Termination for "material breach" – what
exactly is "material"?
Contracts for the international sale of goods
often contain provisions entitling one of the
parties to terminate the contract for “material
breach”. If the parties have expressly defined
what they mean by material breach, then this
should not give rise to much uncertainty if
the crunch comes, and one party wishes to
terminate. This article considers what
happens if “material breach” is left undefined,
as it is a question which we have been asked
by traders quite often in recent times.
As those familiar with English contract law will know,
a breach which goes to the root of the contract, or
deprives a party of substantially the whole benefit of
the contract, will entitle the innocent party to
terminate for what is known as repudiation. A
contractual right to terminate for “material breach”
allows the innocent party to terminate for a breach
which is not quite as serious as that. But where on
the sliding scale of seriousness does any particular
breach fall? The decision in Dalkia Utilities Services
PLC v Celtech International Limited [2006] EWHC 63
(“Dalkia”) contains some very helpful guidelines
about what constitutes a material breach.
Whether a breach is material is a question of fact.
Defined generally by the English High Court as a
breach that has “a serious effect on the benefit
which the innocent party would otherwise derive”
,
the common denominator in every case analysis is
that a material breach must be substantial.
1. Considerations in Dalkia v Celtech
The facts
The claimant, Dalkia Utilities Services Ltd, entered a
15-year contract to provide energy services to the
defendant, Celtech International Ltd. Payment under
Dalkia Utilities Services PLC v Celtech International Limited
[2006] EWHC 63 (“Dalkia”) at 99.
the contract was to be made in monthly instalments,
known collectively as the “Charges”.
The contract contained a clause that provided, “In
the event of the client (Celtech) being in material
breach of its obligations to pay the Charges, the
company shall have the right to terminate this
Agreement immediately.” There was also a clause
that made a Termination Sum payable by Celtech if
the contract ceased because of Celtech’s breach.
Celtech then failed to pay 3 monthly instalments
consecutively. Dalkia sought to terminate the
contract and claim a Termination Sum from Celtech.
Celtech argued that this failure to pay 3 monthly
instalments, out of over a hundred payments, was
not “material”. These non-payments, they claimed,
were small in proportion to the total amount
payable. The issue in this case was whether
Celtech’s non-payment of 3 monthly instalments in a
15-year contract amounted to a material breach of
the contract.
The decision
The High Court ruled in favour of the Claimant,
Dalkia. Celtech, having failed to pay three
consecutive monthly instalments, had committed a
material breach of its obligations to make payment
under the contract.
The total amount of the instalments combined was
“neither trivial nor minimal”
, as they formed a
quarter of the current year’s payments and Celtech
was on the brink of insolvency.
Christopher Clarke J laid down the following (non-
exhaustive) factors in assessing the materiality of a
breach
:
1. The nature of the contract and the specific
obligations involved;