Renewable Energy Financing Schemes for Indonesia
64
F. Sanctions and Incentives
. Bid bond of [e.g., ,] /MW would be required to participate in the
bidding process. This should be placed at the same time when submitting
the full proposal in the second RfP stage of the process.
. The bid bond should be in form of a standby letter of credit by a bank
located in Indonesia.
. The bidders who are not successful in the bidding process would have their
bid bonds released/cancelled after the award of the VGF to the successful
bidders.
. The winning bidders shall double this bid bond to [e.g., ,] /MW after
being awarded the top-up premium tari, before signing the premium tari
agreement with the VGF manager (similar to a PPA).
. The performance bond would be released/cancelled at COD and validation
of the actual generation capacity.
. In case the bidder withdraws from the process during the bidding or
implementation phase, the bid bond or completion bond, respectively, would
be claimed by the VGF fund manager, as a sanction for the bidder in failing
to meet its obligations in the process.
. In case the project misses the COD set in the premium tari agreement
(the rules of calculating the COD deadline is clearly defined in the RfP
documentation already), the VGF manager will be able to claim part of the
completion bond on a daily basis until the delayed project achieves the
COD. The daily sanction would be [completion bond/]. Therefore, after
months the whole completion bond would be fully depleted.
. After months of delay from the agreed COD, the VGF manager would
have the right to terminate the premium tari agreement at its sole
discretion.
Peak load hours per annum 2,000.00
Annual generation, MWh/a 10,000.00
Cumulative generation, 10 years 100,000.00
Bid price for premium, $/MWh 5.00
Total funding request, $ 500,000.00
Peak load hours per annum 3,000.00
Annual generation, MWh/a 30,000.00
Cumulative generation, 10 years 300,000.00
Bid price for premium, $/MWh 10.00
Total funding request, $ 3,000,000.00
Peak load hours per annum 5,000.00
Annual generation, MWh/a 20,000.00
Cumulative generation, 10 years 200,000.00
Bid price for premium, $/MWh 15.00
Total funding request, $ 3,000,000.00
Project 3, Hydro 4 MW
Peak load hours per annum 6,000.00
Annual generation, MWh/a 18,000.00
Cumulative generation, 10 years 180,000.00
Bid price for premium, $/MWh 20.00
Total funding request, $ 3,600,000.00
Project 4, Hydro 3 MW
Figure 9: Illustrative Example of Bid Premium
Tari Levels in a Bidding Process
MW megawatt, MWh megawatt-hour, MWh/a megawatt hour per annum,
PV photovoltaic.
Source: ADB.