.8%
Grand Central Traditional 3,803 97.2% 71.3%
Great Western Railway
2
Delay Repay (DR 15)* 71,380 100.0% 71.9%
Greater Anglia Delay Repay (DR 15) 149,274 100.0% 88.5%
Heathrow Express Delays of 15+ mins 1,157 100.0% 38.1%
Hull Trains Traditional 5,068 96.6% 97.0%
London North Eastern Railway Delay Repay (DR 30) 117,911 91.7% 85.9%
London Overground Traditional 3,911 100.0% 80.5%
Merseyrail Traditional 322 100.0% 98.4%
Northern Delay Repay (DR 15) 63,516 96.3% 80.4%
ScotRail Delay Repay (DR 30) 29,687 100.0% 83.6%
South Western Railway Delay Repay (DR 15) 158,249 99.9% 83.7%
Southeastern
3
Delay Repay (DR 15*) 87,093 100.0% 86.5%
TfL Rail Traditional 1,676 100.0% 88.5%
TfW Rail Delay Repay (DR 15) 17,179 99.6% 92.5%
TransPennine Express Delay Repay (DR 30) 50,323 99.9% 67.2%
Virgin Trains West Coast
4
Delay Repay (DR 30) 141,901 93.1% 86.0%
West Midlands Trains Delay Repay (DR 15) 116,975 98.7% 84.4%
Great Britain 1,416,966 98.0% 84.5%
Comparison of delay compensation claim volumes between train operators should be treated with
caution – This is due to different thresholds to claim compensation between each delay compensation
scheme and the different number of services for each train operator.
All tables associated with this release can be found under data tables on the passenger delay compensation
page of the ORR Data Portal. The figures presented in this release are provisional and subject to revision.
Note some train operators have changed delay compensation scheme since 2018-19 so some time
comparisons must be treated with caution.
For up-to-date information on the delay compensation scheme each train operator operates, please see the
individual train operators website or the National Rail Enquiries website. The following information is accurate
as far as ORR know at the time of publication.
Notes:
1). East Midlands Railway took over the East Midlands Trains franchise from 18 August 2019 (start of rail period 6).
From 18 August 2019 onwards, East Midlands Railway is operating the DR 15 scheme instead of DR 30.
2). Great Western Railway operates the DR 15 scheme with some season tickets on a traditional charter scheme.
3). From 11 September 2019 onwards, Southeastern is operating the DR 15 scheme instead of DR 30.
4). Avanti West Coast took over the Virgin Trains West Coast franchise from 8 December 2019 (start of rail period 10).
From 8 December 2019 onwards, Avanti West Coast will be operating the DR 15 scheme instead of DR 30.
5). c2c, Northern and Virgin Trains West Coast operate Automatic Delay Repay on some tickets, with other operators providing automated
Delay Repay: See the notes on page 4 for further details on these schemes.
Type of schemes: The most popular delay
compensation scheme is Delay Repay. Delay
Repay is a national scheme train operators use to
compensate passengers for delays. For those
operators using the Delay Repay scheme, all ticket
types are covered and passengers can make a
claim for delay compensation whatever the cause
of disruption. There are two types of Delay Repay
schemes available:
Delay Repay 30 (DR 30): Passengers can claim
compensation if the train is delayed by 30 minutes
or more. Passengers delayed between 30 and 59
minutes are entitled to 50% of the cost of a single
ticket, and if the passenger is delayed by 60
minutes or more, the passenger is entitled to a
100% refund of a single ticket. If delayed 120
minutes or more the passenger can claim the cost
of a return journey if they have a return ticket.
Delay Repay 15 (DR 15): Passengers can
additionally claim compensation if the train is
delayed by 15 minutes or more. DR 15 allows a
passenger to claim 25% of the cost of a single
ticket if they are delayed between 15 and 29
minutes. Eight train companies operated this
scheme from the beginning of 2019-20, with East
Midlands Railway, Southeastern and Avanti West
Coast moving to this scheme during 2019-20.
Other schemes (traditional schemes): A small
number of operators run other schemes which are
different to Delay Repay. Often these schemes
have different timeframes to be eligible, and
compensation can vary between each schemes.
Compensation may not be available if the delay is
caused by an event outside the operators control.
Frequently asked questions:
How are several claims on one form recorded?
If a passenger submitted several journeys on one
delay compensation form, then each journey is
counted as a claim.
Are discretionary compensation payments or
enhanced compensation claims included?
These statistics include claims for delays only, and
exclude discretionary compensation payments made
following complaints of poor service (for example,
compensation due to wi-fi not working). Some
operators may also provide enhanced or additional
compensation during periods of extended disruption,
but these claims are not included within these
statistics.
Are Automatic Delay Repay claims included?
Automatic Delay Repay is when a passenger is
automatically compensated when their journey is
delayed within the timescales to be eligible for
compensation. Northern and Virgin Trains West Coast
offer Automatic Delay Repay if the passenger has
booked through their website or app and has an
advance ticket. c2c offers eligible passengers with a
registered smartcard 3p back per minute for delays of
between two and fourteen minutes - These c2c
automatic compensation volumes are not included
within these statistics.
Are Automated Delay Repay claims included? A
number of operators now provide automated Delay
Repay where they automatically advise passengers
who use smartcards and/or buy advance tickets that
they may be eligible for compensation by generating a
delay repay claim for them. The passenger has to then
login to the system and confirm that the claim is
correct. Only claims which are confirmed by the
passenger are included within these statistics.
Other sources of delay compensation information:
ORR publish statistics on rail passenger complaints
which shows 8.3% of all complaints nationally were
about delay compensation schemes in 2018-19.
Furthermore, appeals to the Rail Ombudsman on delay
compensation schemes, such as appeals on claims
which are rejected or the claims process, are most
appealed complaint category.
The Department for Transport (DfT) publishes
compensation amounts paid by train operators to
passengers from 2009-10. The DfT figures are not
comparable to statistics given here due to the different
time periods involved, changes to delay compensation
schemes and franchises from previous years, and the
fact DfT figures include discretionary compensation
payments made following complaints of poor service.
Key findings from Department for Transport
research (March 2018) on Rail Delays and
Compensation
Compensation claims: The research showed only
39% of eligible passengers claimed for a 30 minute or
longer delay, and only 18% of eligible passengers
claimed for a 15 minute delay.
Satisfaction with speed of payment: 69% of
claimants were satisfied with the speed of payment.
Claim rate: The proportion of passengers claiming
compensation is strongly correlated to the price of
their ticket: 52% of passengers who paid over £40
claimed compensation, compared to 25% when the
ticket was £5 or less. The research also found the
longer the delay, the more likely the passenger is to
claim compensation.