Liquidated damages
637
Further, his Honour held that in order for such a clause to constitute an exhaustive
remedy for damages due to late completion, it would require clear words that the
liquidated damages clause was the entirety of the proprietor's rights because,
otherwise, the proprietor would be exposed to being left with no entitlement at all to
damages for delay. Thomas (2008: 88) cites this consideration of the Court as an
example of the Court taking into account commercial circumstance in the
interpretation of contractual wording.
His Honour, therefore, held that clause 10.14 was not an exhaustive agreement as to
the damages for delay thereby distinguishing Baese from Temloc.
In Silent Vector Pty Ltd t/a Sizer Builders v Squarcini [2008] WASC 246 (henceforth
"Squarcini") the Supreme Court of Western Australia upheld an arbitrator’s decision
that the insertion "N/A" (presumably an abbreviation of "Not Applicable") in the LD
clause, although clearly excluding a right to recover LD, did nothing to exclude the
recovery of ULD for losses incurred by the employer. The Court held that it was not
convinced that this insertion meant that the parties intended that no damages at all
were to be recoverable for delay
In Squarcini, the parties used the Australian Standard General Conditions of Contract
AS2124-1992, cl 35.6 of which states:
If the Contractor fails to reach Practical Completion by the Date for Practical
Completion, the Contractor shall be indebted to the Principal for liquidated damages
at the rate stated in the Annexure for every day after the Date for Practical Completion
to and including the Date of Practical Completion or the date that the Contract is
terminated under Clause 44, whichever first occurs.
The question as to whether this clause represented a mandatory LD provision or not,
and thereby constituted an exhaustive remedy for damages due to late completion, was
not considered by the arbitrator. The Court, however, did not deem this to be
sufficient to disturb the arbitrator’s original decision on the basis of an error of law,
considering it sufficient that “the learned arbitrator's reasoning was based on the facts,
particularly the express terms of the Contract and the surrounding facts, such as they
were known to the learned arbitrator” (para 83).
The Court’s endorsement of the basis for the arbitrator’s reasoning in Squarcini
indicates a move towards a contextual approach to interpreting LD clauses in
Australia, which has been subsequently further developed in J-Corp Pty Ltd. v
Mladenis [2009] WASCA 157 (henceforth "J-Corp").
In J-Corp, a builder (J-Corp) entered into a building contract with an employer
(Mladenis) to construct a three storey house for the sum of A$311,484.12. The
Contract was a standard form used by J-Corp. Clause 11.9 of the Contract provided
that if the Builder failed to reach practical completion by the due date ‘it shall be
liable to pay the Proprietor liquidated damages at the rate of NIL DOLLARS ($00.00)
per day for each day beyond the due date for practical completion until practical
completion is deemed to have taken place’.
J-Corp did not reach practical completion within the specified period and the
employer sought to recover ULD as a result of the delay. J-Corp (citing the English
case of Temloc as authority) argued that the insertion of $NIL DOLLARS in the LD
clause excluded both LD and ULD. The Court of first instance rejected J-Corp's
argument. J-Corp appealed.